 * Type B Past Week Summary
  * Fabian, Mark, Yokogawa-kun and Kuwahara-kun did BS installation at Kamioka:
   * Calculated BS pitch correction ([[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5630|JGW-T1605630]])
   * Hung dummy optic and set pitch.
   * Prepared RM.
   * Placed vacuum feedthroughs on assembly frame and cleaned D-Sub cables.
   * Decided position of BS rack with Miyakawa-san.
   * Measured maraging rods.
  * Hirata-san made a 3D assembly model for SR2 and added the optical design.
  * Hirata-san worked with Uchiyama-san to solve the 90° rotation problem. It turns out the "box" part with the pistons can be rotated, so we can build the SR2 according to the original design.
  * Hirata-san investigated the puzzle of the BF-IM maraging rods, where the 2D drawings and 3D CAD do not agree. Fortunately the actual parts seem to agree with the 3D CAD.
  * Hirata-san washed 3 OSEMs (last of initial 10 for BS) and parts for two BFs (for Type A). He moved the BF parts into the clean room and will assemble them with ATC staff from next Wednesday 9/7.
 * Type B ongoing issues
  * Longer cables for BF->PI and SF->PI - RECEIVED
 * Longer term to-do list
  * Decide position of BS rack - DONE
  * Do Inventor assembly for SR2 in chamber and on assembly frame (Hirata) - NEARLY DONE.
  * Write more of payload assembly procedure (Fabian) - ONGOING
  * Write more of BS Assembly Procedure [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]], [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]] (Mark) - ONGOING
  * Lower breadboard installation to be incorporated into the procedure document.
  * Work on BS simulation (Fabian)
  * Do BS Simulink model (Mark, Kokeyama)
  * Do 2D drawings of SR2 parts (Hirata)
  * Redesign SRx IM wire clamps for larger prisms, remachined RMs
  * Order SRM/PRM parts (Hirata/Shoda)
  * Order SRx fasteners (Hirata)
=== Type B (Mark) ===
==== Report for week of 3/5 ====
 * We removed the non-vacuum-compatible ballast mass from the BS tank.
 * We secured all the PR2 feedthrough connections with screws.
 * We grabbed an extra empty rack for SRM and set it up next to the one for SR3 (we will stuff them next week).
 * We calibrated the SR2 SF LVDT and FR.
 * We put the SF cap on and lifted and weighed the SF/... section.
 * We moved the filter building bench and tools into the SRM area and started the rebuild of the two remaining BFs (the one from the BS Test Hang and the one with the tilted keystone).
 * Mark finished -v2 of the schedule ([[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7779| L1807779]]).
 * Mark worked on slides for the ASJ and LVC meetings.
 * Sawada-san postponed the SRM mushroom work to next week and offloaded it to Mirapro.
Line 32: Line 17:
  ==== Plan for week of ====
 * Shoda-san at Mitaka.
 * Hirata-san vacation Mon 3/5, then Kamioka
 * Fabian Mitaka Mon-Tue (COMSOL training), Kamioka Wed-Fri.
 * Others at Kamioka.
 * -
 * '''Remove LBB temporary ballast masses from BS chamber.'''
 * Finish recovering IM OSEM alignment.
 * Calibrate SF LVDT.
 * Lift SF/... section and check total mass and balance.
 * Get SRM tank mushroom section installed (Hirata-san, Kimura-san)
 * Set up for rebuilding of two BFs.

==== Plan for week of 3/12 ====
 * Shoda-san at Mitaka.
 * Mark at ASJ (Chiba) Fri, then Mitaka.
 * Hirata-san vacation Mon 3/5; Kamioka Tue-Thu; Mitaka Fri
 * Others Kamioka Mon-Thu
 * Install boxes in SR3 and SRM racks.
 * Lay SR3 in-air cabling.
 * Continue rebuild of BFs.

==== Plan for week of 3/19 ====
 * Mark at LVC meeting
 * All others at Mitaka
 * Make two sets of IM OSEMs
 * Make last in-air pico adapter cable
 * Make three in-air stepper splitter cables for SR2, SR3 and SRM.
 * Set up Dummy BS prism removal.

==== Plan for week of 3/26 ====
 * Mark vacation.
 * Shoda-san at Mitaka
 * Others at Kamioka
 * --
 * F0 Prototype Blade Test
  * Characterize blades.
  * Choose best set of three.
  * Remove cracked blades from filter in SRM area.
  * Set up test weights in SRM area, first floor.
  * Remove floor panel in SRM area, second floor.
  * Install chosen blades.
  * Measure load capacity.

==== To-Do Lists, Schedule ====
 * [[KAGRA/Subgroups/VIS/TypeB/March2018]]
 * [[KAGRA/Subgroups/VIS/TypeB/April2018]]
 * [[KAGRA/Subgroups/VIS/TypeB/ToDoBS]]
 * [[KAGRA/Subgroups/VIS/TypeB/ToDoSR]]
 * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7779|JGW-L1807779-v1 Type B Schedule (SR)]]

==== Vacation Info ====
 * Mark at LVC, then vacation, 3/18 (Sun) - 4/1 (Sun)
 * Hirata-san vacation, Mon 3/5.
 * Fabian vacation, 3/26-4/27 (then gone).

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Report for week of 3/5

  • We removed the non-vacuum-compatible ballast mass from the BS tank.
  • We secured all the PR2 feedthrough connections with screws.
  • We grabbed an extra empty rack for SRM and set it up next to the one for SR3 (we will stuff them next week).
  • We calibrated the SR2 SF LVDT and FR.
  • We put the SF cap on and lifted and weighed the SF/... section.
  • We moved the filter building bench and tools into the SRM area and started the rebuild of the two remaining BFs (the one from the BS Test Hang and the one with the tilted keystone).
  • Mark finished -v2 of the schedule (L1807779).

  • Mark worked on slides for the ASJ and LVC meetings.
  • Sawada-san postponed the SRM mushroom work to next week and offloaded it to Mirapro.

Plan for week of

  • Shoda-san at Mitaka.
  • Hirata-san vacation Mon 3/5, then Kamioka
  • Fabian Mitaka Mon-Tue (COMSOL training), Kamioka Wed-Fri.
  • Others at Kamioka.
  • -
  • Remove LBB temporary ballast masses from BS chamber.

  • Finish recovering IM OSEM alignment.
  • Calibrate SF LVDT.
  • Lift SF/... section and check total mass and balance.
  • Get SRM tank mushroom section installed (Hirata-san, Kimura-san)
  • Set up for rebuilding of two BFs.

Plan for week of 3/12

  • Shoda-san at Mitaka.
  • Mark at ASJ (Chiba) Fri, then Mitaka.
  • Hirata-san vacation Mon 3/5; Kamioka Tue-Thu; Mitaka Fri
  • Others Kamioka Mon-Thu
  • Install boxes in SR3 and SRM racks.
  • Lay SR3 in-air cabling.
  • Continue rebuild of BFs.

Plan for week of 3/19

  • Mark at LVC meeting
  • All others at Mitaka
  • Make two sets of IM OSEMs
  • Make last in-air pico adapter cable
  • Make three in-air stepper splitter cables for SR2, SR3 and SRM.
  • Set up Dummy BS prism removal.

Plan for week of 3/26

  • Mark vacation.
  • Shoda-san at Mitaka
  • Others at Kamioka
  • --
  • F0 Prototype Blade Test
    • Characterize blades.
    • Choose best set of three.
    • Remove cracked blades from filter in SRM area.
    • Set up test weights in SRM area, first floor.
    • Remove floor panel in SRM area, second floor.
    • Install chosen blades.
    • Measure load capacity.

To-Do Lists, Schedule

Vacation Info

  • Mark at LVC, then vacation, 3/18 (Sun) - 4/1 (Sun)
  • Hirata-san vacation, Mon 3/5.
  • Fabian vacation, 3/26-4/27 (then gone).