Differences between revisions 62 and 183 (spanning 121 versions)
Revision 62 as of 2016-09-02 13:42:20
Size: 2658
Editor: MarkBarton
Comment:
Revision 183 as of 2017-09-01 13:47:28
Size: 2134
Editor: MarkBarton
Comment:
Deletions are marked like this. Additions are marked like this.
Line 5: Line 5:
 * Type B Past Week Summary - weeks of 8/22 and 8/29
  * Fabian, Mark, Zhao-kun and Yokogawa-kun did BS installation at Kamioka:
   * Weighed the BF, SF and dummy BS (in mirror box).
   * Moved the geophones onto the optical table, clamped them down and took another time series for analysis.
   * Aligned the IM, installed the extra trim masses, tested the picos and weighed the whole assembly.
   * Placed vacuum flanges and cleaned D-Sub cables ready for routing to the rack.
   * Realigned and immobilized the optical table (which had been bumped).
   * Made safety improvements on the second floor (new safety rail, new arrangement of floor pieces, caution tape around holes)
   * Suspended the dummy BS. Currently however it is not hanging correctly, but is off in the +Y direction by several mm relative to the mirror box.
   * We set up the BS OL, using one of the wheeled chests of drawers as a base and using the OL breadboard from the PR2 assembly frame.
  * Hirata-san made a 3D assembly model for SR2 and added the optical design.
  * Hirata-san worked with Uchiyama-san to solve the 90° rotation problem. It turns out the "box" part with the pistons can be rotated, so we can build the SR2 according to the original design.
  * Hirata-san investigated the puzzle of the BF-IM maraging rods, where the 2D drawings and 3D CAD do not agree. Fortunately the actual parts seem to agree with the 3D CAD.
  * Hirata-san washed 3 OSEMs (last of initial 10 for BS) and parts for two BFs (for Type A). He moved the BF parts into the clean room and will assemble them with ATC staff from next Wednesday 9/7.
 * Type B ongoing issues
  * Longer cables for BF->PI and SF->PI - RECEIVED
 * Longer term to-do list
  * Decide position of BS rack - DONE
  * Do Inventor assembly for SR2 in chamber and on assembly frame (Hirata) - NEARLY DONE.
  * Write more of payload assembly procedure (Fabian) - ONGOING
  * Write more of BS Assembly Procedure [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]], [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]] (Mark) - ONGOING
  * Lower breadboard installation to be incorporated into the procedure document.
  * Work on BS simulation (Fabian)
  * Do BS Simulink model (Mark, Kokeyama)
  * Do 2D drawings of SR2 parts (Hirata)
  * Redesign SRx IM wire clamps for larger prisms, remachined RMs
  * Order SRM/PRM parts (Hirata/Shoda)
  * Order SRx fasteners (Hirata)
=== Type B (Mark) ===
==== Past week report ====
At Kamioka (Mark, Ohishi-san, Fabian, Enzo, Hirata-san, Yoshioka-kun, Kozu-kun):
 * We solved the problem with the OSEMs: cables had been plugged into the confusingly named "PD current monitor" outputs (actually LED current monitors), not the "OSEM outputs".
 * We solved a problem with the real-time model freezing which turned out to be the IO chassis having lost power.
 * We took some mass off the IM to allow for the weight of the cables, and readjusted it in pitch and roll.
 * We aligned the IRM to the IM and set the OSEMs to mid-range.
 * We added ballast to the BF.
 * We changed the receptacles for the SF-BF rod. The low receptacle did not fit properly into the BF keystone and Hirata-san had to file it.
 * We fixed a broken wire on the BF yaw pico, retested the pico and added the BF cap.
 * We cabled and tested the BF cap picos.
 * We lifted the BF and weighed and balanced it.
 * We installed the SF ring and brought in the SF.
 * We cabled the SF LVDT and did a quick test (not a full calibration).
 * We replaced non-vacuum compatible cables in the PI, removed various sticky labels and wiped it with ethanol.
 * We tried to hook the SF-BF rod but found the hole in the hex cable clamp was too small for the 8 mm rod head. We enlarged the hole but then found the PEEK pieces were too loose. We tried using foil, but then managed to lose a PEEK piece into the BF, so we will need to remove the cap of the BF to get it.
Line 34: Line 22:
  ==== Plan for week of 8/28 ====
Kamioka: Mark (except Tue), Ohishi-san, Fabian (except Tue), Enzo (except Tue), Hirata-san, Yoshioka-kun (Fri), Kozu-kun (Thu, Fri).
 * Fix/adjust IRM OSEMs.
 * Add BF cap; cable and test BF-1 and BF-2 picos.
 * Lift and weigh BF/IRM/IM/RM/BS; adjust ballast mass.
 * Crane in SF.
 * Suspend BF/IRM/IM/RM/BS.

==== Plan for week of 9/4 ====
 * Install SF cap; route cables.
 * Lift and weigh SF/BF/IRM/IM/RM/BS.
 * Adjust SF ballast.

==== Vacation Info ====
Mark: TBD Mid-Oct

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Past week report

At Kamioka (Mark, Ohishi-san, Fabian, Enzo, Hirata-san, Yoshioka-kun, Kozu-kun):

  • We solved the problem with the OSEMs: cables had been plugged into the confusingly named "PD current monitor" outputs (actually LED current monitors), not the "OSEM outputs".
  • We solved a problem with the real-time model freezing which turned out to be the IO chassis having lost power.
  • We took some mass off the IM to allow for the weight of the cables, and readjusted it in pitch and roll.
  • We aligned the IRM to the IM and set the OSEMs to mid-range.
  • We added ballast to the BF.
  • We changed the receptacles for the SF-BF rod. The low receptacle did not fit properly into the BF keystone and Hirata-san had to file it.
  • We fixed a broken wire on the BF yaw pico, retested the pico and added the BF cap.
  • We cabled and tested the BF cap picos.
  • We lifted the BF and weighed and balanced it.
  • We installed the SF ring and brought in the SF.
  • We cabled the SF LVDT and did a quick test (not a full calibration).
  • We replaced non-vacuum compatible cables in the PI, removed various sticky labels and wiped it with ethanol.
  • We tried to hook the SF-BF rod but found the hole in the hex cable clamp was too small for the 8 mm rod head. We enlarged the hole but then found the PEEK pieces were too loose. We tried using foil, but then managed to lose a PEEK piece into the BF, so we will need to remove the cap of the BF to get it.

Plan for week of 8/28

Kamioka: Mark (except Tue), Ohishi-san, Fabian (except Tue), Enzo (except Tue), Hirata-san, Yoshioka-kun (Fri), Kozu-kun (Thu, Fri).

  • Fix/adjust IRM OSEMs.
  • Add BF cap; cable and test BF-1 and BF-2 picos.
  • Lift and weigh BF/IRM/IM/RM/BS; adjust ballast mass.
  • Crane in SF.
  • Suspend BF/IRM/IM/RM/BS.

Plan for week of 9/4

  • Install SF cap; route cables.
  • Lift and weigh SF/BF/IRM/IM/RM/BS.
  • Adjust SF ballast.

Vacation Info

Mark: TBD Mid-Oct

KAGRA/Subgroups/VIS/TypeB/Minutes (last edited 2022-10-28 10:02:46 by fabian.arellano)