Line 5: Line 5:
 * Type B Past Week Summary
  * Fabian, Mark, Yokogawa-kun and Kuwahara-kun did BS installation at Kamioka:
   * Calculated BS pitch correction ([[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5630|JGW-T1605630]])
   * Hung dummy optic and set pitch.
   * Prepared RM.
   * Placed vacuum feedthroughs on assembly frame and cleaned D-Sub cables.
   * Decided position of BS rack with Miyakawa-san.
   * Measured maraging rods.
  * Hirata-san made a 3D assembly model for SR2 and added the optical design.
  * Hirata-san worked with Uchiyama-san to solve the 90° rotation problem. It turns out the "box" part with the pistons can be rotated, so we can build the SR2 according to the original design.
  * Hirata-san investigated the puzzle of the BF-IM maraging rods, where the 2D drawings and 3D CAD do not agree. Fortunately the actual parts seem to agree with the 3D CAD.
  * Hirata-san washed 3 OSEMs (last of initial 10 for BS) and parts for two BFs (for Type A). He moved the BF parts into the clean room and will assemble them with ATC staff from next Wednesday 9/7.
 * Type B ongoing issues
  * Longer cables for BF->PI and SF->PI - RECEIVED
 * Longer term to-do list
  * Decide position of BS rack - DONE
  * Do Inventor assembly for SR2 in chamber and on assembly frame (Hirata) - NEARLY DONE.
  * Write more of payload assembly procedure (Fabian) - ONGOING
  * Write more of BS Assembly Procedure [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]], [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]] (Mark) - ONGOING
  * Lower breadboard installation to be incorporated into the procedure document.
  * Work on BS simulation (Fabian)
  * Do BS Simulink model (Mark, Kokeyama)
  * Do 2D drawings of SR2 parts (Hirata)
  * Redesign SRx IM wire clamps for larger prisms, remachined RMs
  * Order SRM/PRM parts (Hirata/Shoda)
  * Order SRx fasteners (Hirata)
=== Type B (Mark) ===
==== Report for week of 10/15 ====
===== SRM =====
 * We received the fourth feedthrough we had been waiting for and installed it on the AF.
 * Fabian added the cables between the FE computer and the ADC/DAC boxes, and we checked that we were getting IO in the real-time model.
 * Fabian and Enzo connected up the Sat Amps.
 * Fabian double-checked the optic pitch, got the IRM nicely aligned to the IM, cabled IM OSEMs V1, V2, V3 and H1, and adjusted those OSEMs in/out to midrange.
 * Hirata-san set the compression on the F0 to 30 mm and measured the height and frequency as a function of load. He then fixed a loose screw on one of the blade tips and repeated the measurement. The frequency was fairly constant at around 0.5, which will do. He did a mass budget and chose a F1 CuBe spring. We may do a tiny bit more compression if the frequency degrades, and/or choose an even stronger spring if the load capacity is not enough.
 * Hirata-san took apart and reassembled one of the LBB blade units, which had a badly seated blade.
 * Hirata-san put cable clamps on the SF and on the PI. We are very short on the PEEK clamp pieces, so he scavenged some from SR2.
 * We added a new LAN hub for SRM, and configured two stepper drivers as SRM_IP and SRM_GAS.
 * Late in the week we received extra Type 3-4 cables (thanks to Sato-san for expediting) and were able to cable IM OSEMs H2 and H3, and the BF LVDT.
 * Enzo made a new batch of feedthrough adapters.
===== SR2 =====
 * We finalized the geophone cabling and reinstalled the geophones.
 * We received the new arc weights, and used some of them to install a basic allotment of 6 38-mm weights on SR3 per the CAD. We then added two extra 19-mm arc weights for tuning and got a good IP frequency of 0.133 Hz.
 * Apart from the F0 yaw stepper issue and the OL, the SR2 is now more-or-less complete and adjusted mechanically, and just needs software work (control loops etc). We will however have to borrow one of the geophones at some point to do a huddle test with the final batch of new geophones (including those for SRM). Terrence can set up the OL in the week of 10/29.
==== Plan for week of 10/22 ====
 * Friday is NAOJ Open Day Prep - no Kamioka work.
 * Mark and Fabian at Kamioka Mon-Thu.
 * Enzo and Hirata-san at Kamioka Tue-Thu.
===== SR2 =====
 * Do a measurement of how much torque is required on the F0 keystone to move the system in yaw. (This will help Sato-san choose a suitable stepper driver for the new design.)
 * Continue shakedown.
 * Gather parts for the OL (with help from Simon).
===== SRM =====
 * Scavenge HPCDs from SR2 and SR3 (currently we only have one for SRM) and organize to get LPCDs modified.
 * Suspend/weigh/balance the BF/... section.
 * Build up the AF and SS to the SF level.
 * Install the SF.
==== Plan for week of 10/29 ====
 * Mark, Enzo, Hirata-san, Fabian and Terrence at Kamioka Mon-Fri.
===== SR2 =====
 * Set up OL.
===== SRM =====
 * Continue assembly.
==== To-Do Lists, Schedule ====
 * [[KAGRA/Subgroups/VIS/TypeB/ToDoBS]]
 * [[KAGRA/Subgroups/VIS/TypeB/ToDoSR]]
 * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7779|JGW-L1807779 Type B Schedule (SR)]]
Line 32: Line 46:
  ==== Vacation/Visitor Info ====
 * Terrence: 10/29-11/2 at Kamioka.

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Report for week of 10/15

SRM
  • We received the fourth feedthrough we had been waiting for and installed it on the AF.
  • Fabian added the cables between the FE computer and the ADC/DAC boxes, and we checked that we were getting IO in the real-time model.
  • Fabian and Enzo connected up the Sat Amps.
  • Fabian double-checked the optic pitch, got the IRM nicely aligned to the IM, cabled IM OSEMs V1, V2, V3 and H1, and adjusted those OSEMs in/out to midrange.
  • Hirata-san set the compression on the F0 to 30 mm and measured the height and frequency as a function of load. He then fixed a loose screw on one of the blade tips and repeated the measurement. The frequency was fairly constant at around 0.5, which will do. He did a mass budget and chose a F1 CuBe spring. We may do a tiny bit more compression if the frequency degrades, and/or choose an even stronger spring if the load capacity is not enough.

  • Hirata-san took apart and reassembled one of the LBB blade units, which had a badly seated blade.
  • Hirata-san put cable clamps on the SF and on the PI. We are very short on the PEEK clamp pieces, so he scavenged some from SR2.
  • We added a new LAN hub for SRM, and configured two stepper drivers as SRM_IP and SRM_GAS.
  • Late in the week we received extra Type 3-4 cables (thanks to Sato-san for expediting) and were able to cable IM OSEMs H2 and H3, and the BF LVDT.
  • Enzo made a new batch of feedthrough adapters.

SR2
  • We finalized the geophone cabling and reinstalled the geophones.
  • We received the new arc weights, and used some of them to install a basic allotment of 6 38-mm weights on SR3 per the CAD. We then added two extra 19-mm arc weights for tuning and got a good IP frequency of 0.133 Hz.
  • Apart from the F0 yaw stepper issue and the OL, the SR2 is now more-or-less complete and adjusted mechanically, and just needs software work (control loops etc). We will however have to borrow one of the geophones at some point to do a huddle test with the final batch of new geophones (including those for SRM). Terrence can set up the OL in the week of 10/29.

Plan for week of 10/22

  • Friday is NAOJ Open Day Prep - no Kamioka work.
  • Mark and Fabian at Kamioka Mon-Thu.
  • Enzo and Hirata-san at Kamioka Tue-Thu.

SR2
  • Do a measurement of how much torque is required on the F0 keystone to move the system in yaw. (This will help Sato-san choose a suitable stepper driver for the new design.)
  • Continue shakedown.
  • Gather parts for the OL (with help from Simon).

SRM
  • Scavenge HPCDs from SR2 and SR3 (currently we only have one for SRM) and organize to get LPCDs modified.
  • Suspend/weigh/balance the BF/... section.
  • Build up the AF and SS to the SF level.
  • Install the SF.

Plan for week of 10/29

  • Mark, Enzo, Hirata-san, Fabian and Terrence at Kamioka Mon-Fri.

SR2
  • Set up OL.

SRM
  • Continue assembly.

To-Do Lists, Schedule

Vacation/Visitor Info

  • Terrence: 10/29-11/2 at Kamioka.