 * Type B Past Week Summary
  * Mark, Fabian and Hirata-san cleaned glue off the dummy BS, attached Akutsu-san's new SS mirror plates, reglued the flags and prisms, and removed the gluing hardware, so the dummy BS is ready for shipping. Tatsumi-san's refinements to the tooling (especially the new flag holders) worked very smoothly. We were more generous with the glue and much more careful with the alignment of the prisms to the barrel, both during rehearsal and the final gluing.
  * Mark wrote up the gluing procedure as a new document [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5505| E1605505]]. (The original plan was to do an addendum to Tatsumi-san's PR gluing procedure JGW-E1504248, but there was too much material.)
  * Hirata-san organized with Takahashi-san to get the BS payload masses shipped to Kamioka. They will go in an air-ride truck on Wed 8/17 together with a load of Type A stuff, and will arrive early on Thu 8/17.
  * The RM, IM and IRM were weighed, and wrapped/packed for shipment to Kamioka.
  * Mark made a checklist of all the parts of the BS mirror box and gluing jig, to help with collecting the parts from Kashiwa.
  * Mark, Fabian and Hirata-san retrieved the dummy BS and mirror box from Kashiwa.
  * Fabian designed an extra 600 g of trim masses for the IM and Hirata-san made drawings and ordered them. The design allows for the masses to be added to the IM even after it has been placed in the assembly frame and the dummy optic and RM have been hung, so it should not delay work.
  * Mark worked on the schedule, making the next few weeks more realistic and incorporating the new plan for the SR RMs (the test will be used for SR2 but two more will be made from scratch next financial year).
  * Fabian worked on the payload assembly procedure.
  * Hirata-san washed 7 OSEMs for Akutsu-san, and various other parts for Yamamoto-san of ICRR.
  * Hirata-san removed the remaining glue from the BS primary and secondary prisms, as well as the prisms removed from the PR hanging test mirror. (The small sapphire prisms for the PR were not intended to be reused and one had already broken at Kashiwa, but the metal PR secondaries can and will be used again.)
=== Type B (Mark) ===
==== Past week report ====
At Kamioka (Mark, Ohishi-san, Fabian, Enzo, Hirata-san, Kozu-kun):
 * We couldn't account for a bubble level, so we removed a service port cover, searched again on top of the BF and found it.
 * We put the table KOACH filters on the table. Ohishi-san then removed the FC in two stages (AR side on Tue, HR side on Fri).
 * Ohishi-san measured the height of the SS and optic relative to the tank and found the optic was 3 mm low but the SS was 2 mm high. According to the GAS LVDTs, the suspension had not sagged but was 1.7 mm high.
 * Therefore we raised the suspension by 9 quarter-turns of the tank jacks (4.5 mm) so that the optic would be in the right position after (future) downward adjustment of the GAS filters.
 * We put the GAS LVDT calibration data as offsets and gains in the LVDTINF filters so the output would be height in µm relative to nominal.
 * We calibrated the IP LVDTs. We had worked around a mechanical interference due to the poor design of the old LVDTs by setting them to be 4 mm off-center with the IP locked centrally, but we discovered this was overkill and we have lost some linear range on the LVDT sensor in the opposite direction. If we have time we may move the LVDT bases 1-2 mm to a compromise position.
 * We worked with Simon to get the OL aligned and to learn the adjustment procedure.
 * Mark updated Sekiguchi-san's SUMCON to allow for comments to be entered next to all values (75% finished).
 * Kozu-kun worked on deriving the diagonalization matrices for the IP FRs.
Line 18: Line 18:
 * Type B ongoing issues
  * OSEMs
   * Akutsu-san is working to get wide-mouth OSEMs ([[http://klog.icrr.u-tokyo.ac.jp/osl/?r=1853|2 assembled]]; another few were assembled and a batch of 7 were washed.
  * Longer cables for BF->PI and SF->PI.
   * Connectors RECEIVED, cables being made.
  * Lower breadboard stuff
   * Installation to be incorporated into the procedure document. Mark/Takahashi to discuss.
  * Documents
   * BS Assembly Procedure [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]], [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]]
 * To-do list during Mark's vacation
  * Weigh IM/RM/IRM (Fabian, Hirata) - DONE
   * New trim mass - ORDERED.
  * Pack/ship IM/RM/IRM to Kamioka (Hirata/Fabian) - READY TO SHIP.
  * Analyze geophone data (Fabian/Shoda) - DONE.
  * Remove glue from dummy BS face (Fabian) - MOSTLY DONE.
  * Reglue flags and prisms (Tatsumi, Fabian) - from Friday 8/5.
  * Clean wire for BS and RM (Hirata) - DONE
  * Get new winch parts for new wire diameters - ORDERED, expected 8/5.
  * Do fit/function test of winches (Fabian/Hirata) - fit test DONE, function test from 8/8
  * Ship winches to Kamioka (Hirata/Fabian)
  * Work on BS simulation (Fabian)
  * Do Inventor assembly for SR2 in chamber and on assembly frame (Hirata) - ONGOING.
  * Write more of payload assembly procedure (Fabian) - ONGOING
  * Write more of main assembly procedure (Mark) - ONGOING
 * Longer term to-do list
  * Do BS Simulink model (Mark, Kokeyama)
  * Do 2D drawings of SR2 parts (Hirata)
  * Redesign SRx IM wire clamps for larger prisms, remachined RMs
  * Order SRM/PRM parts (Hirata/Shoda)
  * Order SRx fasteners (Hirata)
At Mitaka (Hirata-san):
 * Hirata-san met with manufacturers and requested quotes.
 * Hirata-san made many assembly drawings for sections of the SR.
 * Hirata-san worked on compiling the SR inventory.

==== Plan for week of 10/16 ====
Kamioka: all but Mark
 * Remove sticker residue and permanent marker writing on PI.
 * Fix broken and unreliable connections on IP LVDTs.
 * Wipe any rust from around IP LVDTs.
 * (If Enzo thinks it necessary and there's time) adjust IP LVDT mechanical offsets to maximize usable range and recalibrate.
 * Add IP LVDT gains and offsets to IP_LVDTINF filter blocks.
 * Calibrate IP LVDT actuation against IP LVDT sensing.
 * Install damping filters for IP LVDTs.
 * Adjust gains and debug damping for IM OSEMs and GAS LVDTs.
 * Modify IP LVDT damping filters to include set point.
 * Install and debug IP LVDT and geophone diagonalization matrices.
 * (Time permitting) Try adding mass to IP.
 * Work with alignment team.
 * Work with Mirapro on SR LBB and tank installation (Hirata-san, from Wed)
 * Work with Miyo-kun to get user interface for stepper motors.
 * Calibrate IP FR actuation against IP LVDT sensing.
 * SR procurement.

==== Vacation Info ====
Mark: 10/16-24

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Past week report

At Kamioka (Mark, Ohishi-san, Fabian, Enzo, Hirata-san, Kozu-kun):

  • We couldn't account for a bubble level, so we removed a service port cover, searched again on top of the BF and found it.
  • We put the table KOACH filters on the table. Ohishi-san then removed the FC in two stages (AR side on Tue, HR side on Fri).
  • Ohishi-san measured the height of the SS and optic relative to the tank and found the optic was 3 mm low but the SS was 2 mm high. According to the GAS LVDTs, the suspension had not sagged but was 1.7 mm high.
  • Therefore we raised the suspension by 9 quarter-turns of the tank jacks (4.5 mm) so that the optic would be in the right position after (future) downward adjustment of the GAS filters.
  • We put the GAS LVDT calibration data as offsets and gains in the LVDTINF filters so the output would be height in µm relative to nominal.
  • We calibrated the IP LVDTs. We had worked around a mechanical interference due to the poor design of the old LVDTs by setting them to be 4 mm off-center with the IP locked centrally, but we discovered this was overkill and we have lost some linear range on the LVDT sensor in the opposite direction. If we have time we may move the LVDT bases 1-2 mm to a compromise position.
  • We worked with Simon to get the OL aligned and to learn the adjustment procedure.
  • Mark updated Sekiguchi-san's SUMCON to allow for comments to be entered next to all values (75% finished).
  • Kozu-kun worked on deriving the diagonalization matrices for the IP FRs.

At Mitaka (Hirata-san):

  • Hirata-san met with manufacturers and requested quotes.
  • Hirata-san made many assembly drawings for sections of the SR.
  • Hirata-san worked on compiling the SR inventory.

Plan for week of 10/16

Kamioka: all but Mark

  • Remove sticker residue and permanent marker writing on PI.
  • Fix broken and unreliable connections on IP LVDTs.
  • Wipe any rust from around IP LVDTs.
  • (If Enzo thinks it necessary and there's time) adjust IP LVDT mechanical offsets to maximize usable range and recalibrate.
  • Add IP LVDT gains and offsets to IP_LVDTINF filter blocks.
  • Calibrate IP LVDT actuation against IP LVDT sensing.
  • Install damping filters for IP LVDTs.
  • Adjust gains and debug damping for IM OSEMs and GAS LVDTs.
  • Modify IP LVDT damping filters to include set point.
  • Install and debug IP LVDT and geophone diagonalization matrices.
  • (Time permitting) Try adding mass to IP.
  • Work with alignment team.
  • Work with Mirapro on SR LBB and tank installation (Hirata-san, from Wed)
  • Work with Miyo-kun to get user interface for stepper motors.
  • Calibrate IP FR actuation against IP LVDT sensing.
  • SR procurement.

Vacation Info

Mark: 10/16-24