Differences between revisions 62 and 143 (spanning 81 versions)
Revision 62 as of 2016-09-02 13:42:20
Size: 2658
Editor: MarkBarton
Comment:
Revision 143 as of 2017-05-18 18:34:50
Size: 3401
Editor: MarkBarton
Comment:
Deletions are marked like this. Additions are marked like this.
Line 5: Line 5:
 * Type B Past Week Summary - weeks of 8/22 and 8/29
  * Fabian, Mark, Zhao-kun and Yokogawa-kun did BS installation at Kamioka:
   * Weighed the BF, SF and dummy BS (in mirror box).
   * Moved the geophones onto the optical table, clamped them down and took another time series for analysis.
   * Aligned the IM, installed the extra trim masses, tested the picos and weighed the whole assembly.
   * Placed vacuum flanges and cleaned D-Sub cables ready for routing to the rack.
   * Realigned and immobilized the optical table (which had been bumped).
   * Made safety improvements on the second floor (new safety rail, new arrangement of floor pieces, caution tape around holes)
   * Suspended the dummy BS. Currently however it is not hanging correctly, but is off in the +Y direction by several mm relative to the mirror box.
   * We set up the BS OL, using one of the wheeled chests of drawers as a base and using the OL breadboard from the PR2 assembly frame.
  * Hirata-san made a 3D assembly model for SR2 and added the optical design.
  * Hirata-san worked with Uchiyama-san to solve the 90° rotation problem. It turns out the "box" part with the pistons can be rotated, so we can build the SR2 according to the original design.
  * Hirata-san investigated the puzzle of the BF-IM maraging rods, where the 2D drawings and 3D CAD do not agree. Fortunately the actual parts seem to agree with the 3D CAD.
  * Hirata-san washed 3 OSEMs (last of initial 10 for BS) and parts for two BFs (for Type A). He moved the BF parts into the clean room and will assemble them with ATC staff from next Wednesday 9/7.
 * Type B ongoing issues
  * Longer cables for BF->PI and SF->PI - RECEIVED
 * Longer term to-do list
  * Decide position of BS rack - DONE
  * Do Inventor assembly for SR2 in chamber and on assembly frame (Hirata) - NEARLY DONE.
  * Write more of payload assembly procedure (Fabian) - ONGOING
  * Write more of BS Assembly Procedure [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]], [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]] (Mark) - ONGOING
  * Lower breadboard installation to be incorporated into the procedure document.
  * Work on BS simulation (Fabian)
  * Do BS Simulink model (Mark, Kokeyama)
  * Do 2D drawings of SR2 parts (Hirata)
  * Redesign SRx IM wire clamps for larger prisms, remachined RMs
  * Order SRM/PRM parts (Hirata/Shoda)
  * Order SRx fasteners (Hirata)
=== Type B (Mark) ===
==== Past week report ====
At Kamioka (Mark, Fabian, Enzo, Perry, Hirata-san):
Line 34: Line 9:
 * We cleared space for the PR2 team to remove a bellows from their tank.
 * We installed safety bars on the pillars near the assembly frame at about waist height for someone on the tall ladder. We reinforced the clamps with cable ties.
 * We bridged a gap in the second floor on the -X side of the SF2 tank with spare floor panels.
 * We removed the PI from the assembly frame.
 * We encountered a problem with the PI-SF rod jamming in the SF. We finally got it out by clamping a pair of vice grips to the rod and hammering. We found that the receptacle part was the right size (7.0 mm) but had been deformed around the edge. Hirata-san used a knife and sandpaper to lean up the edge and then ultrasonically cleaned it.
 * We removed the LLB blade units from the PI, removed the blades from the clamps and sent the blades away for more rework to fix the length problem. Fortunately the tab section at the tip is fairly long, so we can just add a second hole further from the end.
 * We tested the SR fishing rod again, but it would only go up, not down. We found that reseting the driver fixed it, but we also moved the driver boxes into the cleanbooth to reduce the length of the motor cables. (Instead, we had to run some long DC and LAN cables.)
 * We adjusted the limit nut on the SF fishing rod to increase the range.
 * We debugged an issue with the SF keystone sitting lower than previously and found we had accidentally left two eyebolts on top of the BF. We retrimmed the BF/... section to reset the keystone to nominal (65.5 mm) with the fishing rod at mid-range.
 * We removed one segment of the Cu ring on the SF cap and reconfigured the other two to be symmetrical.
 * Fabian designed a layout for the SF damper ring magnets that would work with the modified Cu ring, and placed the magnets with the template. The poles of the magnets were not on the expected faces so we had to stand the magnets up, with the 12x12 faces sideways and the 10x12 mm pole faces up/down. We will need to raise the magnet ring by 2 mm to allow for the extra height.
 * Hirata-san made a cable for the PI v vertical LVDT. We identified the coils by their resistances which were similar to BF/SF: Primary 193Ω, Secondary 75Ω, Actuation 112Ω.
 * We added the remaining cable clamps to the PI (some places had not been accessible with the PI on the frame).
 * We placed the geophones but discovered we didn't have some mounting brackets called out in the 3D CAD.
 * Enzo made a PI yaw/vertical stepper adapter cable and a trial geophone descrambler cable (one of three).
 * We found that part of the problem with the SF LVDT was that the actuation had not been enabled for SF or F0 in the real-time model. We fixed the model and are now able to drive the LVDT actuator and see input at the LVDT sensor.

==== Plan for coming weeks ====
For more detail, see [[KAGRA/Subgroups/VIS/TypeB/ToDo]].

Week of 5/22:
 * Reinstall PI, this time with rods and damper ring.
 * Reinstall PI-SF rod, this time with hex cable clamp.
 * Prepare for PR2 bellows removal on 5/15 (move table with tools).
 * Cable/test PI horizontal LVDTs and steppers.
 * Install/cable/test geophones.

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Past week report

At Kamioka (Mark, Fabian, Enzo, Perry, Hirata-san):

  • We cleared space for the PR2 team to remove a bellows from their tank.
  • We installed safety bars on the pillars near the assembly frame at about waist height for someone on the tall ladder. We reinforced the clamps with cable ties.
  • We bridged a gap in the second floor on the -X side of the SF2 tank with spare floor panels.
  • We removed the PI from the assembly frame.
  • We encountered a problem with the PI-SF rod jamming in the SF. We finally got it out by clamping a pair of vice grips to the rod and hammering. We found that the receptacle part was the right size (7.0 mm) but had been deformed around the edge. Hirata-san used a knife and sandpaper to lean up the edge and then ultrasonically cleaned it.
  • We removed the LLB blade units from the PI, removed the blades from the clamps and sent the blades away for more rework to fix the length problem. Fortunately the tab section at the tip is fairly long, so we can just add a second hole further from the end.
  • We tested the SR fishing rod again, but it would only go up, not down. We found that reseting the driver fixed it, but we also moved the driver boxes into the cleanbooth to reduce the length of the motor cables. (Instead, we had to run some long DC and LAN cables.)
  • We adjusted the limit nut on the SF fishing rod to increase the range.
  • We debugged an issue with the SF keystone sitting lower than previously and found we had accidentally left two eyebolts on top of the BF. We retrimmed the BF/... section to reset the keystone to nominal (65.5 mm) with the fishing rod at mid-range.
  • We removed one segment of the Cu ring on the SF cap and reconfigured the other two to be symmetrical.
  • Fabian designed a layout for the SF damper ring magnets that would work with the modified Cu ring, and placed the magnets with the template. The poles of the magnets were not on the expected faces so we had to stand the magnets up, with the 12x12 faces sideways and the 10x12 mm pole faces up/down. We will need to raise the magnet ring by 2 mm to allow for the extra height.
  • Hirata-san made a cable for the PI v vertical LVDT. We identified the coils by their resistances which were similar to BF/SF: Primary 193Ω, Secondary 75Ω, Actuation 112Ω.
  • We added the remaining cable clamps to the PI (some places had not been accessible with the PI on the frame).
  • We placed the geophones but discovered we didn't have some mounting brackets called out in the 3D CAD.
  • Enzo made a PI yaw/vertical stepper adapter cable and a trial geophone descrambler cable (one of three).
  • We found that part of the problem with the SF LVDT was that the actuation had not been enabled for SF or F0 in the real-time model. We fixed the model and are now able to drive the LVDT actuator and see input at the LVDT sensor.

Plan for coming weeks

For more detail, see KAGRA/Subgroups/VIS/TypeB/ToDo.

Week of 5/22:

  • Reinstall PI, this time with rods and damper ring.
  • Reinstall PI-SF rod, this time with hex cable clamp.
  • Prepare for PR2 bellows removal on 5/15 (move table with tools).
  • Cable/test PI horizontal LVDTs and steppers.
  • Install/cable/test geophones.

KAGRA/Subgroups/VIS/TypeB/Minutes (last edited 2022-10-28 10:02:46 by fabian.arellano)