Size: 1892
Comment:
|
Size: 2314
Comment:
|
Deletions are marked like this. | Additions are marked like this. |
Line 2: | Line 2: |
Line 5: | Line 4: |
* Type B Past Week Summary * Fabian, Mark, Yokogawa-kun and Kuwahara-kun did BS installation at Kamioka: * Calculated BS pitch correction ([[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5630|JGW-T1605630]]) * Hung dummy optic and set pitch. * Prepared RM. * Placed vacuum feedthroughs on assembly frame and cleaned D-Sub cables. * Decided position of BS rack with Miyakawa-san. * Measured maraging rods. * Placed safety rails, rearranged floor panels, cleaned new floor panels, and otherwise improved safety. * Hirata-san: * Made new 3D models of the maraging rods for PRx and SRx * Made new collet design for PRx and SRx. * Made new IM flag design for PRx and SRx. * Washed lots of Type A BF parts and OSEM parts. * Measure some BF part dimensions. * Pre-assembled parts for BFs. * Type B ongoing issues * Longer term to-do list * Do Inventor assembly for SR2 in chamber and on assembly frame (Hirata) - NEARLY DONE. * Part "disk security" top has to be modified - screw positions do not match. * Write more of payload assembly procedure (Fabian) - ONGOING * Write more of BS Assembly Procedure [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]], [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]] (Mark) - ONGOING * Lower breadboard installation to be incorporated into the procedure document. * Work on BS simulation (Fabian) * Do BS Simulink model (Mark, Kokeyama) * Do 2D drawings of SR2 parts (Hirata) * Redesign SRx IM wire clamps for larger prisms, remachined RMs * Order SRM/PRM parts (Hirata/Shoda) * Order SRx fasteners (Hirata) |
=== Type B (Mark) === ==== Report for the week of 4/8 ==== * Support of Type Bp * Mark made lots of Guardian improvements: * Used Guardian's timer functionality to drastically reduce the number of notifications during ramping. * Added new requestable states DCCTRL_ONLY and NEUTRAL (and associated transitional states) to facilitate testing. * Tidied up the code to use tabs consistently throughout for indentation. * Disabled the test for the IM-H coil driver WD (to work around the fact that only the relay in the chassis has been disabled, not the WD signals going to the BIO). * We opened the BS tank lid and offloaded a large IM-Y offset to F0-Y with manual adjustment of the broken yaw mechanism). * We opened the SR2 side doors and adjusted the V1 OSEM to mid-range. * Mark offloaded a large SR2 IM-Y offset to F0-Y. * Mark did health checks for BS, SR2 and SR3. * Fabian offloaded yaw from SRM and did the SRM health check. * Fabian updated the Python code for the stepper driver MEDM screen to reflect that two stepper drivers have different mappings to work around dead channels. * Fabian monitored pumpdown on Friday afternoon and will continue on Saturday. |
Line 35: | Line 20: |
==== Plan for week of 4/15 ==== * Mark, Hirata-san at Kamioka Tue-Thu. * Fabian at Kamioka Mon-Wed. * All at f2f Meeting 4/19-21. * Post-pumpdown health checks. * Teach Hirata-san about the computer systems and control theory. * Work with Lucia to do blending of the IP LVDTs and geophones. * More Guardian improvements. * Update vistools.py (formerly LIGO sustools.py) for Type B and KAGRA, and have the TYPEB.py Guardian use it where appropriate. * Modify RT models and/or Guardian to revert to the SAFE state under control in all but the most extreme emergency situations (rather than suddenly shutting off all output). * Work on Type B paper. * Tidy up. * Gather and clean tools. * Gather and organize unused parts and fasteners. ==== Vacation/Travel Info ==== * Mark at Mitaka 4/15. * f2f 4/19 (Friday), 4/20, 4/21. * Terrence's next visit from 4/18. * Fabian's vacation 4/26 to 5/10. * Mark's US vacation from 5/22 to 6/11. * Mark's final day 6/28. |
Scraps of text for incorporation in the VIS Meeting Minutes
KAGRA/Subgroups/VIS/MeetingNAOJ
Type B (Mark)
Report for the week of 4/8
- Support of Type Bp
- Mark made lots of Guardian improvements:
- Used Guardian's timer functionality to drastically reduce the number of notifications during ramping.
- Added new requestable states DCCTRL_ONLY and NEUTRAL (and associated transitional states) to facilitate testing.
- Tidied up the code to use tabs consistently throughout for indentation.
- Disabled the test for the IM-H coil driver WD (to work around the fact that only the relay in the chassis has been disabled, not the WD signals going to the BIO).
- Mark made lots of Guardian improvements:
- We opened the BS tank lid and offloaded a large IM-Y offset to F0-Y with manual adjustment of the broken yaw mechanism).
- We opened the SR2 side doors and adjusted the V1 OSEM to mid-range.
- Mark offloaded a large SR2 IM-Y offset to F0-Y.
- Mark did health checks for BS, SR2 and SR3.
- Fabian offloaded yaw from SRM and did the SRM health check.
- Fabian updated the Python code for the stepper driver MEDM screen to reflect that two stepper drivers have different mappings to work around dead channels.
- Fabian monitored pumpdown on Friday afternoon and will continue on Saturday.
Plan for week of 4/15
- Mark, Hirata-san at Kamioka Tue-Thu.
- Fabian at Kamioka Mon-Wed.
- All at f2f Meeting 4/19-21.
- Post-pumpdown health checks.
- Teach Hirata-san about the computer systems and control theory.
- Work with Lucia to do blending of the IP LVDTs and geophones.
- More Guardian improvements.
- Update vistools.py (formerly LIGO sustools.py) for Type B and KAGRA, and have the TYPEB.py Guardian use it where appropriate.
- Modify RT models and/or Guardian to revert to the SAFE state under control in all but the most extreme emergency situations (rather than suddenly shutting off all output).
- Work on Type B paper.
- Tidy up.
- Gather and clean tools.
- Gather and organize unused parts and fasteners.
Vacation/Travel Info
- Mark at Mitaka 4/15.
- f2f 4/19 (Friday), 4/20, 4/21.
- Terrence's next visit from 4/18.
- Fabian's vacation 4/26 to 5/10.
- Mark's US vacation from 5/22 to 6/11.
- Mark's final day 6/28.