Line 6: Line 6:
  * Mark, Fabian and Hirata-san cleaned glue off the dummy BS, attached Akutsu-san's new SS mirror plates, reglued the flags and prisms, and removed the gluing hardware, so the dummy BS is ready for shipping. Tatsumi-san's refinements to the tooling (especially the new flag holders) worked very smoothly. We were more generous with the glue and much more careful with the alignment of the prisms to the barrel, both during rehearsal and the final gluing.
  * Mark wrote up the gluing procedure as a new document [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5505| E1605505]]. (The original plan was to do an addendum to Tatsumi-san's PR gluing procedure JGW-E1504248, but there was too much material.)
  * Hirata-san organized with Takahashi-san to get the BS payload masses shipped to Kamioka. They will go in an air-ride truck on Wed 8/17 together with a load of Type A stuff, and will arrive early on Thu 8/17.
  * Hirata-san measured another standard filter.
  * Fabian worked on the payload assembly procedure.
  * Komori-kun, Kuwahara-kun and Akutsu-san calibrated an initial batch of 7 wide-mouthed OSEMs. They will be shipped to Kamioka on Friday.
 
 * Type B ongoing issues
  * OSEMs
   * First batch of 7 ready for shipping.
  * Longer cables for BF->PI and SF->PI.
   * Connectors RECEIVED, cables being made.
  * Lower breadboard stuff
   * Installation to be incorporated into the procedure document. Mark/Takahashi to discuss.
  * Documents
   * BS Assembly Procedure [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]], [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]]
 * To-do list during Mark's vacation
  * Weigh IM/RM/IRM (Fabian, Hirata) - DONE
   * New trim mass - ORDERED.
  * Pack/ship IM/RM/IRM to Kamioka (Hirata/Fabian) - READY TO SHIP.
  * Analyze geophone data (Fabian/Shoda) - DONE.
  * Remove glue from dummy BS face (Fabian) - DONE.
  * Reglue flags and prisms (Tatsumi, Fabian) - DONE.
  * Clean wire for BS and RM (Hirata) - DONE
  * Get new winch parts for new wire diameters - ORDERED, expected 8/5.
  * Do fit/function test of winches (Fabian/Hirata) - fit test DONE, function test from 8/8
  * Ship winches to Kamioka (Hirata/Fabian)
  * Work on BS simulation (Fabian)
  * Do Inventor assembly for SR2 in chamber and on assembly frame (Hirata) - ONGOING.
  * Write more of payload assembly procedure (Fabian) - ONGOING
  * Write more of main assembly procedure (Mark) - ONGOING
 * Longer term to-do list
  * Do BS Simulink model (Mark, Kokeyama)
  * Do 2D drawings of SR2 parts (Hirata)
  * Redesign SRx IM wire clamps for larger prisms, remachined RMs
  * Order SRM/PRM parts (Hirata/Shoda)
  * Order SRx fasteners (Hirata)
  * Mark worked on task lists and schedule.
  * Mark worked on an update of the BS Electronic Items doc ([[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5111|E1505111]]) and started a SRx Electronics Items doc ([[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5886|E1605886]]).
  * Mark did a summary spreadsheet of Takahashi-san's cable orders to see what needed to be ordered immediately (new BS TM OSEM cables; geophone adapters) and later (for SRx).
  * Mark worked on an update of the In-Vacuum Cable doc ([[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=3901|E1503901]]), including information on final lengths that Fabian and Hirata-san had decided when making adapter cables.
  * Mark considered an alternative cabling scheme for the geophones (with a different adapter cable to put the signals and power on different lines and a matching unscrambler) but ended up concluding that the existing design would probably be OK. See [[attachment:00 Revised Geophone-v2.PDF]].
  * Fabian worked on a redesign of the EQ stops for the BS (2 of 4 screws under the RM are opposite large holes and there are no screws to restrain the RM front/back at either top or bottom).
  * Hirata-san worked on PR/SR mirror box modifications with Shoda-san (on-going).
  * Hirata-san partially assembled a bottom filter for use in fit tests of the PRx BF recoil mass.

  

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

  • Type B Past Week Summary
    • Mark worked on task lists and schedule.
    • Mark worked on an update of the BS Electronic Items doc (E1505111) and started a SRx Electronics Items doc (E1605886).

    • Mark did a summary spreadsheet of Takahashi-san's cable orders to see what needed to be ordered immediately (new BS TM OSEM cables; geophone adapters) and later (for SRx).
    • Mark worked on an update of the In-Vacuum Cable doc (E1503901), including information on final lengths that Fabian and Hirata-san had decided when making adapter cables.

    • Mark considered an alternative cabling scheme for the geophones (with a different adapter cable to put the signals and power on different lines and a matching unscrambler) but ended up concluding that the existing design would probably be OK. See 00 Revised Geophone-v2.PDF.

    • Fabian worked on a redesign of the EQ stops for the BS (2 of 4 screws under the RM are opposite large holes and there are no screws to restrain the RM front/back at either top or bottom).
    • Hirata-san worked on PR/SR mirror box modifications with Shoda-san (on-going).
    • Hirata-san partially assembled a bottom filter for use in fit tests of the PRx BF recoil mass.