Differences between revisions 52 and 89 (spanning 37 versions)
Revision 52 as of 2016-08-04 17:40:32
Size: 3422
Editor: MarkBarton
Comment:
Revision 89 as of 2016-12-02 10:14:25
Size: 1356
Editor: MarkBarton
Comment:
Deletions are marked like this. Additions are marked like this.
Line 6: Line 6:
  * Akutsu-san provided a set of cleanroom gear (shoes only slightly too tight!) for use by Mark this week. (And Sakamoto-san sent two more sets from Kamioka to Kashiwa!)
  * Fabian did a fit test of the winches onto the IM.
  * The RM, IM and IRM were weighed, and wrapped/packed for shipment to Kamioka.
  * Mark made a checklist of all the parts of the BS mirror box and gluing jig, to help with collecting the parts from Kashiwa.
  * Mark, Fabian and Hirata-san retrieved the dummy BS and mirror box from Kashiwa.
  * Fabian designed an extra 600 g of trim masses for the IM and Hirata-san made drawings and ordered them. The design allows for the masses to be added to the IM even after it has been placed in the assembly frame and the dummy optic and RM have been hung, so it should not delay work.
  * Mark worked on the schedule, making the next few weeks more realistic and incorporating the new plan for the SR RMs (the test will be used for SR2 but two more will be made from scratch next financial year).
  * Fabian worked on the payload assembly procedure.
  * Hirata-san washed 7 OSEMs for Akutsu-san, and various other parts for Yamamoto-san of ICRR.
  * Hirata-san removed the remaining glue from the BS primary and secondary prisms, as well as the prisms removed from the PR hanging test mirror. (The small sapphire prisms for the PR were not intended to be reused and one had already broken at Kashiwa, but the metal PR secondaries can and will be used again.)
 
 * Type B ongoing issues
  * OSEMs
   * Akutsu-san is working to get wide-mouth OSEMs ([[http://klog.icrr.u-tokyo.ac.jp/osl/?r=1853|2 assembled]]; another few were assembled and a batch of 7 were washed.
  * Longer cables for BF->PI and SF->PI.
   * Connectors RECEIVED, cables being made.
  * Lower breadboard stuff
   * Installation to be incorporated into the procedure document. Mark/Takahashi to discuss.
  * Documents
   * BS Assembly Procedure [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]], [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]]
 * To-do list during Mark's vacation
  * Weigh IM/RM/IRM (Fabian, Hirata) - DONE
   * New trim mass - ORDERED.
  * Pack/ship IM/RM/IRM to Kamioka (Hirata/Fabian) - READY TO SHIP.
  * Analyze geophone data (Fabian/Shoda) - DONE.
  * Remove glue from dummy BS face (Fabian) - MOSTLY DONE.
  * Reglue flags and prisms (Tatsumi, Fabian) - from Friday 8/5.
  * Clean wire for BS and RM (Hirata) - DONE
  * Get new winch parts for new wire diameters - ORDERED, expected 8/5.
  * Do fit/function test of winches (Fabian/Hirata) - fit test DONE, function test from 8/8
  * Ship winches to Kamioka (Hirata/Fabian)
  * Work on BS simulation (Fabian)
  * Do Inventor assembly for SR2 in chamber and on assembly frame (Hirata) - ONGOING.
  * Write more of payload assembly procedure (Fabian) - ONGOING
  * Write more of main assembly procedure (Mark) - ONGOING
 * Longer term to-do list
  * Do BS Simulink model (Mark, Kokeyama)
  * Do 2D drawings of SR2 parts (Hirata)
  * Redesign SRx IM wire clamps for larger prisms, remachined RMs
  * Order SRM/PRM parts (Hirata/Shoda)
  * Order SRx fasteners (Hirata)
  * Mark worked on task lists and schedule.
  * Mark worked on an update of the BS Electronic Items doc ([[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5111|E1505111]]) and started a SRx Electronics Items doc ([[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5886|E1605886]]).
  * Mark worked on an update of the In-Vacuum Cable doc ([[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=3901|E1503901]]), including information on final lengths that Fabian and Hirata-san had decided when making adapter cables.
  * Mark considered an alternative cabling scheme for the geophones (with a different adapter cable to put the signals and power on different lines and a matching unscrambler) but ended up concluding that the existing design would probably be OK.
  * Fabian worked on a redesign of the EQ stops for the BS (2 of 4 screws under the RM are opposite large holes and there are no screws to restrain the RM front/back at either top or bottom).
  * Hirata-san worked on PR/SR mirror box modifications with Shoda-san (on-going).
  * Hirata-san partially assembled a bottom filter for use in fit tests of the PRx BF recoil mass.

  

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

  • Type B Past Week Summary
    • Mark worked on task lists and schedule.
    • Mark worked on an update of the BS Electronic Items doc (E1505111) and started a SRx Electronics Items doc (E1605886).

    • Mark worked on an update of the In-Vacuum Cable doc (E1503901), including information on final lengths that Fabian and Hirata-san had decided when making adapter cables.

    • Mark considered an alternative cabling scheme for the geophones (with a different adapter cable to put the signals and power on different lines and a matching unscrambler) but ended up concluding that the existing design would probably be OK.
    • Fabian worked on a redesign of the EQ stops for the BS (2 of 4 screws under the RM are opposite large holes and there are no screws to restrain the RM front/back at either top or bottom).
    • Hirata-san worked on PR/SR mirror box modifications with Shoda-san (on-going).
    • Hirata-san partially assembled a bottom filter for use in fit tests of the PRx BF recoil mass.

KAGRA/Subgroups/VIS/TypeB/Minutes (last edited 2022-10-28 10:02:46 by fabian.arellano)