Differences between revisions 52 and 191 (spanning 139 versions)
Revision 52 as of 2016-08-04 17:40:32
Size: 3422
Editor: MarkBarton
Comment:
Revision 191 as of 2017-09-15 13:27:49
Size: 3359
Editor: MarkBarton
Comment:
Deletions are marked like this. Additions are marked like this.
Line 5: Line 5:
 * Type B Past Week Summary
  * Akutsu-san provided a set of cleanroom gear (shoes only slightly too tight!) for use by Mark this week. (And Sakamoto-san sent two more sets from Kamioka to Kashiwa!)
  * Fabian did a fit test of the winches onto the IM.
  * The RM, IM and IRM were weighed, and wrapped/packed for shipment to Kamioka.
  * Mark made a checklist of all the parts of the BS mirror box and gluing jig, to help with collecting the parts from Kashiwa.
  * Mark, Fabian and Hirata-san retrieved the dummy BS and mirror box from Kashiwa.
  * Fabian designed an extra 600 g of trim masses for the IM and Hirata-san made drawings and ordered them. The design allows for the masses to be added to the IM even after it has been placed in the assembly frame and the dummy optic and RM have been hung, so it should not delay work.
  * Mark worked on the schedule, making the next few weeks more realistic and incorporating the new plan for the SR RMs (the test will be used for SR2 but two more will be made from scratch next financial year).
  * Fabian worked on the payload assembly procedure.
  * Hirata-san washed 7 OSEMs for Akutsu-san, and various other parts for Yamamoto-san of ICRR.
  * Hirata-san removed the remaining glue from the BS primary and secondary prisms, as well as the prisms removed from the PR hanging test mirror. (The small sapphire prisms for the PR were not intended to be reused and one had already broken at Kashiwa, but the metal PR secondaries can and will be used again.)
 
 * Type B ongoing issues
  * OSEMs
   * Akutsu-san is working to get wide-mouth OSEMs ([[http://klog.icrr.u-tokyo.ac.jp/osl/?r=1853|2 assembled]]; another few were assembled and a batch of 7 were washed.
  * Longer cables for BF->PI and SF->PI.
   * Connectors RECEIVED, cables being made.
  * Lower breadboard stuff
   * Installation to be incorporated into the procedure document. Mark/Takahashi to discuss.
  * Documents
   * BS Assembly Procedure [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]], [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]]
 * To-do list during Mark's vacation
  * Weigh IM/RM/IRM (Fabian, Hirata) - DONE
   * New trim mass - ORDERED.
  * Pack/ship IM/RM/IRM to Kamioka (Hirata/Fabian) - READY TO SHIP.
  * Analyze geophone data (Fabian/Shoda) - DONE.
  * Remove glue from dummy BS face (Fabian) - MOSTLY DONE.
  * Reglue flags and prisms (Tatsumi, Fabian) - from Friday 8/5.
  * Clean wire for BS and RM (Hirata) - DONE
  * Get new winch parts for new wire diameters - ORDERED, expected 8/5.
  * Do fit/function test of winches (Fabian/Hirata) - fit test DONE, function test from 8/8
  * Ship winches to Kamioka (Hirata/Fabian)
  * Work on BS simulation (Fabian)
  * Do Inventor assembly for SR2 in chamber and on assembly frame (Hirata) - ONGOING.
  * Write more of payload assembly procedure (Fabian) - ONGOING
  * Write more of main assembly procedure (Mark) - ONGOING
 * Longer term to-do list
  * Do BS Simulink model (Mark, Kokeyama)
  * Do 2D drawings of SR2 parts (Hirata)
  * Redesign SRx IM wire clamps for larger prisms, remachined RMs
  * Order SRM/PRM parts (Hirata/Shoda)
  * Order SRx fasteners (Hirata)
=== Type B (Mark) ===
==== Past week report ====
At Kamioka (Mark, Ohishi-san, Fabian, Enzo, Hirata-san, Yoshioka-kun, Kozu-kun):
 * We disconnected the SF/... section and reinstalled the F0-SF rod with the hex cable clamp attached.
 * We debugged an issue with the actuation (the real-time model needed rebooting).
 * We routed all the SF/... cables up to the bottom of the PI, and then to the feedthroughs.
 * We unlocked the F0 keystone and experimented to find the amount of mass needed on the SF (≈845 g).
 * We attached the SF trim mass, adjusting it laterally so that the SF was level in pitch and roll.
 * We corrected some errors on the MEDM screens (some broken links and Take/Restore Safe.snap buttons).
 * We cabled all the PI items through to the rack and did very basic testing.
 * We disconnected the security structure from the assembly frame and adjusted the PI till the SS was vertical.
 * We unlocked the IP and adjusted the PI jacks and FRs till the IP was centered.
 * We passed the halves of the LBB Cu damping ring (less the Cu) into the chamber and joined them.
 * We put the magnets on the LBB damper ring using the template.
 * We locked various combinations of keystones and measured the vertical resonance frequencies of the unlocked filters.
 * We spent time on getting the geophones working. The original descrambler adapters had gone missing, so Enzo created three new ones. We borrowed a cable to replace one that had broken. The geophone distributor (S1402167) failed (no power on the negative rail), and a replacement borrowed from SR3 (S1605513) kept switching off.

==== Plan for week of 9/19 ====
No work Mon 9/18 (敬老の日)<<BR>>
Mark, Fabian, Enzo, Ohishi-san, Hirata-san, Yoshioka-kun (Tue, Wed, Thu, Fri), Kozu-kun
 * Double check BS pitch with OL.
 * Adjust SF damper ring to correct gap.
 * Install lock nuts on F0 GAS FR at TBD positions.
 * Lock BF and F0 keystones (but ''not'' SF keystone).
 * Lock RM to BS and IRM to IM.
 * Lock RM, IRM and BF (but not SF) to security structure.
 * Lock IP.
 * Remove F0 keystone top plate (including yaw stepper) and immobilize SF/... in yaw.
 * Attach lifting fixture.
 * Remove BF- and SF-level crossbars.
 * Remove geophones for craning.
 * Disconnect in-vacuum cables from feedthrough and coil neatly for craning.
 * Attach lifting plates.
 * Attach Cu segments to LBB damper ring (needs Cu segments and BUMAX countersunk screws, expected 9/20).
 * Pass halves of LBB magnet ring into tank, join, and make sandwich for craning.
 * Crane tank lid off.
 * Crane LBB damper rings to top of tank and suspend.
 * Crane suspension out of assembly frame.
 * Attach LBB upper rods to LBB blade tips and rotate suspension 45° clockwise.
 * Crane suspension into tank and connect upper rods to LBB Cu ring.
 * Unclamp LBB ring "sandwich" so LBB Cu ring is suspended on upper rods.
 * Install LBB lower rods and hook LBB.
 * Measure required ballast for LBB.
 * Unlock suspension and readjust.
 * Move in-air cabling and feedthroughs and reconnect in-vacuum cables (through Cu O-rings).

==== Plan for week of 9/25 ====
TBD

 * Debug cabling.
 * Run TFs.
 * Install LSOL?

==== Vacation Info ====
Mark: 10/16-24

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Past week report

At Kamioka (Mark, Ohishi-san, Fabian, Enzo, Hirata-san, Yoshioka-kun, Kozu-kun):

  • We disconnected the SF/... section and reinstalled the F0-SF rod with the hex cable clamp attached.
  • We debugged an issue with the actuation (the real-time model needed rebooting).
  • We routed all the SF/... cables up to the bottom of the PI, and then to the feedthroughs.
  • We unlocked the F0 keystone and experimented to find the amount of mass needed on the SF (≈845 g).
  • We attached the SF trim mass, adjusting it laterally so that the SF was level in pitch and roll.
  • We corrected some errors on the MEDM screens (some broken links and Take/Restore Safe.snap buttons).
  • We cabled all the PI items through to the rack and did very basic testing.
  • We disconnected the security structure from the assembly frame and adjusted the PI till the SS was vertical.
  • We unlocked the IP and adjusted the PI jacks and FRs till the IP was centered.
  • We passed the halves of the LBB Cu damping ring (less the Cu) into the chamber and joined them.
  • We put the magnets on the LBB damper ring using the template.
  • We locked various combinations of keystones and measured the vertical resonance frequencies of the unlocked filters.
  • We spent time on getting the geophones working. The original descrambler adapters had gone missing, so Enzo created three new ones. We borrowed a cable to replace one that had broken. The geophone distributor (S1402167) failed (no power on the negative rail), and a replacement borrowed from SR3 (S1605513) kept switching off.

Plan for week of 9/19

No work Mon 9/18 (敬老の日)
Mark, Fabian, Enzo, Ohishi-san, Hirata-san, Yoshioka-kun (Tue, Wed, Thu, Fri), Kozu-kun

  • Double check BS pitch with OL.
  • Adjust SF damper ring to correct gap.
  • Install lock nuts on F0 GAS FR at TBD positions.
  • Lock BF and F0 keystones (but not SF keystone).

  • Lock RM to BS and IRM to IM.
  • Lock RM, IRM and BF (but not SF) to security structure.
  • Lock IP.
  • Remove F0 keystone top plate (including yaw stepper) and immobilize SF/... in yaw.
  • Attach lifting fixture.
  • Remove BF- and SF-level crossbars.
  • Remove geophones for craning.
  • Disconnect in-vacuum cables from feedthrough and coil neatly for craning.
  • Attach lifting plates.
  • Attach Cu segments to LBB damper ring (needs Cu segments and BUMAX countersunk screws, expected 9/20).
  • Pass halves of LBB magnet ring into tank, join, and make sandwich for craning.
  • Crane tank lid off.
  • Crane LBB damper rings to top of tank and suspend.
  • Crane suspension out of assembly frame.
  • Attach LBB upper rods to LBB blade tips and rotate suspension 45° clockwise.
  • Crane suspension into tank and connect upper rods to LBB Cu ring.
  • Unclamp LBB ring "sandwich" so LBB Cu ring is suspended on upper rods.
  • Install LBB lower rods and hook LBB.
  • Measure required ballast for LBB.
  • Unlock suspension and readjust.
  • Move in-air cabling and feedthroughs and reconnect in-vacuum cables (through Cu O-rings).

Plan for week of 9/25

TBD

  • Debug cabling.
  • Run TFs.
  • Install LSOL?

Vacation Info

Mark: 10/16-24

KAGRA/Subgroups/VIS/TypeB/Minutes (last edited 2022-10-28 10:02:46 by fabian.arellano)