 * Type B Past Week Summary - weeks of 8/22 and 8/29
  * Fabian, Mark, Zhao-kun and Yokogawa-kun did BS installation at Kamioka:
   * Weighed the BF, SF and dummy BS (in mirror box).
   * Moved the geophones onto the optical table, clamped them down and took another time series for analysis.
   * Aligned the IM, installed the extra trim masses, tested the picos and weighed the whole assembly.
   * Placed vacuum flanges and cleaned D-Sub cables ready for routing to the rack.
   * Realigned and immobilized the optical table (which had been bumped).
   * Made safety improvements on the second floor (new safety rail, new arrangement of floor pieces, caution tape around holes)
   * Suspended the dummy BS. Currently however it is not hanging correctly, but is off in the +Y direction by several mm relative to the mirror box.
   * We set up the BS OL, using one of the wheeled chests of drawers as a base and using the OL breadboard from the PR2 assembly frame.
  * Hirata-san made a 3D assembly model for SR2 and added the optical design.
  * Hirata-san worked with Uchiyama-san to solve the 90° rotation problem. It turns out the "box" part with the pistons can be rotated, so we can build the SR2 according to the original design.
  * Hirata-san investigated the puzzle of the BF-IM maraging rods, where the 2D drawings and 3D CAD do not agree. Fortunately the actual parts seem to agree with the 3D CAD.
  * Hirata-san washed 3 OSEMs (last of initial 10 for BS) and parts for two BFs (for Type A). He moved the BF parts into the clean room and will assemble them with ATC staff from next Wednesday 9/7.
 * Type B ongoing issues
  * Longer cables for BF->PI and SF->PI - RECEIVED
 * Longer term to-do list
  * Decide position of BS rack - DONE
  * Do Inventor assembly for SR2 in chamber and on assembly frame (Hirata) - NEARLY DONE.
  * Write more of payload assembly procedure (Fabian) - ONGOING
  * Write more of BS Assembly Procedure [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]], [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]] (Mark) - ONGOING
  * Lower breadboard installation to be incorporated into the procedure document.
  * Work on BS simulation (Fabian)
  * Do BS Simulink model (Mark, Kokeyama)
  * Do 2D drawings of SR2 parts (Hirata)
  * Redesign SRx IM wire clamps for larger prisms, remachined RMs
  * Order SRM/PRM parts (Hirata/Shoda)
  * Order SRx fasteners (Hirata)
=== Type B (Mark) ===
==== Past week report ====
At Kamioka (Mark, Enzo, Yoshioka-kun):
 * We experimented with rearranging the arc weights to accommodate the magic wands and came up with a suitable scheme.
 * We used spare arc weights as extra ballast on the LBB to get it to float, and measured the height for a known load.
 * We put the blocks back under the LBB and unhooked it.
 * We moved the suspension from the tank back to the assembly frame.
 * We craned the LBB rings down onto the LBB but did not remove them yet. (This however is the last crane work in the tank until reinstallation, so the lid does not have to come off again and the pallet can be used for the PI.)
 * We put the crossbars back in the assembly frame underneath the SF and BF (and corrected an error in the height of the BF ones).
 * Enzo started setting up the SR3 rack (with help from Yamamoto-san).
 * We received the real BS optic and gluing tools, and glued the disks and rods into the modified magnet jigs. We also tried the re-made secondary prisms in the gluing jigs and made shims to hold them more securely.
Line 34: Line 17:
  At Mitaka (Fabian and Hirata-san):
 * Hirata-san shipped the optic and gluing tools to Kamioka.
 * Hirata-san did drawings and RFQs for IM/BF/SF ballast masses
 * Fabian worked on the SRx assembly frame.

==== Plan for week of 7/18 ====
Full team at Kamioka from Tue-Fri, except Hirata-san (Tue-Wed only).
 * Glue prisms/magnets on BS.
 * Dismantle suspension.
 * Finish setting up filter service area (mostly already done by Mirapro).
 * Move BF to filter service area.

==== Plan for week of 7/24 ====
Full team at Kamioka from Mon-Fri, except Hirata-san (Tue-Fri) and Enzo (vacation).
 * Recheck alignment of assembly frame and centering of optical table.
 * Install IM, suspend BS and RM.

Vacation Info:
Hirata-san: Thu 7/20 through Mon 7/24
Enzo: Sat 7/22 through Sun 8/6
Fabian: Fri 8/4 through Mon 8/21
Mark: TBD Mid-Oct

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Past week report

At Kamioka (Mark, Enzo, Yoshioka-kun):

  • We experimented with rearranging the arc weights to accommodate the magic wands and came up with a suitable scheme.
  • We used spare arc weights as extra ballast on the LBB to get it to float, and measured the height for a known load.
  • We put the blocks back under the LBB and unhooked it.
  • We moved the suspension from the tank back to the assembly frame.
  • We craned the LBB rings down onto the LBB but did not remove them yet. (This however is the last crane work in the tank until reinstallation, so the lid does not have to come off again and the pallet can be used for the PI.)
  • We put the crossbars back in the assembly frame underneath the SF and BF (and corrected an error in the height of the BF ones).
  • Enzo started setting up the SR3 rack (with help from Yamamoto-san).
  • We received the real BS optic and gluing tools, and glued the disks and rods into the modified magnet jigs. We also tried the re-made secondary prisms in the gluing jigs and made shims to hold them more securely.

At Mitaka (Fabian and Hirata-san):

  • Hirata-san shipped the optic and gluing tools to Kamioka.
  • Hirata-san did drawings and RFQs for IM/BF/SF ballast masses
  • Fabian worked on the SRx assembly frame.

Plan for week of 7/18

Full team at Kamioka from Tue-Fri, except Hirata-san (Tue-Wed only).

  • Glue prisms/magnets on BS.
  • Dismantle suspension.
  • Finish setting up filter service area (mostly already done by Mirapro).
  • Move BF to filter service area.

Plan for week of 7/24

Full team at Kamioka from Mon-Fri, except Hirata-san (Tue-Fri) and Enzo (vacation).

  • Recheck alignment of assembly frame and centering of optical table.
  • Install IM, suspend BS and RM.

Vacation Info: Hirata-san: Thu 7/20 through Mon 7/24 Enzo: Sat 7/22 through Sun 8/6 Fabian: Fri 8/4 through Mon 8/21 Mark: TBD Mid-Oct