Differences between revisions 52 and 224 (spanning 172 versions)
Revision 52 as of 2016-08-04 17:40:32
Size: 3422
Editor: MarkBarton
Comment:
Revision 224 as of 2018-02-02 09:34:57
Size: 2165
Editor: MarkBarton
Comment:
Deletions are marked like this. Additions are marked like this.
Line 5: Line 5:
 * Type B Past Week Summary
  * Akutsu-san provided a set of cleanroom gear (shoes only slightly too tight!) for use by Mark this week. (And Sakamoto-san sent two more sets from Kamioka to Kashiwa!)
  * Fabian did a fit test of the winches onto the IM.
  * The RM, IM and IRM were weighed, and wrapped/packed for shipment to Kamioka.
  * Mark made a checklist of all the parts of the BS mirror box and gluing jig, to help with collecting the parts from Kashiwa.
  * Mark, Fabian and Hirata-san retrieved the dummy BS and mirror box from Kashiwa.
  * Fabian designed an extra 600 g of trim masses for the IM and Hirata-san made drawings and ordered them. The design allows for the masses to be added to the IM even after it has been placed in the assembly frame and the dummy optic and RM have been hung, so it should not delay work.
  * Mark worked on the schedule, making the next few weeks more realistic and incorporating the new plan for the SR RMs (the test will be used for SR2 but two more will be made from scratch next financial year).
  * Fabian worked on the payload assembly procedure.
  * Hirata-san washed 7 OSEMs for Akutsu-san, and various other parts for Yamamoto-san of ICRR.
  * Hirata-san removed the remaining glue from the BS primary and secondary prisms, as well as the prisms removed from the PR hanging test mirror. (The small sapphire prisms for the PR were not intended to be reused and one had already broken at Kashiwa, but the metal PR secondaries can and will be used again.)
=== Type B (Mark) ===
==== Report for week of 1/29 ====
 * We moved the top filter intended for SR2 (#1) into the SR3 cleanbooth.
 * Unfortunately we noticed one of the blades had many small X-shaped stress fractures on the top surface (klog [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=4058|4058]]).
 * We moved the top filter entered for SR3 (#3) into the SRM cleanbooth and inspected the blades. Two had one smallish stress fracture each and one had a huge fracture and looks close to failing (klog [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=4061|4061]]).
 * We referred the BS OL.
 * We removed the BS tank lid and inspected the BS top filter blades. They seemed fine.
 * Hirata-san received and washed some ferromagnetic disks for IM flags and other small parts.
 * Hirata-san moved the BF with the tilted keystone (#1) out of the cleanbooth in preparation for rebuilding.
 * Hirata-san placed the second order for payload parts, and an order for remachining of nuts for cable clamps on rods.
 * Fabian measured the gain of the ADC system (homework from the Commissioning Workshop).
Line 17: Line 17:
 * Type B ongoing issues
  * OSEMs
   * Akutsu-san is working to get wide-mouth OSEMs ([[http://klog.icrr.u-tokyo.ac.jp/osl/?r=1853|2 assembled]]; another few were assembled and a batch of 7 were washed.
  * Longer cables for BF->PI and SF->PI.
   * Connectors RECEIVED, cables being made.
  * Lower breadboard stuff
   * Installation to be incorporated into the procedure document. Mark/Takahashi to discuss.
  * Documents
   * BS Assembly Procedure [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]], [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]]
 * To-do list during Mark's vacation
  * Weigh IM/RM/IRM (Fabian, Hirata) - DONE
   * New trim mass - ORDERED.
  * Pack/ship IM/RM/IRM to Kamioka (Hirata/Fabian) - READY TO SHIP.
  * Analyze geophone data (Fabian/Shoda) - DONE.
  * Remove glue from dummy BS face (Fabian) - MOSTLY DONE.
  * Reglue flags and prisms (Tatsumi, Fabian) - from Friday 8/5.
  * Clean wire for BS and RM (Hirata) - DONE
  * Get new winch parts for new wire diameters - ORDERED, expected 8/5.
  * Do fit/function test of winches (Fabian/Hirata) - fit test DONE, function test from 8/8
  * Ship winches to Kamioka (Hirata/Fabian)
  * Work on BS simulation (Fabian)
  * Do Inventor assembly for SR2 in chamber and on assembly frame (Hirata) - ONGOING.
  * Write more of payload assembly procedure (Fabian) - ONGOING
  * Write more of main assembly procedure (Mark) - ONGOING
 * Longer term to-do list
  * Do BS Simulink model (Mark, Kokeyama)
  * Do 2D drawings of SR2 parts (Hirata)
  * Redesign SRx IM wire clamps for larger prisms, remachined RMs
  * Order SRM/PRM parts (Hirata/Shoda)
  * Order SRx fasteners (Hirata)

==== Plan for week of 1/29 ====
 * Enzo at Mitaka 1/29 and most of 1/30, then vacation.
 * Kozu-kun away.
 * All others at Kamioka.
 * Make in-air pico adapter cables.
 * Test IM picos and BF yaw pico.
 * Test FR.
 * Calibrate LVDT.
 * Get screws for ballast mass from Takahashi-san.
 * Install ballast mass in BF.
 * Set up for F0 test.
  * Lower IM crossbars in SR3 assembly frame.
  * Open curtain on SR3 crane slot.
  * Set up dummy load (weight carrier, rods etc).
 * Do F0 test.
  * Bring in F0.
  * Hook up dummy load.
  * Adjust dummy load.

==== Plan for week of 2/5 ====
 * Enzo on vacation; all others at Kamioka.
 * Build IRM around IM.
 * Cable/test/adjust IM OSEMs.
 * Time permitting, do TFs from IM OSEMs to themselves and to optical sensor.

==== Plan for week of 2/12 ====
 * Enzo on vacation; all others at Kamioka.

==== Vacation Info ====
 * Enzo 1/30-2/19 (at Mitaka 1/29, part of 1/30)
 * Kozu-kun 1/29-2/2

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Report for week of 1/29

  • We moved the top filter intended for SR2 (#1) into the SR3 cleanbooth.
  • Unfortunately we noticed one of the blades had many small X-shaped stress fractures on the top surface (klog 4058).

  • We moved the top filter entered for SR3 (#3) into the SRM cleanbooth and inspected the blades. Two had one smallish stress fracture each and one had a huge fracture and looks close to failing (klog 4061).

  • We referred the BS OL.
  • We removed the BS tank lid and inspected the BS top filter blades. They seemed fine.
  • Hirata-san received and washed some ferromagnetic disks for IM flags and other small parts.
  • Hirata-san moved the BF with the tilted keystone (#1) out of the cleanbooth in preparation for rebuilding.
  • Hirata-san placed the second order for payload parts, and an order for remachining of nuts for cable clamps on rods.
  • Fabian measured the gain of the ADC system (homework from the Commissioning Workshop).

Plan for week of 1/29

  • Enzo at Mitaka 1/29 and most of 1/30, then vacation.
  • Kozu-kun away.
  • All others at Kamioka.
  • Make in-air pico adapter cables.
  • Test IM picos and BF yaw pico.
  • Test FR.
  • Calibrate LVDT.
  • Get screws for ballast mass from Takahashi-san.
  • Install ballast mass in BF.
  • Set up for F0 test.
    • Lower IM crossbars in SR3 assembly frame.
    • Open curtain on SR3 crane slot.
    • Set up dummy load (weight carrier, rods etc).
  • Do F0 test.
    • Bring in F0.
    • Hook up dummy load.
    • Adjust dummy load.

Plan for week of 2/5

  • Enzo on vacation; all others at Kamioka.
  • Build IRM around IM.
  • Cable/test/adjust IM OSEMs.
  • Time permitting, do TFs from IM OSEMs to themselves and to optical sensor.

Plan for week of 2/12

  • Enzo on vacation; all others at Kamioka.

Vacation Info

  • Enzo 1/30-2/19 (at Mitaka 1/29, part of 1/30)
  • Kozu-kun 1/29-2/2

KAGRA/Subgroups/VIS/TypeB/Minutes (last edited 2022-10-28 10:02:46 by fabian.arellano)