  * Mark, Fabian and Hirata-san cleaned glue off the dummy BS, attached Akutsu-san's new SS mirror plates, reglued the flags and prisms, and removed the gluing hardware, so the dummy BS is ready for shipping. Tatsumi-san's refinements to the tooling (especially the new flag holders) worked very smoothly. We were more generous with the glue and much more careful with the alignment of the prisms to the barrel, both during rehearsal and the final gluing.
  * Mark wrote up the gluing procedure as a new document [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5505| E1605505]]. (The original plan was to do an addendum to Tatsumi-san's PR gluing procedure JGW-E1504248, but there was too much material.)
  * Hirata-san organized with Takahashi-san to get the BS payload masses shipped to Kamioka. They will go in an air-ride truck on Wed 8/17 together with a load of Type A stuff, and will arrive early on Thu 8/17.
  * Hirata-san shipped the collection of Type B fasteners to Kamioka, to arrive Mon 8/15.
  * Hirata-san measured another standard filter and cleaned various parts for people.
  * Hirata-san worked on the SR2 Inventor assembly. He spotted a problem with the orientation: given the position of the pistons in the SR2 tank (according to the assembly from Mirapro), mating the standard Type B SR chain and the chamber in the natural way puts the optic at 90° to what it needs to be. A similar problem was found in the Type B Test at Mitaka, and it was eventually worked around, but with some difficulty. Hirata-san will investigate the best way of making a correction.
  * Komori-kun, Kuwahara-kun and Akutsu-san calibrated an initial batch of 7 wide-mouthed OSEMs. They will be shipped to Kamioka on Friday.
  * Fabian worked on the payload assembly procedure.
=== Type B (Mark) ===
==== Report for week of 11/12 ====
 * BS
  * Kozu-kun noticed the BS OL was out of range, and Fabian and Fujii-kun investigated. It turns out that the temperature has risen by over 2°C, so all the GAS filters have sagged and several stages are touching. Miyoki-san and Furuta-san are looking at what can be done.
  * We ordered three more geophone cables in the standard (non-flipped pinout) to save time during the December vent, where we will replace at least two of the preamps to fix issues and take the opportunity to put in non-flipped ones.
 * SRM
  * We cabled all the SF/... through to the rack and checked that all items worked.
  * We did the vertical height survey and found that as with SR2 and SR3, the chain is longer than the CAD, this time by ≈7 mm, and again mostly between the SF and BF. We decided on a keystone height of 11.5 mm (5 mm higher than CAD), which can be achieved with 1 kg more on the SF and 1 kg in reserve for a yaw stepper mechanism. We reset the height of the yoke to give near-zero LVDT output for the new nominal height, and corrected the sensing and actuation signs, but still need to do the calibration.
  * The final SRM small glass mirror became available, so we had Hirose-san ship it to us so we can install it while the suspension is still on the assembly frame. Hirata-san ordered shims to make up the new recommended thickness of 1.4 mm and a micrometer to check the combination, which should arrive on Monday 11/26.
  * Enzo took calibration data for the last batch of geophones, for SRM. We had to borrow cables from SR2 because one cable was missing and another was miswired. And it turned out that one of the SR2 cables was defective as well. But if we can find two possibly borrowed by Okutomi-san and rewire one, we should have enough for SR2 and SRM. The geophones appear to be healthy and we will seal them next week.
  * We raised the PI clear of the assembly frame and unlocked and centered the IP. We calibrated the IP LVDTs, and reversed connections to get positive LVDT output for positive yaw. We borrowed a HPCD from SR3-IM-V for the SRM IP but haven't checked the actuation yet.
  
 * SR2
  * While we were grabbing geophone cables from SR2, we added extra arc weights to get the IP frequency below 0.1 Hz.
  * Akutsu-san showed us how to install the OL transmitter support pillar, receiver shelf and viewports. We believe we have the parts to finish setting up the SR2 OL.
Line 15: Line 21:
 * Type B ongoing issues
  * OSEMs
   * First batch of 7 ready for shipping.
  * Longer cables for BF->PI and SF->PI still not received, Takahashi-san to check status.
  * Lower breadboard stuff
   * Installation to be incorporated into the procedure document. Mark/Takahashi to discuss.
  * Documents
   * BS Assembly Procedure [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]], [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]]
 * To-do list during Mark's vacation
  * Weigh IM/RM/IRM (Fabian, Hirata) - DONE
   * New trim mass - ORDERED.
  * Pack/ship IM/RM/IRM to Kamioka (Hirata/Fabian) - READY TO SHIP.
  * Analyze geophone data (Fabian/Shoda) - DONE.
  * Remove glue from dummy BS face (Fabian) - DONE.
  * Reglue flags and prisms (Tatsumi, Fabian) - DONE.
  * Clean wire for BS and RM (Hirata) - DONE
  * Get new winch parts for new wire diameters - ORDERED, expected 8/5.
  * Do fit/function test of winches (Fabian/Hirata) - fit test DONE, function test from 8/8
  * Ship winches to Kamioka (Hirata/Fabian)
  * Work on BS simulation (Fabian)
  * Do Inventor assembly for SR2 in chamber and on assembly frame (Hirata) - ONGOING.
  * Write more of payload assembly procedure (Fabian) - ONGOING
  * Write more of main assembly procedure (Mark) - ONGOING
 * Longer term to-do list
  * Do BS Simulink model (Mark, Kokeyama)
  * Do 2D drawings of SR2 parts (Hirata)
  * Redesign SRx IM wire clamps for larger prisms, remachined RMs
  * Order SRM/PRM parts (Hirata/Shoda)
  * Order SRx fasteners (Hirata)
==== To-Do Lists, Schedule ====
 * [[KAGRA/Subgroups/VIS/TypeB/ToDoBS]]
 * [[KAGRA/Subgroups/VIS/TypeB/ToDoSR]]
 * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7779|JGW-L1807779 Type B Schedule (SR)]]

==== Plan for week of 11/26 ====
 * SRM
  * Clean tools and metal parts for final SRM glass mass.
  * Swap in final glass mass.
  * Adjust SF trim mass.
  * Check/adjust alignment of SS.
  * Calibrate IP LVDTs.
  * Add arc weights and geophones.
  * Improve centering/tuning of IP and SS alignment.
  * Disconnect cables at feedthroughs, lock suspension.
  * Crane into tank.
 * SR2
  * Finish OL setup
  * TFs.
  * Control loops.

==== Plan for week of 12/3 ====
 * f2f Meeting at NAOJ - no Kamioka work.
==== Plan for week of 12/10 ====
 * Prepare for vent of BS.
 * BS work - see [[KAGRA/Subgroups/VIS/TypeB/ToDoBS]].


==== Vacation/Event Info ====
 * Hirata-san at Mitaka, Fri 11/30 (medical check for solvent use).
 * Enzo at Mitaka, Fri 11/30 (Mitaka day).

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Report for week of 11/12

  • BS
    • Kozu-kun noticed the BS OL was out of range, and Fabian and Fujii-kun investigated. It turns out that the temperature has risen by over 2°C, so all the GAS filters have sagged and several stages are touching. Miyoki-san and Furuta-san are looking at what can be done.
    • We ordered three more geophone cables in the standard (non-flipped pinout) to save time during the December vent, where we will replace at least two of the preamps to fix issues and take the opportunity to put in non-flipped ones.
  • SRM
    • We cabled all the SF/... through to the rack and checked that all items worked.
    • We did the vertical height survey and found that as with SR2 and SR3, the chain is longer than the CAD, this time by ≈7 mm, and again mostly between the SF and BF. We decided on a keystone height of 11.5 mm (5 mm higher than CAD), which can be achieved with 1 kg more on the SF and 1 kg in reserve for a yaw stepper mechanism. We reset the height of the yoke to give near-zero LVDT output for the new nominal height, and corrected the sensing and actuation signs, but still need to do the calibration.
    • The final SRM small glass mirror became available, so we had Hirose-san ship it to us so we can install it while the suspension is still on the assembly frame. Hirata-san ordered shims to make up the new recommended thickness of 1.4 mm and a micrometer to check the combination, which should arrive on Monday 11/26.
    • Enzo took calibration data for the last batch of geophones, for SRM. We had to borrow cables from SR2 because one cable was missing and another was miswired. And it turned out that one of the SR2 cables was defective as well. But if we can find two possibly borrowed by Okutomi-san and rewire one, we should have enough for SR2 and SRM. The geophones appear to be healthy and we will seal them next week.
    • We raised the PI clear of the assembly frame and unlocked and centered the IP. We calibrated the IP LVDTs, and reversed connections to get positive LVDT output for positive yaw. We borrowed a HPCD from SR3-IM-V for the SRM IP but haven't checked the actuation yet.
  • SR2
    • While we were grabbing geophone cables from SR2, we added extra arc weights to get the IP frequency below 0.1 Hz.
    • Akutsu-san showed us how to install the OL transmitter support pillar, receiver shelf and viewports. We believe we have the parts to finish setting up the SR2 OL.

To-Do Lists, Schedule

Plan for week of 11/26

  • SRM
    • Clean tools and metal parts for final SRM glass mass.
    • Swap in final glass mass.
    • Adjust SF trim mass.
    • Check/adjust alignment of SS.
    • Calibrate IP LVDTs.
    • Add arc weights and geophones.
    • Improve centering/tuning of IP and SS alignment.
    • Disconnect cables at feedthroughs, lock suspension.
    • Crane into tank.
  • SR2
    • Finish OL setup
    • TFs.
    • Control loops.

Plan for week of 12/3

  • f2f Meeting at NAOJ - no Kamioka work.

Plan for week of 12/10

Vacation/Event Info

  • Hirata-san at Mitaka, Fri 11/30 (medical check for solvent use).