Line 5: Line 5:
 * Type B Past Week Summary - weeks of 8/22 and 8/29
  * Fabian, Mark, Zhao-kun and Yokogawa-kun did BS installation at Kamioka:
   * Weighed the BF, SF and dummy BS (in mirror box).
   * Moved the geophones onto the optical table, clamped them down and took another time series for analysis.
   * Aligned the IM, installed the extra trim masses, tested the picos and weighed the whole assembly.
   * Placed vacuum flanges and cleaned D-Sub cables ready for routing to the rack.
   * Realigned and immobilized the optical table (which had been bumped).
   * Made safety improvements on the second floor (new safety rail, new arrangement of floor pieces, caution tape around holes)
   * Suspended the dummy BS. Currently however it is not hanging correctly, but is off in the +Y direction by several mm relative to the mirror box.
   * We set up the BS OL, using one of the wheeled chests of drawers as a base and using the OL breadboard from the PR2 assembly frame.
  * Hirata-san made a 3D assembly model for SR2 and added the optical design.
  * Hirata-san worked with Uchiyama-san to solve the 90° rotation problem. It turns out the "box" part with the pistons can be rotated, so we can build the SR2 according to the original design.
  * Hirata-san investigated the puzzle of the BF-IM maraging rods, where the 2D drawings and 3D CAD do not agree. Fortunately the actual parts seem to agree with the 3D CAD.
  * Hirata-san washed 3 OSEMs (last of initial 10 for BS) and parts for two BFs (for Type A). He moved the BF parts into the clean room and will assemble them with ATC staff from next Wednesday 9/7.
 * Type B ongoing issues
  * Longer cables for BF->PI and SF->PI - RECEIVED
 * Longer term to-do list
  * Decide position of BS rack - DONE
  * Do Inventor assembly for SR2 in chamber and on assembly frame (Hirata) - ONGOING.
  * Write more of payload assembly procedure (Fabian) - ONGOING
  * Write more of BS Assembly Procedure [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]], [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]] (Mark) - ONGOING
  * Lower breadboard installation to be incorporated into the procedure document.
  * Work on BS simulation (Fabian)
  * Do BS Simulink model (Mark, Kokeyama)
  * Do 2D drawings of SR2 parts (Hirata)
  * Redesign SRx IM wire clamps for larger prisms, remachined RMs
  * Order SRM/PRM parts (Hirata/Shoda)
  * Order SRx fasteners (Hirata)
=== Type B (Mark) ===
==== Past week report ====
At Kamioka (Mark, Ohishi-san, Fabian, Enzo, Hirata-san, Yoshioka-kun):
 * We moved or covered stuff in the BS cleanbooth to prepare for the SR2 crane slot cutting and BS-> SR2 assembly frame move.
 * We put the service port covers back on at the BF level of the BS tank.
 * We used the PI jacks to center the bottom of the security structure around the RM.
 * We debugged a mechanical issue where the #2 IP LVDT had too narrow a gap between the moving and fixed parts, so that there was interference with only a very small clockwise yaw of the IP. We fixed it by moving the bottom baseplate (taking advantage of the fact that it was held by screws in oversize holes for this purpose).
 * We used the IP FRs to center the IP.
 * We set the gains on the IP LVDT driver.
 
Line 34: Line 16:
  ==== Plan for week of 10/2 ====
Kamioka: Mark, Enzo (Tue-Fri), Ohishi-san, Kozu-kun.
 * Finish preparation for SR2 work.
 * Debug electronics, especially actuation.
 * Tune IP, do LVDT/stepper calibration.
 * Remove First Contact, try OL.
Mitaka: Fabian, Hirata-san
 * Design ballast for LBB.
 * Design improved PI yaw adjustment.
 * SR procurement.

==== Plan for week of 10/10 ====
Holiday Mon 10/9, Open Day prep Fri 10/13.<<BR>>
 * TFs, final preparation for alignment in week of 10/16.

==== Plan for week of 10/16 ====
Kamioka: all but Mark
 * Work with alignment team.

==== Vacation Info ====
Mark: 10/16-24

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Past week report

At Kamioka (Mark, Ohishi-san, Fabian, Enzo, Hirata-san, Yoshioka-kun):

  • We moved or covered stuff in the BS cleanbooth to prepare for the SR2 crane slot cutting and BS-> SR2 assembly frame move.

  • We put the service port covers back on at the BF level of the BS tank.
  • We used the PI jacks to center the bottom of the security structure around the RM.
  • We debugged a mechanical issue where the #2 IP LVDT had too narrow a gap between the moving and fixed parts, so that there was interference with only a very small clockwise yaw of the IP. We fixed it by moving the bottom baseplate (taking advantage of the fact that it was held by screws in oversize holes for this purpose).
  • We used the IP FRs to center the IP.
  • We set the gains on the IP LVDT driver.

Plan for week of 10/2

Kamioka: Mark, Enzo (Tue-Fri), Ohishi-san, Kozu-kun.

  • Finish preparation for SR2 work.
  • Debug electronics, especially actuation.
  • Tune IP, do LVDT/stepper calibration.
  • Remove First Contact, try OL.

Mitaka: Fabian, Hirata-san

  • Design ballast for LBB.
  • Design improved PI yaw adjustment.
  • SR procurement.

Plan for week of 10/10

Holiday Mon 10/9, Open Day prep Fri 10/13.

  • TFs, final preparation for alignment in week of 10/16.

Plan for week of 10/16

Kamioka: all but Mark

  • Work with alignment team.

Vacation Info

Mark: 10/16-24