 * Type B Past Week Summary - weeks of 8/22 and 8/29
  * Fabian, Mark, Zhao-kun and Yokogawa-kun did BS installation at Kamioka:
   * Weighed the BF, SF and dummy BS (in mirror box).
   * Moved the geophones onto the optical table, clamped them down and took another time series for analysis.
   * Aligned the IM, installed the extra trim masses, tested the picos and weighed the whole assembly.
   * Placed vacuum flanges and cleaned D-Sub cables ready for routing to the rack.
   * Realigned and immobilized the optical table (which had been bumped).
   * Made safety improvements on the second floor (new safety rail, new arrangement of floor pieces, caution tape around holes)
   * Suspended the dummy BS. Currently however it is not hanging correctly, but is off in the +Y direction by several mm relative to the mirror box.
   * We set up the BS OL, using one of the wheeled chests of drawers as a base and using the OL breadboard from the PR2 assembly frame.
  * Hirata-san made a 3D assembly model for SR2 and added the optical design.
  * Hirata-san worked with Uchiyama-san to solve the 90° rotation problem. It turns out the "box" part with the pistons can be rotated, so we can build the SR2 according to the original design.
  * Hirata-san investigated the puzzle of the BF-IM maraging rods, where the 2D drawings and 3D CAD do not agree. Fortunately the actual parts seem to agree with the 3D CAD.
  * Hirata-san washed 3 OSEMs (last of initial 10 for BS) and parts for two BFs (for Type A). He moved the BF parts into the clean room and will assemble them with ATC staff from next Wednesday 9/7.
 * Type B ongoing issues
  * Longer cables for BF->PI and SF->PI - RECEIVED
 * Longer term to-do list
  * Decide position of BS rack - DONE
  * Do Inventor assembly for SR2 in chamber and on assembly frame (Hirata) - ONGOING.
  * Write more of payload assembly procedure (Fabian) - ONGOING
  * Write more of BS Assembly Procedure [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]], [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]] (Mark) - ONGOING
  * Lower breadboard installation to be incorporated into the procedure document.
  * Work on BS simulation (Fabian)
  * Do BS Simulink model (Mark, Kokeyama)
  * Do 2D drawings of SR2 parts (Hirata)
  * Redesign SRx IM wire clamps for larger prisms, remachined RMs
  * Order SRM/PRM parts (Hirata/Shoda)
  * Order SRx fasteners (Hirata)
=== Type B (Mark) ===
==== Report for the week of 3/4 ====
 * On Monday, Mark helped Aso-san with PR3, and Monday, Tuesday and Wednesday, Fabian helped Fujii-kun with PRM.
 * Mark and Terrence attempted to offload some BS IM/IRM yaw adjustments that had been done by Enomoto-san last Friday. They rezeroed the OL and then opened the tank lid and did a compensating adjustment to the F0 yaw stepper, then undid the IM/IRM yaw with the pico. However this did not have the desired effect, probably because the buoyancy correction had not been cancelled when Enomoto-san was working and the BF keystone was very high, with the IM-V OSEMs way too far in and possibly touching. We did our best to back out all the adjustments but the roll TFs were still messy and there were signs that the IM was not free in yaw (the IM/IRM Y varied oppositely to IP Y, indicating that the IMR was free and the IM wasn't). We ended up deciding to have Mirapro remove the ducts on the ±X sides of the tank so we could go in and inspect.
 * Terrence tuned the SR3 LEN OL to be free of yaw cross-coupling.
 * Terrence and Enzo did a full set of filters and a Guardian for SR2 and SR3.
 * Terrence did health checks on SR2 and SR3.
 * Enzo measured mode Qs.
Line 34: Line 13:
  ==== Plan for week of 3/11 =====
 * Mark at Kamioka full week.
 * Enzo at Kamioka Mon, Tue, then JPS.
 * Hirata-san at Kamioka from Monday lunchtime through Friday.
 * Fix BS.
 * Final test of stepper remote enable system (someone in cleanroom checks the lights go on/off).
 * Install/test hardware watchdogs.
 * Continue monitoring SRM yaw drift.
 * More mode Q measurements.
 * Work on Type B paper.


==== Vacation/Travel Info ====
 * Enzo at JPS then final vacation, 3/13-29
 * Terrence's last day, 3/29.

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Report for the week of 3/4

  • On Monday, Mark helped Aso-san with PR3, and Monday, Tuesday and Wednesday, Fabian helped Fujii-kun with PRM.
  • Mark and Terrence attempted to offload some BS IM/IRM yaw adjustments that had been done by Enomoto-san last Friday. They rezeroed the OL and then opened the tank lid and did a compensating adjustment to the F0 yaw stepper, then undid the IM/IRM yaw with the pico. However this did not have the desired effect, probably because the buoyancy correction had not been cancelled when Enomoto-san was working and the BF keystone was very high, with the IM-V OSEMs way too far in and possibly touching. We did our best to back out all the adjustments but the roll TFs were still messy and there were signs that the IM was not free in yaw (the IM/IRM Y varied oppositely to IP Y, indicating that the IMR was free and the IM wasn't). We ended up deciding to have Mirapro remove the ducts on the ±X sides of the tank so we could go in and inspect.
  • Terrence tuned the SR3 LEN OL to be free of yaw cross-coupling.
  • Terrence and Enzo did a full set of filters and a Guardian for SR2 and SR3.
  • Terrence did health checks on SR2 and SR3.
  • Enzo measured mode Qs.

==== Plan for week of 3/11 =====

  • Mark at Kamioka full week.
  • Enzo at Kamioka Mon, Tue, then JPS.
  • Hirata-san at Kamioka from Monday lunchtime through Friday.
  • Fix BS.
  • Final test of stepper remote enable system (someone in cleanroom checks the lights go on/off).
  • Install/test hardware watchdogs.
  • Continue monitoring SRM yaw drift.
  • More mode Q measurements.
  • Work on Type B paper.

Vacation/Travel Info

  • Enzo at JPS then final vacation, 3/13-29
  • Terrence's last day, 3/29.

KAGRA/Subgroups/VIS/TypeB/Minutes (last edited 2022-10-28 10:02:46 by fabian.arellano)