Line 6: Line 6:
  * Fabian, Mark, Yokogawa-kun and Kuwahara-kun did BS installation at Kamioka:
   * Calculated BS pitch correction ([[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5630|JGW-T1605630]])
   * Hung dummy optic and set pitch.
   * Prepared RM.
   * Placed vacuum feedthroughs on assembly frame and cleaned D-Sub cables.
   * Decided position of BS rack with Miyakawa-san.
   * Measured maraging rods.
  * Hirata-san made a 3D assembly model for SR2 and added the optical design.
  * Hirata-san worked with Uchiyama-san to solve the 90° rotation problem. It turns out the "box" part with the pistons can be rotated, so we can build the SR2 according to the original design.
  * Hirata-san investigated the puzzle of the BF-IM maraging rods, where the 2D drawings and 3D CAD do not agree. Fortunately the actual parts seem to agree with the 3D CAD.
  * Hirata-san washed 3 OSEMs (last of initial 10 for BS) and parts for two BFs (for Type A). He moved the BF parts into the clean room and will assemble them with ATC staff from next Wednesday 9/7.
 * Type B ongoing issues
  * Longer cables for BF->PI and SF->PI - RECEIVED
  * Fabian, Mark and Liu-kun did BS installation at Kamioka:
   * Connected the DIO card to the LPCD. (Simulink model changes will be needed to make use of it.)
   * Took TF data from the TM-H1 coil output to the voltage and current monitors and found that the response was approximately flat, meaning that meaningful TFs can be taken of the RM/BS stage with no DIO.
   * Used the 90° prism and the optical lever to set the pitch of the RM to match the dummy BS.
   * Removed the RM trolley and added the bottom section of the security structure.
   * Lifted the IM/RM/BS with the load gauge adapter and load gauge and measured its mass.
  * Hirata-san:
   * Modified drawing of maraging rods for BS [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5706| D1605706]]
   * Made 3D models of stub flag gluing jigs.
   * Made 3D models and 2D drawing of BS BF-IM hexagon cable clamp assembly and cone parts. [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5734| D1605734]]
   * Washed parts and screws.
   * (For Type A) Assembled and adjusted blades of BF #9.
  * Mark checked lots of drawings by Hirata-san.
  * Mark worked on schedule but only succeeded in completely garbling the Type B section of the VIS schedule on the server.
Line 20: Line 21:
  * Decide position of BS rack - DONE
* Do Inventor assembly for SR2 in chamber and on assembly frame (Hirata) - NEARLY DONE.
  * Do Inventor assembly for SRx in chamber and on assembly frame (Hirata) - SR2/SR3 DONE, SRM ongoing.
   * Part "disk security" top has to be modified - screw positions do not match.
Line 26: Line 27:
  * Do BS Simulink model (Mark, Kokeyama)   * Do BS Simulink model (Mark, Kokeyama) - TM/IM/BF level DONE

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

  • Type B Past Week Summary
    • Fabian, Mark and Liu-kun did BS installation at Kamioka:
      • Connected the DIO card to the LPCD. (Simulink model changes will be needed to make use of it.)
      • Took TF data from the TM-H1 coil output to the voltage and current monitors and found that the response was approximately flat, meaning that meaningful TFs can be taken of the RM/BS stage with no DIO.
      • Used the 90° prism and the optical lever to set the pitch of the RM to match the dummy BS.
      • Removed the RM trolley and added the bottom section of the security structure.
      • Lifted the IM/RM/BS with the load gauge adapter and load gauge and measured its mass.
    • Hirata-san:
      • Modified drawing of maraging rods for BS D1605706

      • Made 3D models of stub flag gluing jigs.
      • Made 3D models and 2D drawing of BS BF-IM hexagon cable clamp assembly and cone parts. D1605734

      • Washed parts and screws.
      • (For Type A) Assembled and adjusted blades of BF #9.
    • Mark checked lots of drawings by Hirata-san.
    • Mark worked on schedule but only succeeded in completely garbling the Type B section of the VIS schedule on the server.
  • Longer term to-do list
    • Do Inventor assembly for SRx in chamber and on assembly frame (Hirata) - SR2/SR3 DONE, SRM ongoing.
      • Part "disk security" top has to be modified - screw positions do not match.
    • Write more of payload assembly procedure (Fabian) - ONGOING
    • Write more of BS Assembly Procedure E1504235, E1504235 draft (Mark) - ONGOING

    • Lower breadboard installation to be incorporated into the procedure document.
    • Work on BS simulation (Fabian)
    • Do BS Simulink model (Mark, Kokeyama) - TM/IM/BF level DONE
    • Do 2D drawings of SR2 parts (Hirata)
    • Redesign SRx IM wire clamps for larger prisms, remachined RMs
    • Order SRM/PRM parts (Hirata/Shoda)
    • Order SRx fasteners (Hirata)