Differences between revisions 54 and 324 (spanning 270 versions)
Revision 54 as of 2016-08-11 17:31:41
Size: 2980
Editor: MarkBarton
Comment:
Revision 324 as of 2018-09-13 15:33:31
Size: 3776
Editor: EnzoTapia
Comment:
Deletions are marked like this. Additions are marked like this.
Line 5: Line 5:
 * Type B Past Week Summary
  * Mark, Fabian and Hirata-san cleaned glue off the dummy BS, attached Akutsu-san's new SS mirror plates, reglued the flags and prisms, and removed the gluing hardware, so the dummy BS is ready for shipping. Tatsumi-san's refinements to the tooling (especially the new flag holders) worked very smoothly. We were more generous with the glue and much more careful with the alignment of the prisms to the barrel, both during rehearsal and the final gluing.
  * Mark wrote up the gluing procedure as a new document [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5505| E1605505]]. (The original plan was to do an addendum to Tatsumi-san's PR gluing procedure JGW-E1504248, but there was too much material.)
  * Hirata-san organized with Takahashi-san to get the BS payload masses shipped to Kamioka. They will go in an air-ride truck on Wed 8/17 together with a load of Type A stuff, and will arrive early on Thu 8/17.
  * Hirata-san measured another standard filter.
  * Fabian worked on the payload assembly procedure.
  * Komori-kun, Kuwahara-kun and Akutsu-san calibrated an initial batch of 7 wide-mouthed OSEMs. They will be shipped to Kamioka on Friday.
 
 * Type B ongoing issues
  * OSEMs
   * First batch of 7 ready for shipping.
  * Longer cables for BF->PI and SF->PI.
   * Connectors RECEIVED, cables being made.
  * Lower breadboard stuff
   * Installation to be incorporated into the procedure document. Mark/Takahashi to discuss.
  * Documents
   * BS Assembly Procedure [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]], [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]]
 * To-do list during Mark's vacation
  * Weigh IM/RM/IRM (Fabian, Hirata) - DONE
   * New trim mass - ORDERED.
  * Pack/ship IM/RM/IRM to Kamioka (Hirata/Fabian) - READY TO SHIP.
  * Analyze geophone data (Fabian/Shoda) - DONE.
  * Remove glue from dummy BS face (Fabian) - DONE.
  * Reglue flags and prisms (Tatsumi, Fabian) - DONE.
  * Clean wire for BS and RM (Hirata) - DONE
  * Get new winch parts for new wire diameters - ORDERED, expected 8/5.
  * Do fit/function test of winches (Fabian/Hirata) - fit test DONE, function test from 8/8
  * Ship winches to Kamioka (Hirata/Fabian)
  * Work on BS simulation (Fabian)
  * Do Inventor assembly for SR2 in chamber and on assembly frame (Hirata) - ONGOING.
  * Write more of payload assembly procedure (Fabian) - ONGOING
  * Write more of main assembly procedure (Mark) - ONGOING
 * Longer term to-do list
  * Do BS Simulink model (Mark, Kokeyama)
  * Do 2D drawings of SR2 parts (Hirata)
  * Redesign SRx IM wire clamps for larger prisms, remachined RMs
  * Order SRM/PRM parts (Hirata/Shoda)
  * Order SRx fasteners (Hirata)
=== Type B (Mark) ===
==== Report for week of 9/10 ====
 * We finish the invacuum and in air cabling for SR2, but the in-vacuum cables for Geophones and F0 Yaw stepper motor are just temporary and will be replaced later once the suspension is inside the tank.
 * We checked all the motors, like:
       *the IM picos, BF picos.
 * We checked the BF Stepper (Fishing rod), SF Stepper (SF Fishing rod), F0 Stepper (F0 Fishing rod).
 * We debugged an issue with the IP LVDTs and discovered it was a broken interface card D1402829 in the LVDT driver. We made up a working chassis with the original two driver cards, so we didn't have to reset all the phases and gains.
 * We reset the IP FRs to midrange.
 * We added a basic set of arc weights and recentered the IP. We then adjusted the verticality of the security structure.
 * We relocked the IP temporarily, unlocked the SF/... section and aligned the IM OSEMs.
 * We powered down the BS, SR3 and SR2 electronics in preparation for the power outage.

=== Type B (Mark) ===
==== Report for week of 9/3 ====
 * We did more in-vacuum and in-air cabling for SR2 and got nearly everything connected.
 * We debugged the IM OSEMs and fixed two broken in-vacuum cables and some mislabeled in-air cables.
 * We debugged an issue with the IP LVDTs and discovered it was a broken interface card D1402829 in the LVDT driver. We made up a working chassis with the original two driver cards, so we didn't have to reset all the phases and gains.
 * We reset the IP FRs to midrange.
 * We added a basic set of arc weights and recentered the IP. We then adjusted the verticality of the security structure.
 * We relocked the IP temporarily, unlocked the SF/... section and aligned the IM OSEMs.
 * We powered down the BS, SR3 and SR2 electronics in preparation for the power outage.

==== Plan for week of 9/10 ====
 * Monday 9/10 is scheduled power outage.
 * Mark in US (job interview).
 * Hirata-san, Fabian, Kozu-kun, Panwei at Kamioka Tue-Fri.
 * Enzo at Kamioka Tue-Thu, then JPS Meeting Fri, then vacation.
===== Etc =====
 * Recover from power outage.
===== SR2 =====
 * Calibrate F0 LVDTs.
 * Calibrate IP LVDTs.
 * Cable geophones and any other remaining PI items.
 * Finish in-air cabling (sort out and relabel rack and feedthrough ends of any repurposed cables).
 * Do basic go/no-go test of electronic items.
 * Check SF keystone height and offload with FR as necessary.
 * Adjust ballast/trim mass of SF, with reserve for yaw stepper.
 * Set SF damper magnet ring height.
 * Check/tweak optic pitch.
 * TFs.
==== Plan for week of 9/17 ====
 * Monday 9/17 is holiday (Respect for the Aged Day).
 * Enzo on vacation.
 * Mark, Hirata-san, Fabian, Panwei at Kamioka Tue-Fri.
===== SR2 =====
 * Crane SR2 into tank.
 * Move SR2 in-air cables.
 * Remove First Contact.
 * Unlock and realign suspension.
===== SRM =====
 * Set pitch of SRM and RM, tighten clamps, remove winch system.
 * Weigh IM/... section.
 * Build up SS to BF level.
 * Add BF.

==== Plan for week of 9/24 ====
 * Monday 9/24 is holiday (Autumn Equinox).
 * Mark, Hirata-san, Fabian, Panwei at Kamioka Tue-Fri.
 * Suspend IM and tweak height/balance.
===== SRM =====
 * Cable/test BF.
 * Install IRM.
 * Install/cable/test IM OSEMs.

==== To-Do Lists, Schedule ====
 * [[KAGRA/Subgroups/VIS/TypeB/ToDoBS]]
 * [[KAGRA/Subgroups/VIS/TypeB/ToDoSR]]
 * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7779|JGW-L1807779 Type B Schedule (SR)]]

==== Vacation Info ====
 * Mark: 9/10-14 (job interview in US).
 * Enzo: 9/14 JPS, 9/15 through 10/8 vacation in Chile.

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Report for week of 9/10

  • We finish the invacuum and in air cabling for SR2, but the in-vacuum cables for Geophones and F0 Yaw stepper motor are just temporary and will be replaced later once the suspension is inside the tank.
  • We checked all the motors, like:
    • the IM picos, BF picos.
  • We checked the BF Stepper (Fishing rod), SF Stepper (SF Fishing rod), F0 Stepper (F0 Fishing rod).
  • We debugged an issue with the IP LVDTs and discovered it was a broken interface card D1402829 in the LVDT driver. We made up a working chassis with the original two driver cards, so we didn't have to reset all the phases and gains.
  • We reset the IP FRs to midrange.
  • We added a basic set of arc weights and recentered the IP. We then adjusted the verticality of the security structure.
  • We relocked the IP temporarily, unlocked the SF/... section and aligned the IM OSEMs.
  • We powered down the BS, SR3 and SR2 electronics in preparation for the power outage.

Type B (Mark)

Report for week of 9/3

  • We did more in-vacuum and in-air cabling for SR2 and got nearly everything connected.
  • We debugged the IM OSEMs and fixed two broken in-vacuum cables and some mislabeled in-air cables.
  • We debugged an issue with the IP LVDTs and discovered it was a broken interface card D1402829 in the LVDT driver. We made up a working chassis with the original two driver cards, so we didn't have to reset all the phases and gains.
  • We reset the IP FRs to midrange.
  • We added a basic set of arc weights and recentered the IP. We then adjusted the verticality of the security structure.
  • We relocked the IP temporarily, unlocked the SF/... section and aligned the IM OSEMs.
  • We powered down the BS, SR3 and SR2 electronics in preparation for the power outage.

Plan for week of 9/10

  • Monday 9/10 is scheduled power outage.
  • Mark in US (job interview).
  • Hirata-san, Fabian, Kozu-kun, Panwei at Kamioka Tue-Fri.
  • Enzo at Kamioka Tue-Thu, then JPS Meeting Fri, then vacation.

Etc
  • Recover from power outage.

SR2
  • Calibrate F0 LVDTs.
  • Calibrate IP LVDTs.
  • Cable geophones and any other remaining PI items.
  • Finish in-air cabling (sort out and relabel rack and feedthrough ends of any repurposed cables).
  • Do basic go/no-go test of electronic items.
  • Check SF keystone height and offload with FR as necessary.
  • Adjust ballast/trim mass of SF, with reserve for yaw stepper.
  • Set SF damper magnet ring height.
  • Check/tweak optic pitch.
  • TFs.

Plan for week of 9/17

  • Monday 9/17 is holiday (Respect for the Aged Day).
  • Enzo on vacation.
  • Mark, Hirata-san, Fabian, Panwei at Kamioka Tue-Fri.

SR2
  • Crane SR2 into tank.
  • Move SR2 in-air cables.
  • Remove First Contact.
  • Unlock and realign suspension.

SRM
  • Set pitch of SRM and RM, tighten clamps, remove winch system.
  • Weigh IM/... section.
  • Build up SS to BF level.
  • Add BF.

Plan for week of 9/24

  • Monday 9/24 is holiday (Autumn Equinox).
  • Mark, Hirata-san, Fabian, Panwei at Kamioka Tue-Fri.
  • Suspend IM and tweak height/balance.

SRM
  • Cable/test BF.
  • Install IRM.
  • Install/cable/test IM OSEMs.

To-Do Lists, Schedule

Vacation Info

  • Mark: 9/10-14 (job interview in US).
  • Enzo: 9/14 JPS, 9/15 through 10/8 vacation in Chile.

KAGRA/Subgroups/VIS/TypeB/Minutes (last edited 2022-10-28 10:02:46 by fabian.arellano)