 * Type B Past Week Summary
  * Mark, Fabian and Hirata-san cleaned glue off the dummy BS, attached Akutsu-san's new SS mirror plates, reglued the flags and prisms, and removed the gluing hardware, so the dummy BS is ready for shipping. Tatsumi-san's refinements to the tooling (especially the new flag holders) worked very smoothly. We were more generous with the glue and much more careful with the alignment of the prisms to the barrel, both during rehearsal and the final gluing.
  * Mark wrote up the gluing procedure as a new document [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5505| E1605505]]. (The original plan was to do an addendum to Tatsumi-san's PR gluing procedure JGW-E1504248, but there was too much material.)
  * Hirata-san organized with Takahashi-san to get the BS payload masses shipped to Kamioka. They will go in an air-ride truck on Wed 8/17 together with a load of Type A stuff, and will arrive early on Thu 8/17.
  * Hirata-san measured another standard filter.
  * Fabian worked on the payload assembly procedure.
  * Komori-kun, Kuwahara-kun and Akutsu-san calibrated an initial batch of 7 wide-mouthed OSEMs. They will be shipped to Kamioka on Friday.
 
 * Type B ongoing issues
  * OSEMs
   * First batch of 7 ready for shipping.
  * Longer cables for BF->PI and SF->PI.
   * Connectors RECEIVED, cables being made.
  * Lower breadboard stuff
   * Installation to be incorporated into the procedure document. Mark/Takahashi to discuss.
  * Documents
   * BS Assembly Procedure [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]], [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]]
 * To-do list during Mark's vacation
  * Weigh IM/RM/IRM (Fabian, Hirata) - DONE
   * New trim mass - ORDERED.
  * Pack/ship IM/RM/IRM to Kamioka (Hirata/Fabian) - READY TO SHIP.
  * Analyze geophone data (Fabian/Shoda) - DONE.
  * Remove glue from dummy BS face (Fabian) - DONE.
  * Reglue flags and prisms (Tatsumi, Fabian) - DONE.
  * Clean wire for BS and RM (Hirata) - DONE
  * Get new winch parts for new wire diameters - ORDERED, expected 8/5.
  * Do fit/function test of winches (Fabian/Hirata) - fit test DONE, function test from 8/8
  * Ship winches to Kamioka (Hirata/Fabian)
  * Work on BS simulation (Fabian)
  * Do Inventor assembly for SR2 in chamber and on assembly frame (Hirata) - ONGOING.
  * Write more of payload assembly procedure (Fabian) - ONGOING
  * Write more of main assembly procedure (Mark) - ONGOING
 * Longer term to-do list
  * Do BS Simulink model (Mark, Kokeyama)
  * Do 2D drawings of SR2 parts (Hirata)
  * Redesign SRx IM wire clamps for larger prisms, remachined RMs
  * Order SRM/PRM parts (Hirata/Shoda)
  * Order SRx fasteners (Hirata)
=== Type B (Mark) ===
==== Past week report ====

 * Mark and Fabian did a huge cleanup of the SR2 area and prepared a workspace for assembling the IM.
 * Fabian did a stocktake of the screws for the SR.
  * We have all we need for the IM, except one type that can be added after the rest of the IP is assembled.
  * We have most of what we need for the rest of the payload, and Hirata-san has ordered the others.
 * Hirata-san worked on SR procurement:
  * Suspension wire
  * SR additional parts (compensation masses, clamps etc)
  * Regular, SDC and BUMAX screws.
  * Additional machining on the BS sapphire prism jig to allow it to be used on the PR/SR mirror box.
  * LBB blade design.
 * Enzo and Kozu-kun (with help from Fujii-kun) worked on export from SUMCON to Matlab, and on filter design.

==== Plan for week of 11/20 ====
 * Holiday on Thu 3/23
 * All at Mitaka.
 * SR procurement, planning (Mark, Hirata-san)
 * SR mass budget (Fabian)
 * BS modeling filter design (Enzo, Kozu-kun)


==== Plan for week of 11/27 ====
 * Fabian at commissioning workshop
 * Hirata-san at Kamioka to work with Mirapro on SRM LBB installation.
 * All others at Kamioka to start SR2 assembly.

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Past week report

  • Mark and Fabian did a huge cleanup of the SR2 area and prepared a workspace for assembling the IM.
  • Fabian did a stocktake of the screws for the SR.
    • We have all we need for the IM, except one type that can be added after the rest of the IP is assembled.
    • We have most of what we need for the rest of the payload, and Hirata-san has ordered the others.
  • Hirata-san worked on SR procurement:
    • Suspension wire
    • SR additional parts (compensation masses, clamps etc)
    • Regular, SDC and BUMAX screws.
    • Additional machining on the BS sapphire prism jig to allow it to be used on the PR/SR mirror box.
    • LBB blade design.
  • Enzo and Kozu-kun (with help from Fujii-kun) worked on export from SUMCON to Matlab, and on filter design.

Plan for week of 11/20

  • Holiday on Thu 3/23
  • All at Mitaka.
  • SR procurement, planning (Mark, Hirata-san)
  • SR mass budget (Fabian)
  • BS modeling filter design (Enzo, Kozu-kun)

Plan for week of 11/27

  • Fabian at commissioning workshop
  • Hirata-san at Kamioka to work with Mirapro on SRM LBB installation.
  • All others at Kamioka to start SR2 assembly.