* Type B Past Week Summary * Fabian, Mark, Yokogawa-kun and Kuwahara-kun did BS installation at Kamioka: * Calculated BS pitch correction ([[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5630|JGW-T1605630]]) * Hung dummy optic and set pitch. * Prepared RM. * Placed vacuum feedthroughs on assembly frame and cleaned D-Sub cables. * Decided position of BS rack with Miyakawa-san. * Measured maraging rods. * Placed safety rails, rearranged floor panels, cleaned new floor panels, and otherwise improved safety. * Hirata-san: * Made new 3D models of the maraging rods for PRx and SRx * Made new collet design for PRx and SRx. * Made new IM flag design for PRx and SRx. * Washed lots of Type A BF parts and OSEM parts. * Measure some BF part dimensions. * Pre-assembled parts for BFs. * Type B ongoing issues * Longer term to-do list * Do Inventor assembly for SR2 in chamber and on assembly frame (Hirata) - NEARLY DONE. * Part "disk security" top has to be modified - screw positions do not match. * Write more of payload assembly procedure (Fabian) - ONGOING * Write more of BS Assembly Procedure [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]], [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]] (Mark) - ONGOING * Lower breadboard installation to be incorporated into the procedure document. * Work on BS simulation (Fabian) * Do BS Simulink model (Mark, Kokeyama) * Do 2D drawings of SR2 parts (Hirata) * Redesign SRx IM wire clamps for larger prisms, remachined RMs * Order SRM/PRM parts (Hirata/Shoda) * Order SRx fasteners (Hirata) |
=== Type B (Mark) === ==== Report for week of 7/17 ==== * We checked the polarity of the IP LVDTs and flipped coil connections to get the standard arrangement. * We debugged an issue where one of the LVDT actuators had half the magnets in backwards resulting in no force. * We calibrated all the PI LVDTs. * We set the SF damper ring gap. * We prepped the suspension for craning, moved it into the tank and hooked the LBB damper ring rods. * Type A merged the SRM F0 with the correct IP, and we moved it out of the way (to the second floor behind the SRM tank). * We installed more cable clamps on the SR2 PI. |
Line 35: | Line 15: |
==== Plan for week of 7/23 ==== * Mark, Enzo, Fabian, Kozu-kun, Terrence, Panwei at Kamioka Mon-Fri. * Hirata-san at Kamioka Mon-Thu. * Mirapro moves assembly frame ≈7/25 (Wed). ===== SR3 ===== * Unlock suspension. * Rearrange cables. * Test. ===== SR2 ===== * Finish PI prep. * Crane into AF, suspend. * Start cable routing. ===== SRM ===== * Prepare to assemble SRM metal mass (most parts due Wed 7/25). * Help Mirapro with AF move. * Start rebuild of top filter of PI #2. ==== To-Do Lists, Schedule ==== * [[KAGRA/Subgroups/VIS/TypeB/ToDoBS]] * [[KAGRA/Subgroups/VIS/TypeB/ToDoSR]] * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7779|JGW-L1807779 Type B Schedule (SR)]] ==== Vacation Info ==== * Hirata-san at Mitaka 7/27. * Terrence: 8/24-26 f2f, then returns to Hong Kong. * Enzo: 9/14 JPS, 9/15 through 10/8 vacation in Chile. |
Scraps of text for incorporation in the VIS Meeting Minutes
KAGRA/Subgroups/VIS/MeetingNAOJ
Type B (Mark)
Report for week of 7/17
- We checked the polarity of the IP LVDTs and flipped coil connections to get the standard arrangement.
- We debugged an issue where one of the LVDT actuators had half the magnets in backwards resulting in no force.
- We calibrated all the PI LVDTs.
- We set the SF damper ring gap.
- We prepped the suspension for craning, moved it into the tank and hooked the LBB damper ring rods.
- Type A merged the SRM F0 with the correct IP, and we moved it out of the way (to the second floor behind the SRM tank).
- We installed more cable clamps on the SR2 PI.
Plan for week of 7/23
- Mark, Enzo, Fabian, Kozu-kun, Terrence, Panwei at Kamioka Mon-Fri.
- Hirata-san at Kamioka Mon-Thu.
- Mirapro moves assembly frame ≈7/25 (Wed).
SR3
- Unlock suspension.
- Rearrange cables.
- Test.
SR2
- Finish PI prep.
- Crane into AF, suspend.
- Start cable routing.
SRM
- Prepare to assemble SRM metal mass (most parts due Wed 7/25).
- Help Mirapro with AF move.
- Start rebuild of top filter of PI #2.
To-Do Lists, Schedule
Vacation Info
- Hirata-san at Mitaka 7/27.
- Terrence: 8/24-26 f2f, then returns to Hong Kong.
- Enzo: 9/14 JPS, 9/15 through 10/8 vacation in Chile.