 * Type B Past Week Summary - weeks of 8/22 and 8/29
  * Fabian, Mark, Zhao-kun and Yokogawa-kun did BS installation at Kamioka:
   * Weighed the BF, SF and dummy BS (in mirror box).
   * Moved the geophones onto the optical table, clamped them down and took another time series for analysis.
   * Aligned the IM, installed the extra trim masses, tested the picos and weighed the whole assembly.
   * Placed vacuum flanges and cleaned D-Sub cables ready for routing to the rack.
   * Realigned and immobilized the optical table (which had been bumped).
   * Made safety improvements on the second floor (new safety rail, new arrangement of floor pieces, caution tape around holes)
   * Suspended the dummy BS. Currently however it is not hanging correctly, but is off in the +Y direction by several mm relative to the mirror box.
   * We set up the BS OL, using one of the wheeled chests of drawers as a base and using the OL breadboard from the PR2 assembly frame.
  * Hirata-san made a 3D assembly model for SR2 and added the optical design.
  * Hirata-san worked with Uchiyama-san to solve the 90° rotation problem. It turns out the "box" part with the pistons can be rotated, so we can build the SR2 according to the original design.
  * Hirata-san investigated the puzzle of the BF-IM maraging rods, where the 2D drawings and 3D CAD do not agree. Fortunately the actual parts seem to agree with the 3D CAD.
  * Hirata-san washed 3 OSEMs (last of initial 10 for BS) and parts for two BFs (for Type A). He moved the BF parts into the clean room and will assemble them with ATC staff from next Wednesday 9/7.
 * Type B ongoing issues
  * Longer cables for BF->PI and SF->PI - RECEIVED
 * Longer term to-do list
  * Decide position of BS rack - DONE
  * Do Inventor assembly for SR2 in chamber and on assembly frame (Hirata) - ONGOING.
  * Write more of payload assembly procedure (Fabian) - ONGOING
  * Write more of BS Assembly Procedure [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]], [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]] (Mark) - ONGOING
  * Lower breadboard installation to be incorporated into the procedure document.
  * Work on BS simulation (Fabian)
  * Do BS Simulink model (Mark, Kokeyama)
  * Do 2D drawings of SR2 parts (Hirata)
  * Redesign SRx IM wire clamps for larger prisms, remachined RMs
  * Order SRM/PRM parts (Hirata/Shoda)
  * Order SRx fasteners (Hirata)
=== Type B (Mark) ===
==== Report for the week of 3/25 ====
 * Mark and Fabian helped Fujii-kun with PR2. The problem turned out to be two broken flags. Hirata-san drew up a design for a jig to help reglue the flags in situ.
 * Fabian documented the height budget for the Type B suspension in the wiki ([[KAGRA/Subgroups/VIS/OpsManual/TypeB/SR3Data]] etc).
 * Terrence wrote up the final version of his OL diagonalization scheme.
 * Terrence worked on L2P decoupling for the TM.
 * Terrence and Mark edited the Type B Guardian to put turning on the payload damping later in the sequence, to help ensure that the OSEMs are not touching by the time they're needed (which can happen if the BF is buoyancy compensated for vacuum but the suspension is vented).
 * Mark started on a big tidy-up of the cleanbooth.
==== Plan for week of 3/25 ====
 * Mark, Fabian at Kamioka Mon-Fri.
 * Assist with PR2.
 * Work on Type B paper.
 * Tidy up.
  * Throw out foil and other garbage.
  * Gather and clean tools.
  * Gather and organize unused parts and fasteners.
  * Return all unused cables to tent.
  * Tidy up cables in rear of SR2 rack.
Line 34: Line 23:
  ==== Vacation/Travel Info ====
 * Enzo's last day 3/29.
 * Terrence's last day for now, 3/29.
 * Mark compensation day for 3/21: 3/29. (He is not really typing these minutes, and anyone who sounds like him in the meeting is an impostor!)
 * Type B going-away party for Terrence/Enzo, 3/29 in Tokyo.
 * Terrence's next visit from 4/18.
 * Fabian's vacation 4/26 to 5/10.
 * Mark's vacation from about 5/22 to 6/11 (TBD).
 * Mark's final day 6/28.

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Report for the week of 3/25

  • Mark and Fabian helped Fujii-kun with PR2. The problem turned out to be two broken flags. Hirata-san drew up a design for a jig to help reglue the flags in situ.
  • Fabian documented the height budget for the Type B suspension in the wiki (KAGRA/Subgroups/VIS/OpsManual/TypeB/SR3Data etc).

  • Terrence wrote up the final version of his OL diagonalization scheme.
  • Terrence worked on L2P decoupling for the TM.
  • Terrence and Mark edited the Type B Guardian to put turning on the payload damping later in the sequence, to help ensure that the OSEMs are not touching by the time they're needed (which can happen if the BF is buoyancy compensated for vacuum but the suspension is vented).
  • Mark started on a big tidy-up of the cleanbooth.

Plan for week of 3/25

  • Mark, Fabian at Kamioka Mon-Fri.
  • Assist with PR2.
  • Work on Type B paper.
  • Tidy up.
    • Throw out foil and other garbage.
    • Gather and clean tools.
    • Gather and organize unused parts and fasteners.
    • Return all unused cables to tent.
    • Tidy up cables in rear of SR2 rack.

Vacation/Travel Info

  • Enzo's last day 3/29.
  • Terrence's last day for now, 3/29.
  • Mark compensation day for 3/21: 3/29. (He is not really typing these minutes, and anyone who sounds like him in the meeting is an impostor!)
  • Type B going-away party for Terrence/Enzo, 3/29 in Tokyo.
  • Terrence's next visit from 4/18.
  • Fabian's vacation 4/26 to 5/10.
  • Mark's vacation from about 5/22 to 6/11 (TBD).
  • Mark's final day 6/28.