 * Type B Past Week Summary
  * Mark, Fabian and Hirata-san cleaned glue off the dummy BS, attached Akutsu-san's new SS mirror plates, reglued the flags and prisms, and removed the gluing hardware, so the dummy BS is ready for shipping. Tatsumi-san's refinements to the tooling (especially the new flag holders) worked very smoothly. We were more generous with the glue and much more careful with the alignment of the prisms to the barrel, both during rehearsal and the final gluing.
  * Mark wrote up the gluing procedure as a new document [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5505| E1605505]]. (The original plan was to do an addendum to Tatsumi-san's PR gluing procedure JGW-E1504248, but there was too much material.)
  * Hirata-san organized with Takahashi-san to get the BS payload masses shipped to Kamioka. They will go in an air-ride truck on Wed 8/17 together with a load of Type A stuff, and will arrive early on Thu 8/17.
  * Hirata-san measured another standard filter.
  * Fabian worked on the payload assembly procedure.
  * Komori-kun, Kuwahara-kun and Akutsu-san calibrated an initial batch of 7 wide-mouthed OSEMs. They will be shipped to Kamioka on Friday.
 
 * Type B ongoing issues
  * OSEMs
   * First batch of 7 ready for shipping.
  * Longer cables for BF->PI and SF->PI.
   * Connectors RECEIVED, cables being made.
  * Lower breadboard stuff
   * Installation to be incorporated into the procedure document. Mark/Takahashi to discuss.
  * Documents
   * BS Assembly Procedure [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]], [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]]
 * To-do list during Mark's vacation
  * Weigh IM/RM/IRM (Fabian, Hirata) - DONE
   * New trim mass - ORDERED.
  * Pack/ship IM/RM/IRM to Kamioka (Hirata/Fabian) - READY TO SHIP.
  * Analyze geophone data (Fabian/Shoda) - DONE.
  * Remove glue from dummy BS face (Fabian) - DONE.
  * Reglue flags and prisms (Tatsumi, Fabian) - DONE.
  * Clean wire for BS and RM (Hirata) - DONE
  * Get new winch parts for new wire diameters - ORDERED, expected 8/5.
  * Do fit/function test of winches (Fabian/Hirata) - fit test DONE, function test from 8/8
  * Ship winches to Kamioka (Hirata/Fabian)
  * Work on BS simulation (Fabian)
  * Do Inventor assembly for SR2 in chamber and on assembly frame (Hirata) - ONGOING.
  * Write more of payload assembly procedure (Fabian) - ONGOING
  * Write more of main assembly procedure (Mark) - ONGOING
 * Longer term to-do list
  * Do BS Simulink model (Mark, Kokeyama)
  * Do 2D drawings of SR2 parts (Hirata)
  * Redesign SRx IM wire clamps for larger prisms, remachined RMs
  * Order SRM/PRM parts (Hirata/Shoda)
  * Order SRx fasteners (Hirata)
=== Type B (Mark) ===
==== Past two weeks report ====
Kamioka (Mark, Enzo, Kozu-kun):
 * Supported IA team.
 * Replaced LPCDs for IM OSEMs with HPCDs for increased pitch/yaw range.
 * Re-zeroed OL after significant change of beam position during IA.
 * Re-laid-out OL to improve focus of lens to LEN QPD.
 * Offloaded the pitch/yaw actuation at the IM OSEMs using the IM pitch/yaw picos.
 * Enzo worked on design of control loops using the OL.
 * Kozu-kun worked on diagonalizing the OL.

Mitaka (Fabian, Hirata-san):
 * Fabian did mechanical design:
  * F0 FR
  * Cable clamps for the SR IP base.
  * New SR recoil ballast masses.
  * LBB ballast.
  * Update of BS 3D CAD with the as-built ballast.
 * Hirata-san
  * made and updated inventory list for SR.
  * made order list and asked some quotes.
  * Ordered some parts.
  * Talked with mirapro about SRM optical bench.
  * Made some drawings for SR preparation.

==== Plan for week of 11/13 ====

Enzo and Kozu-kun at Mitaka
 * Servos
 * Diagonalization of OL
 * TFs of BF
 * Documentation

Mark and Fabian at Kamioka.
 * Mark attends commissioning workshop at U Toyama.
 * Support BF characterization work.
 * Prepare for mirror gluing.
 * Prepare for IM assembly.

Hirata-san at Mitaka
 * SR procurement.
 * Get BS prism-gluing jigs reworked for use with PR/SR mirror box.

==== Plan for week of 11/20 ====
 * Holiday on Thu 3/23
 * Fabian at commissioning workshop
 *

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Past two weeks report

Kamioka (Mark, Enzo, Kozu-kun):

  • Supported IA team.
  • Replaced LPCDs for IM OSEMs with HPCDs for increased pitch/yaw range.
  • Re-zeroed OL after significant change of beam position during IA.
  • Re-laid-out OL to improve focus of lens to LEN QPD.
  • Offloaded the pitch/yaw actuation at the IM OSEMs using the IM pitch/yaw picos.
  • Enzo worked on design of control loops using the OL.
  • Kozu-kun worked on diagonalizing the OL.

Mitaka (Fabian, Hirata-san):

  • Fabian did mechanical design:
    • F0 FR
    • Cable clamps for the SR IP base.
    • New SR recoil ballast masses.
    • LBB ballast.
    • Update of BS 3D CAD with the as-built ballast.
  • Hirata-san
    • made and updated inventory list for SR.
    • made order list and asked some quotes.
    • Ordered some parts.
    • Talked with mirapro about SRM optical bench.
    • Made some drawings for SR preparation.

Plan for week of 11/13

Enzo and Kozu-kun at Mitaka

  • Servos
  • Diagonalization of OL
  • TFs of BF
  • Documentation

Mark and Fabian at Kamioka.

  • Mark attends commissioning workshop at U Toyama.
  • Support BF characterization work.
  • Prepare for mirror gluing.
  • Prepare for IM assembly.

Hirata-san at Mitaka

  • SR procurement.
  • Get BS prism-gluing jigs reworked for use with PR/SR mirror box.

Plan for week of 11/20

  • Holiday on Thu 3/23
  • Fabian at commissioning workshop

KAGRA/Subgroups/VIS/TypeB/Minutes (last edited 2022-10-28 10:02:46 by fabian.arellano)