Differences between revisions 56 and 289 (spanning 233 versions)
Revision 56 as of 2016-08-12 17:25:29
Size: 3604
Editor: MarkBarton
Comment:
Revision 289 as of 2018-06-01 11:49:44
Size: 3034
Editor: MarkBarton
Comment:
Deletions are marked like this. Additions are marked like this.
Line 5: Line 5:
 * Type B Past Week Summary
  * Mark, Fabian and Hirata-san cleaned glue off the dummy BS, attached Akutsu-san's new SS mirror plates, reglued the flags and prisms, and removed the gluing hardware, so the dummy BS is ready for shipping. Tatsumi-san's refinements to the tooling (especially the new flag holders) worked very smoothly. We were more generous with the glue and much more careful with the alignment of the prisms to the barrel, both during rehearsal and the final gluing.
  * Mark wrote up the gluing procedure as a new document [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5505| E1605505]]. (The original plan was to do an addendum to Tatsumi-san's PR gluing procedure JGW-E1504248, but there was too much material.)
  * Hirata-san organized with Takahashi-san to get the BS payload masses shipped to Kamioka. They will go in an air-ride truck on Wed 8/17 together with a load of Type A stuff, and will arrive early on Thu 8/17.
  * Hirata-san shipped the collection of Type B fasteners to Kamioka, to arrive Mon 8/15.
  * Hirata-san measured another standard filter and cleaned various parts for people.
  * Hirata-san worked on the SR2 Inventor assembly. He spotted a problem with the orientation: given the position of the pistons in the SR2 tank (according to the assembly from Mirapro), mating the standard Type B SR chain and the chamber in the natural way puts the optic at 90° to what it needs to be. A similar problem was found in the Type B Test at Mitaka, and it was eventually worked around, but with some difficulty. Hirata-san will investigate the best way of making a correction.
  * Komori-kun, Kuwahara-kun and Akutsu-san calibrated an initial batch of 7 wide-mouthed OSEMs. They will be shipped to Kamioka on Friday.
  * Fabian worked on the payload assembly procedure.
 
 * Type B ongoing issues
  * OSEMs
   * First batch of 7 ready for shipping.
  * Longer cables for BF->PI and SF->PI still not received, Takahashi-san to check status.
  * Lower breadboard stuff
   * Installation to be incorporated into the procedure document. Mark/Takahashi to discuss.
  * Documents
   * BS Assembly Procedure [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]], [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]]
 * To-do list during Mark's vacation
  * Weigh IM/RM/IRM (Fabian, Hirata) - DONE
   * New trim mass - ORDERED.
  * Pack/ship IM/RM/IRM to Kamioka (Hirata/Fabian) - READY TO SHIP.
  * Analyze geophone data (Fabian/Shoda) - DONE.
  * Remove glue from dummy BS face (Fabian) - DONE.
  * Reglue flags and prisms (Tatsumi, Fabian) - DONE.
  * Clean wire for BS and RM (Hirata) - DONE
  * Get new winch parts for new wire diameters - ORDERED, expected 8/5.
  * Do fit/function test of winches (Fabian/Hirata) - fit test DONE, function test from 8/8
  * Ship winches to Kamioka (Hirata/Fabian)
  * Work on BS simulation (Fabian)
  * Do Inventor assembly for SR2 in chamber and on assembly frame (Hirata) - ONGOING.
  * Write more of payload assembly procedure (Fabian) - ONGOING
  * Write more of main assembly procedure (Mark) - ONGOING
 * Longer term to-do list
  * Do BS Simulink model (Mark, Kokeyama)
  * Do 2D drawings of SR2 parts (Hirata)
  * Redesign SRx IM wire clamps for larger prisms, remachined RMs
  * Order SRM/PRM parts (Hirata/Shoda)
  * Order SRx fasteners (Hirata)
=== Type B (Mark) ===
==== Report for week of 5/28 ====
 * Enzo tested the LVDT driver repaired by Tanaka-san - it was fine.
 * Fujii-kun and Enzo finished assembling a batch of 4 geophones and took test data.
 * Hirata-san modified some Promec masses (drilling out the threads on 2 of 4 holes) so we could use two layers of them inside the BF.
 * Hirata-san installed maraging rod receptacles in the LBB damper rings, and in the bottom of PIs #3 and #1 (for the SF damper rings).
 * After consulting with various people, Hirata-san installed the second half of the LBB top ring in the chamber, simply omitting the pillar and screw associated with the badly threaded hole.
 * Hirata-san took delivery of the screws for the LBB blade units, made up 9 blade units and installed 6 of them on PI #3 and #1 (for SR3 and SR2).
 * Hirata-san made up a set of PI cable clamps and installed them on PI #3 (for SR3).
 * Hirata-san removed the prototype blades from PI #3 to get ready for testing the final blades.
 * We located the #355 disk and #356 poles for the next level of the security structure up to the SF and installed the poles.
 * We installed ballast mass in the BF. After some trial and error we settled on 16 Promec masses (7.1 kg) inside the BF and 5 D1808104-4 and 3 D1808104-5 masses (540 g) on the cap.
 * Enzo and Fujii-kun did several rounds of TFs on the BF/... section of the suspension and debugged a problem with dewhitening filters not being installed in the OSEMINF filter bank.
 * Enzo installed damping filters for the IM OSEMs.

==== Plan for week of 5/28 ====
 * Mark, Enzo at Kamioka Mon-Fri.
 * Hirata-san at Kamioka Tue-Fri. (Mon is monthly Mitaka day.)
 * Matteo at Kamioka from Tue. He may help Type B to get experience.
 * Kozu-kun at Kamioka Mon only. (Rest of week is job interviews.)
 * --

==== Plan for week of 6/4 ====
 * Mark, Enzo, Hirata-san, Kozu-kun at Kamioka Tue-Fri. (Mon is NAOJ medical checkup.)
 * --
 * Cable and test BF cap picos.
 * Build up security structure to SF level.
 * Crane in SF and remove cap.
 * Hook BF and adjust total ballast.
 * Route cables through SF-BF flying saucer up to bottom of SF.
 * Adjust BF trim mass.
 * Readjust payload.
 * Take TFs.
 * Add budgeted ballast mass to SF and weigh SF/... section.
 * Cable, test SF LVDT and FR.
 * Characterize final F0 blades.

==== Plan for week of 6/11 ====
 * Mark Enzo, Hirata-san, Kozu-kun at Kamioka Tue-Fri (Mon is compensation day for f2f.)
 * --
 * Rebuild F0 #3 for SR3.
 * Park F0 #1 (for SR2) in top of SR3 assembly frame.
 * Move F0 #3 behind SR3.
 * Make LBB blade sets (or at least 3 of 9).

==== To-Do Lists, Schedule ====
 * [[KAGRA/Subgroups/VIS/TypeB/ToDoBS]]
 * [[KAGRA/Subgroups/VIS/TypeB/ToDoSR]]
 * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7779|JGW-L1807779-v1 Type B Schedule (SR)]]

==== Vacation Info ====

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Report for week of 5/28

  • Enzo tested the LVDT driver repaired by Tanaka-san - it was fine.
  • Fujii-kun and Enzo finished assembling a batch of 4 geophones and took test data.
  • Hirata-san modified some Promec masses (drilling out the threads on 2 of 4 holes) so we could use two layers of them inside the BF.
  • Hirata-san installed maraging rod receptacles in the LBB damper rings, and in the bottom of PIs #3 and #1 (for the SF damper rings).
  • After consulting with various people, Hirata-san installed the second half of the LBB top ring in the chamber, simply omitting the pillar and screw associated with the badly threaded hole.
  • Hirata-san took delivery of the screws for the LBB blade units, made up 9 blade units and installed 6 of them on PI #3 and #1 (for SR3 and SR2).
  • Hirata-san made up a set of PI cable clamps and installed them on PI #3 (for SR3).
  • Hirata-san removed the prototype blades from PI #3 to get ready for testing the final blades.
  • We located the #355 disk and #356 poles for the next level of the security structure up to the SF and installed the poles.
  • We installed ballast mass in the BF. After some trial and error we settled on 16 Promec masses (7.1 kg) inside the BF and 5 D1808104-4 and 3 D1808104-5 masses (540 g) on the cap.
  • Enzo and Fujii-kun did several rounds of TFs on the BF/... section of the suspension and debugged a problem with dewhitening filters not being installed in the OSEMINF filter bank.
  • Enzo installed damping filters for the IM OSEMs.

Plan for week of 5/28

  • Mark, Enzo at Kamioka Mon-Fri.
  • Hirata-san at Kamioka Tue-Fri. (Mon is monthly Mitaka day.)
  • Matteo at Kamioka from Tue. He may help Type B to get experience.
  • Kozu-kun at Kamioka Mon only. (Rest of week is job interviews.)
  • --

Plan for week of 6/4

  • Mark, Enzo, Hirata-san, Kozu-kun at Kamioka Tue-Fri. (Mon is NAOJ medical checkup.)
  • --
  • Cable and test BF cap picos.
  • Build up security structure to SF level.
  • Crane in SF and remove cap.
  • Hook BF and adjust total ballast.
  • Route cables through SF-BF flying saucer up to bottom of SF.
  • Adjust BF trim mass.
  • Readjust payload.
  • Take TFs.
  • Add budgeted ballast mass to SF and weigh SF/... section.
  • Cable, test SF LVDT and FR.
  • Characterize final F0 blades.

Plan for week of 6/11

  • Mark Enzo, Hirata-san, Kozu-kun at Kamioka Tue-Fri (Mon is compensation day for f2f.)
  • --
  • Rebuild F0 #3 for SR3.
  • Park F0 #1 (for SR2) in top of SR3 assembly frame.
  • Move F0 #3 behind SR3.
  • Make LBB blade sets (or at least 3 of 9).

To-Do Lists, Schedule

Vacation Info

KAGRA/Subgroups/VIS/TypeB/Minutes (last edited 2022-10-28 10:02:46 by fabian.arellano)