Line 5: Line 5:
 * Type B Past Week Summary - weeks of 8/22 and 8/29
  * Fabian, Mark, Zhao-kun and Yokogawa-kun did BS installation at Kamioka:
   * Weighed the BF, SF and dummy BS (in mirror box).
   * Moved the geophones onto the optical table, clamped them down and took another time series for analysis.
   * Aligned the IM, installed the extra trim masses, tested the picos and weighed the whole assembly.
   * Placed vacuum flanges and cleaned D-Sub cables ready for routing to the rack.
   * Realigned and immobilized the optical table (which had been bumped).
   * Made safety improvements on the second floor (new safety rail, new arrangement of floor pieces, caution tape around holes)
   * Suspended the dummy BS. Currently however it is not hanging correctly, but is off in the +Y direction by several mm relative to the mirror box.
   * We set up the BS OL, using one of the wheeled chests of drawers as a base and using the OL breadboard from the PR2 assembly frame.
  * Hirata-san made a 3D assembly model for SR2 and added the optical design.
  * Hirata-san worked with Uchiyama-san to solve the 90° rotation problem. It turns out the "box" part with the pistons can be rotated, so we can build the SR2 according to the original design.
  * Hirata-san investigated the puzzle of the BF-IM maraging rods, where the 2D drawings and 3D CAD do not agree. Fortunately the actual parts seem to agree with the 3D CAD.
  * Hirata-san washed 3 OSEMs (last of initial 10 for BS) and parts for two BFs (for Type A). He moved the BF parts into the clean room and will assemble them with ATC staff from next Wednesday 9/7.
 * Type B ongoing issues
  * Longer cables for BF->PI and SF->PI - RECEIVED
 * Longer term to-do list
  * Decide position of BS rack - DONE
  * Do Inventor assembly for SR2 in chamber and on assembly frame (Hirata) - NEARLY DONE.
  * Write more of payload assembly procedure (Fabian) - ONGOING
  * Write more of BS Assembly Procedure [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]], [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]] (Mark) - ONGOING
  * Lower breadboard installation to be incorporated into the procedure document.
  * Work on BS simulation (Fabian)
  * Do BS Simulink model (Mark, Kokeyama)
  * Do 2D drawings of SR2 parts (Hirata)
  * Redesign SRx IM wire clamps for larger prisms, remachined RMs
  * Order SRM/PRM parts (Hirata/Shoda)
  * Order SRx fasteners (Hirata)
=== Type B (Mark) ===
==== Past week report ====
At Kamioka (Mark, Ohishi-san, Fabian, Enzo, Hirata-san, Yoshioka-kun, Kozu-kun):
 * We put lock nuts on the F0 FR and calibrated the F0 LVDT against FR position and keystone height.
 * Enzo traced the issue with the geophones to a specific cable.
 * We measured the BF and F0 GAS resonant frequencies.
 * We adjusted the spacing of the SR damper.
 * We double-checked the BS pitch with the OL.
 * We debugged the PI yaw mechanism. We managed to get the return spring properly adjusted, but the stepper motor tends to jam because of the strange design.
 * '''We prepared the suspension for lifting and craned it into the tank.'''
 * Hirata-san fixed an issue with one of the nailheads on the LBB intermediate ring support rods not properly seating, by removing the rod and reinstalling it upside down (with the problem nailhead in a less critical position).
 * Enzo and team moved all the in-air cables from the assembly frame to the tank.
 * Fabian and Ohishi-san unlocked the bottom section of the suspension and got it hanging freely.
 
==== Plan for week of 9/25 ====
Mark, Fabian, Enzo (Mon, Tue), Ohishi-san (Tue, Fri), Hirata-san, Yoshioka-kun (Tue, Wed, Fri), Kozu-kun
 * Finish moving in-air cabling and feedthroughs and reconnect in-vacuum cables (through Cu O-rings).
 * Unlock rest of suspension and readjust.
 * Debug electronics.
 * Unclamp LBB ring "sandwich" so LBB Cu ring is suspended on upper rods.
 * Install LBB lower rods and hook LBB.
 * Adjust LBB damper Cu-magnet gap.
 * Measure required ballast for LBB.
 * Remove First Contact, try OL.
 * Prepare for SR2 work.
Line 34: Line 31:
  ==== Plan for week of 10/2 ====
Kamioka: Mark, Enzo, Fabian, Ohishi-san.
 * TFs etc.
Mitaka: Hirata-san?
 * SF design/purchasing.

==== Vacation Info ====
Mark: 10/16-24
Enzo: 9/27-29

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Past week report

At Kamioka (Mark, Ohishi-san, Fabian, Enzo, Hirata-san, Yoshioka-kun, Kozu-kun):

  • We put lock nuts on the F0 FR and calibrated the F0 LVDT against FR position and keystone height.
  • Enzo traced the issue with the geophones to a specific cable.
  • We measured the BF and F0 GAS resonant frequencies.
  • We adjusted the spacing of the SR damper.
  • We double-checked the BS pitch with the OL.
  • We debugged the PI yaw mechanism. We managed to get the return spring properly adjusted, but the stepper motor tends to jam because of the strange design.
  • We prepared the suspension for lifting and craned it into the tank.

  • Hirata-san fixed an issue with one of the nailheads on the LBB intermediate ring support rods not properly seating, by removing the rod and reinstalling it upside down (with the problem nailhead in a less critical position).
  • Enzo and team moved all the in-air cables from the assembly frame to the tank.
  • Fabian and Ohishi-san unlocked the bottom section of the suspension and got it hanging freely.

Plan for week of 9/25

Mark, Fabian, Enzo (Mon, Tue), Ohishi-san (Tue, Fri), Hirata-san, Yoshioka-kun (Tue, Wed, Fri), Kozu-kun

  • Finish moving in-air cabling and feedthroughs and reconnect in-vacuum cables (through Cu O-rings).
  • Unlock rest of suspension and readjust.
  • Debug electronics.
  • Unclamp LBB ring "sandwich" so LBB Cu ring is suspended on upper rods.
  • Install LBB lower rods and hook LBB.
  • Adjust LBB damper Cu-magnet gap.
  • Measure required ballast for LBB.
  • Remove First Contact, try OL.
  • Prepare for SR2 work.

Plan for week of 10/2

Kamioka: Mark, Enzo, Fabian, Ohishi-san.

  • TFs etc.

Mitaka: Hirata-san?

  • SF design/purchasing.

Vacation Info

Mark: 10/16-24 Enzo: 9/27-29