Differences between revisions 59 and 313 (spanning 254 versions)
Revision 59 as of 2016-08-17 21:04:06
Size: 3916
Editor: MarkBarton
Comment:
Revision 313 as of 2018-08-29 12:27:02
Size: 4235
Editor: MarkBarton
Comment:
Deletions are marked like this. Additions are marked like this.
Line 5: Line 5:
 * Type B Past Week Summary - week of 8/8
  * Mark, Fabian and Hirata-san cleaned glue off the dummy BS, attached Akutsu-san's new SS mirror plates, reglued the flags and prisms, and removed the gluing hardware, so the dummy BS is ready for shipping. Tatsumi-san's refinements to the tooling (especially the new flag holders) worked very smoothly. We were more generous with the glue and much more careful with the alignment of the prisms to the barrel, both during rehearsal and the final gluing.
  * Mark wrote up the gluing procedure as a new document [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5505| E1605505]]. (The original plan was to do an addendum to Tatsumi-san's PR gluing procedure JGW-E1504248, but there was too much material.)
  * Hirata-san organized with Takahashi-san to get the BS payload masses shipped to Kamioka. They will go in an air-ride truck on Wed 8/17 together with a load of Type A stuff, and will arrive early on Thu 8/17.
  * Hirata-san shipped the collection of Type B fasteners to Kamioka, to arrive Mon 8/15.
  * Hirata-san measured another standard filter and cleaned various parts for people.
  * Hirata-san worked on the SR2 Inventor assembly. He spotted a problem with the orientation: given the position of the pistons in the SR2 tank (according to the assembly from Mirapro), mating the standard Type B SR chain and the chamber in the natural way puts the optic at 90° to what it needs to be. A similar problem was found in the Type B Test at Mitaka, and it was eventually worked around, but with some difficulty. Hirata-san will investigate the best way of making a correction.
  * Komori-kun, Kuwahara-kun and Akutsu-san calibrated an initial batch of 7 wide-mouthed OSEMs.
  * Fabian worked on the payload assembly procedure.
 * Type B Past Week Summary - week of 8/15
  * Hirata-san shipped the fasteners to Kamioka, and they arrived Tuesday.
  * Hirata-san shipped a large load of Type A and Type B items, which Mark and Fabian received on Thursday 8/18.
  * Akutsu-san shipped the first 7 OSEMs.
  * Hirata-san and Ikenoue-san did a successful function test of the BS winches with the new clamp parts for the thicker wires.
  * Mark, Fabian and Zhao-kun did a major cleanup and reorganization of the BS clean booth at Kamioka, putting PR2 stuff in boxes, vacuuming and wiping, and making space.
  * Mark, Fabian and Zhao-kun set the crossbeams of the assembly frame to their correct positions and installed the EQ stop ring on top, ready to receive the IM. This is the first actual installation activity for Type B.
  *
 * Type B ongoing issues
  * Longer cables for BF->PI and SF->PI still not received, Takahashi-san to check status.
  * Lower breadboard stuff
   * Installation to be incorporated into the procedure document. Mark/Takahashi to discuss.
  * Documents
   * BS Assembly Procedure [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]], [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]]
 * Longer term to-do list
  * Decide position of BS rack (in consultation with Miyakawa-san) - document in progress: [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5413| T1605413]]
  * Do Inventor assembly for SR2 in chamber and on assembly frame (Hirata) - ONGOING.
  * Write more of payload assembly procedure (Fabian) - ONGOING
  * Write more of main assembly procedure (Mark) - ONGOING
  * Work on BS simulation (Fabian)
  * Do BS Simulink model (Mark, Kokeyama)
  * Do 2D drawings of SR2 parts (Hirata)
  * Redesign SRx IM wire clamps for larger prisms, remachined RMs
  * Order SRM/PRM parts (Hirata/Shoda)
  * Order SRx fasteners (Hirata)
=== Type B (Mark) ===
==== Report for week of 8/13 ====
KAGRA was closed Mon/Tue 8/13-14.
===== SR3 =====
 * Enzo and team debugged an issue with height of the SR3 keystone coupling to yaw of the payload as measured by the OL. We suspect a ferromagnetic item on the SF damper, but we're not sure.
==== Report for week of 8/20 ====
===== SR3 =====
 * Hatoya-san and Enzo gathered date for a study of yaw mode Q damping time as a study of damper ring height.
===== SR2 =====
 * We continued with cabling work.
 * We configured the second pico driver and connected it.
 * We assembled the LBB damper rings in the tank, craned them to near the top and hooked them. While the tank was open we also set the jacks below the mushroom that will support the suspension to nominal height.
Line 40: Line 18:
===== SRM =====
 * We reserved and configured two pico drivers.
 * We checked the prism gluing and all the jigs came away successfully.
 * Fabian assembled the RM.
 * Hirata-san added ballast masses to the IM and we weighed it, as well as the RM and the optic in the mirror box.
 * We suspended the optic and RM.

==== Report for week of 8/27 ====
 * We did an inventory of arc weights to see if we had enough for SRM and found that we had only enough for a basic allocation for all of type B (172 kg for BS and 103.2 kg per SR) and almost no spare for tuning. We did a quick study of the IP frequency as a function of the number of arc weights using SR3, to see how much more we might need. If SR3 is typical we would need about 27 kg extra per suspension.
===== SR3 =====
 * After the IP study, we left the SR3 with 6 10-mm arc weights and measured its frequency (with the digital system instead of a stopwatch).

===== SR2 =====
 * We finished routing the the in-vac
===== SRM =====
 * We moved the SRM assembly frame into its final position, reset it to the initial configuration, double-checked the heights of the crossbars, and lowered the optical table by 3 mm (to give margin for the optic to rise during hanging, which we had kept forgetting to do). We cleaned it up with the airgun and wet-wipes. We installed the IM ring and IM.
 * We assembled the SRM metal mass. Hirata-san made a jig from a plate with 4 screws which could safely hold the delicate front Sol-Black-coated ring upside down while the rest of the components were mounted on it.
 * We moved the metal mass to the mirror box and added the prisms and magnet standoffs. We applied the EP30 on Friday morning, but probably won't be able to check the result until after Obon.

==== Plan for week of 8/13 ====
 * KAGRA closed Mon, Tue.
 * Mark on vacation Mon-Thu, then Mitaka on Friday.
 * Enzo, Fabian, Terrence, Panwei, Rikako at Kamioka Wed-Fri.
 * Hirata-san on vacation all week.
 * Fujii-kun to help part-time with crane work and/or the IP tuning.
 * Diagonalization of new OL.
 * TFs with new OL.
 * Test of SF damper ring.
 * Controls work.
 * Tune SR3 IP.

==== Plan for week of 8/20 ====
 * Mark, Enzo, Hirata-san, Fabian, Kozu-kun, Terrence, Panwei at Kamioka Mon-Fri.
 * Enzo, Hirata-san, Fabian, Kozu-kun, Terrence, Panwei at Kamioka Mon-Thu, then f2f.
 * Kozu-kun works at Mozumi Mon.

===== SR3 =====
 * Hook LBB, add ballast mass.
 * Tune IP.

===== SR2 =====
 * Adjust ballast/trim mass, with reserve for yaw stepper.
 * Cable/test PI items (LVDTs, steppers, geophones).
 * Set damper height.
 * Add arc weights, adjust IP.
 * Stage LBB damper rings in tank.
Line 41: Line 65:
===== SRM =====
 * Check gluing result - redo if necessary.
 * Assemble RM.
 * Add IM ballast masses (we forgot this before).
 * Get parts from AOL and set up new pitch-setting OL.
 * Hang metal mass.
 * Hang RM.

==== To-Do Lists, Schedule ====
 * [[KAGRA/Subgroups/VIS/TypeB/ToDoBS]]
 * [[KAGRA/Subgroups/VIS/TypeB/ToDoSR]]
 * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7779|JGW-L1807779 Type B Schedule (SR)]]

==== Vacation Info ====
 * Mark: 8/13-16.
 * Hirata-san: 8/13-17
 * Terrence: 8/24-26 f2f, then returns to Hong Kong.
 * Enzo: 9/14 JPS, 9/15 through 10/8 vacation in Chile.

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Report for week of 8/13

KAGRA was closed Mon/Tue 8/13-14.

SR3
  • Enzo and team debugged an issue with height of the SR3 keystone coupling to yaw of the payload as measured by the OL. We suspect a ferromagnetic item on the SF damper, but we're not sure.

Report for week of 8/20

SR3
  • Hatoya-san and Enzo gathered date for a study of yaw mode Q damping time as a study of damper ring height.

SR2
  • We continued with cabling work.
  • We configured the second pico driver and connected it.
  • We assembled the LBB damper rings in the tank, craned them to near the top and hooked them. While the tank was open we also set the jacks below the mushroom that will support the suspension to nominal height.

SRM
  • We reserved and configured two pico drivers.
  • We checked the prism gluing and all the jigs came away successfully.
  • Fabian assembled the RM.
  • Hirata-san added ballast masses to the IM and we weighed it, as well as the RM and the optic in the mirror box.
  • We suspended the optic and RM.

Report for week of 8/27

  • We did an inventory of arc weights to see if we had enough for SRM and found that we had only enough for a basic allocation for all of type B (172 kg for BS and 103.2 kg per SR) and almost no spare for tuning. We did a quick study of the IP frequency as a function of the number of arc weights using SR3, to see how much more we might need. If SR3 is typical we would need about 27 kg extra per suspension.

SR3
  • After the IP study, we left the SR3 with 6 10-mm arc weights and measured its frequency (with the digital system instead of a stopwatch).

SR2
  • We finished routing the the in-vac

SRM
  • We moved the SRM assembly frame into its final position, reset it to the initial configuration, double-checked the heights of the crossbars, and lowered the optical table by 3 mm (to give margin for the optic to rise during hanging, which we had kept forgetting to do). We cleaned it up with the airgun and wet-wipes. We installed the IM ring and IM.
  • We assembled the SRM metal mass. Hirata-san made a jig from a plate with 4 screws which could safely hold the delicate front Sol-Black-coated ring upside down while the rest of the components were mounted on it.
  • We moved the metal mass to the mirror box and added the prisms and magnet standoffs. We applied the EP30 on Friday morning, but probably won't be able to check the result until after Obon.

Plan for week of 8/13

  • KAGRA closed Mon, Tue.
  • Mark on vacation Mon-Thu, then Mitaka on Friday.
  • Enzo, Fabian, Terrence, Panwei, Rikako at Kamioka Wed-Fri.
  • Hirata-san on vacation all week.
  • Fujii-kun to help part-time with crane work and/or the IP tuning.
  • Diagonalization of new OL.
  • TFs with new OL.
  • Test of SF damper ring.
  • Controls work.
  • Tune SR3 IP.

Plan for week of 8/20

  • Mark, Enzo, Hirata-san, Fabian, Kozu-kun, Terrence, Panwei at Kamioka Mon-Fri.
  • Enzo, Hirata-san, Fabian, Kozu-kun, Terrence, Panwei at Kamioka Mon-Thu, then f2f.
  • Kozu-kun works at Mozumi Mon.

SR3
  • Hook LBB, add ballast mass.
  • Tune IP.

SR2
  • Adjust ballast/trim mass, with reserve for yaw stepper.
  • Cable/test PI items (LVDTs, steppers, geophones).
  • Set damper height.
  • Add arc weights, adjust IP.
  • Stage LBB damper rings in tank.

SRM
  • Check gluing result - redo if necessary.
  • Assemble RM.
  • Add IM ballast masses (we forgot this before).
  • Get parts from AOL and set up new pitch-setting OL.
  • Hang metal mass.
  • Hang RM.

To-Do Lists, Schedule

Vacation Info

  • Mark: 8/13-16.
  • Hirata-san: 8/13-17
  • Terrence: 8/24-26 f2f, then returns to Hong Kong.
  • Enzo: 9/14 JPS, 9/15 through 10/8 vacation in Chile.

KAGRA/Subgroups/VIS/TypeB/Minutes (last edited 2022-10-28 10:02:46 by fabian.arellano)