Line 5: Line 5:
 * Type B Past Week Summary - week of 8/8
  * Mark, Fabian and Hirata-san cleaned glue off the dummy BS, attached Akutsu-san's new SS mirror plates, reglued the flags and prisms, and removed the gluing hardware, so the dummy BS is ready for shipping. Tatsumi-san's refinements to the tooling (especially the new flag holders) worked very smoothly. We were more generous with the glue and much more careful with the alignment of the prisms to the barrel, both during rehearsal and the final gluing.
  * Mark wrote up the gluing procedure as a new document [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5505| E1605505]]. (The original plan was to do an addendum to Tatsumi-san's PR gluing procedure JGW-E1504248, but there was too much material.)
  * Hirata-san organized with Takahashi-san to get the BS payload masses shipped to Kamioka. They will go in an air-ride truck on Wed 8/17 together with a load of Type A stuff, and will arrive early on Thu 8/17.
  * Hirata-san shipped the collection of Type B fasteners to Kamioka, to arrive Mon 8/15.
  * Hirata-san measured another standard filter and cleaned various parts for people.
  * Hirata-san worked on the SR2 Inventor assembly. He spotted a problem with the orientation: given the position of the pistons in the SR2 tank (according to the assembly from Mirapro), mating the standard Type B SR chain and the chamber in the natural way puts the optic at 90° to what it needs to be. A similar problem was found in the Type B Test at Mitaka, and it was eventually worked around, but with some difficulty. Hirata-san will investigate the best way of making a correction.
  * Komori-kun, Kuwahara-kun and Akutsu-san calibrated an initial batch of 7 wide-mouthed OSEMs.
  * Fabian worked on the payload assembly procedure.
 * Type B Past Week Summary - week of 8/15
  * Hirata-san shipped the fasteners to Kamioka, and they arrived Tuesday.
  * Hirata-san shipped a large load of Type A and Type B items, which Mark and Fabian received on Thursday 8/18.
  * Akutsu-san shipped the first 7 OSEMs.
  * Hirata-san and Ikenoue-san did a successful function test of the BS winches with the new clamp parts for the thicker wires.
  * Mark, Fabian and Zhao-kun did a major cleanup and reorganization of the BS clean booth at Kamioka, putting PR2 stuff in boxes, vacuuming and wiping, and making space.
  * Mark, Fabian and Zhao-kun set the crossbeams of the assembly frame to their correct positions and installed the EQ stop ring on top, ready to receive the IM. This is the first actual installation activity for Type B.
  *
 * Type B ongoing issues
  * Longer cables for BF->PI and SF->PI still not received, Takahashi-san to check status.
 * Longer term to-do list
  * Decide position of BS rack (in consultation with Miyakawa-san) - document in progress: [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5413| T1605413]]
  * Do Inventor assembly for SR2 in chamber and on assembly frame (Hirata) - ONGOING.
  * Write more of payload assembly procedure (Fabian) - ONGOING
  * Write more of BS Assembly Procedure [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]], [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]] (Mark) - ONGOING
  * Lower breadboard installation to be incorporated into the procedure document.
  * Work on BS simulation (Fabian)
  * Do BS Simulink model (Mark, Kokeyama)
  * Do 2D drawings of SR2 parts (Hirata)
  * Redesign SRx IM wire clamps for larger prisms, remachined RMs
  * Order SRM/PRM parts (Hirata/Shoda)
  * Order SRx fasteners (Hirata)
 * Mark and Fabian debugged the rubbing issue with the BS. It turns out the EQ stops between the IRM and IM are so misaligned that they can't be used at all. This misalignment was noted on 10/27 klog [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=2090|2090]] but seems to have gotten worse. With the stops removed, the OSEMs (adjusted on 10/27) are still fairly well centered, so the problem probably predates the earthquake of 11/1.
 * The IMM/IRM stops were removed, and Fabian installed the brackets that have EQ stop screws for the IRM. (Thus both the IM and IRM can be restrained independently, but not relatively.)
 * Mark worked on the PR2 rack:
  * Rearranged the items in the rack to make space for new AA and AI chassis at the bottom near the IO chassis.
  * Replaced the AA chassis, which had had a group of channels marked as bad by Michimura-san.
  * Installed a second AA chassis and a second AI chassis in the rack.
  * Installed a second ADC card and a second DAC card in the IO chassis.
  * Modified the k1ioppr2 real-time model to recognize the new ADC/DAC cards and also the extra DIO cards installed previously.
  * Attempted to modify the k1visbs real-time model to recognize the new ADC/DAC cards. Unfortunately, apparently due to changes to library parts made by Okutomi-san, neither the original model or Okutomi-san's new model can be successfully compiled and installed anymore! Debugging is ongoing.
 * Mark and Fabian did a stocktake of all the unused in-vacuum cables. There should be enough for the BS test hang.
 * Fabian finished the redesign of the EQ stops for the BS RM. Hirata-san will refine the 3D design and do drawings.
 * Fabian redesigned the cable clamp on top of the multi-purpose cube (on the BS RM) to avoid the need for clips. (These are too easily moved when the cables are moved during installation and removal of the safety bar between the RM and IM, which has to be done many times.) He will do a similar one for SR.
 * Mark and Fabian reviewed the previous IJECT payload parts order and flagged the items that need updating.
 * Mark worked on task lists and schedule, but the server still won't allow logins to upload anything.
 * Hirata-san finished the PR/SR mirror box modifications.
 * Hirata-san washed parts (screws and collets).
Line 37: Line 22:
    

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

  • Mark and Fabian debugged the rubbing issue with the BS. It turns out the EQ stops between the IRM and IM are so misaligned that they can't be used at all. This misalignment was noted on 10/27 klog 2090 but seems to have gotten worse. With the stops removed, the OSEMs (adjusted on 10/27) are still fairly well centered, so the problem probably predates the earthquake of 11/1.

  • The IMM/IRM stops were removed, and Fabian installed the brackets that have EQ stop screws for the IRM. (Thus both the IM and IRM can be restrained independently, but not relatively.)
  • Mark worked on the PR2 rack:
    • Rearranged the items in the rack to make space for new AA and AI chassis at the bottom near the IO chassis.
    • Replaced the AA chassis, which had had a group of channels marked as bad by Michimura-san.
    • Installed a second AA chassis and a second AI chassis in the rack.
    • Installed a second ADC card and a second DAC card in the IO chassis.
    • Modified the k1ioppr2 real-time model to recognize the new ADC/DAC cards and also the extra DIO cards installed previously.
    • Attempted to modify the k1visbs real-time model to recognize the new ADC/DAC cards. Unfortunately, apparently due to changes to library parts made by Okutomi-san, neither the original model or Okutomi-san's new model can be successfully compiled and installed anymore! Debugging is ongoing.
  • Mark and Fabian did a stocktake of all the unused in-vacuum cables. There should be enough for the BS test hang.
  • Fabian finished the redesign of the EQ stops for the BS RM. Hirata-san will refine the 3D design and do drawings.
  • Fabian redesigned the cable clamp on top of the multi-purpose cube (on the BS RM) to avoid the need for clips. (These are too easily moved when the cables are moved during installation and removal of the safety bar between the RM and IM, which has to be done many times.) He will do a similar one for SR.
  • Mark and Fabian reviewed the previous IJECT payload parts order and flagged the items that need updating.
  • Mark worked on task lists and schedule, but the server still won't allow logins to upload anything.
  • Hirata-san finished the PR/SR mirror box modifications.
  • Hirata-san washed parts (screws and collets).