Size: 2167
Comment:
|
Size: 1856
Comment:
|
Deletions are marked like this. | Additions are marked like this. |
Line 5: | Line 5: |
* Type B Past Week Summary * Fabian, Mark, Yokogawa-kun and Kuwahara-kun did BS installation at Kamioka: * Calculated BS pitch correction ([[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5630|JGW-T1605630]]) * Hung dummy optic and set pitch. * Prepared RM for hanging (adding OSEMs etc). One OSEM (#24) had wobbly leads and was brought back to Mitaka for rework. * Placed vacuum feedthroughs on assembly frame and cleaned initial batch (4) of D-Sub cables. * Decided position of BS rack with Miyakawa-san. * Measured various maraging rods and the rod holders on the SF. * Placed safety rails, rearranged floor panels, cleaned new floor panels, and otherwise improved safety. |
* Activity report for weeks of 12/26 and 1/2 |
Line 15: | Line 8: |
* Made new 3D models of the maraging rods for PRx and SRx * Made new collet design for PRx and SRx (3D and 2D). * Made new IM flag design for PRx and SRx (3D and 2D). * Washed lots of Type A BF parts and OSEM parts. * Cleaned the BS BF-IM maraging rod and organized the rest of the stock of rods. * Measured some BF part dimensions. * Pre-assembled parts for BFs. * Type B ongoing issues * Longer term to-do list * Do Inventor assembly for SR2 in chamber and on assembly frame (Hirata) - NEARLY DONE. * Part "disk security" top has to be modified - screw positions do not match. * Write more of payload assembly procedure (Fabian) - ONGOING * Write more of BS Assembly Procedure [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]], [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]] (Mark) - ONGOING * Lower breadboard installation to be incorporated into the procedure document. * Work on BS simulation (Fabian) * Do BS Simulink model (Mark, Kokeyama) * Do 2D drawings of SR2 parts (Hirata) * Redesign SRx IM wire clamps for larger prisms, remachined RMs * Order SRM/PRM parts (Hirata/Shoda) * Order SRx fasteners (Hirata) |
* Modified parts list and screw list for payload. * Sent lists to i-ject and asked for preliminary quotes. * Made drawings for some jigs (PR hold-down jig) and some parts for payload (PR/SR wire clamps with disposable jaw pieces - improved version with disposable pieces in both primary and secondary clamps). * For Type Bp: * Searched for PR gluing jigs. * Washed and assembled recoilmass base for mirror hanging jigs, and sent them to Kamioka. * Washed additional masses for IM and sent them to Kamioka. * For others: * Washed IMMT plate and sent them to Kamioka. * Fabian * Designed a pull down system to fix the PR IM to the EQ stop (similar to the SR one). * Worked on design of the SR assembly frame. As hoped, the SR version can be almost identical to the BS version. * Worked on design of additional trim mass (≈18 kg) for the BS BF. * Checked assembly PR/SR drawings. There were a few corrections/changes. * Checked fastener list. There were few corrections/changes. * Checked component list for the manufacture order. There were few corrections/changes. * Helped in searching for the PR gluing jigs. * Mark * Started design of SR assembly frame (but then passed it to Fabian). * Worked on task lists and schedule. * Plan for 1/10-13 * Mark and Fabian at Kamioka: * Finish rebalance of IM * Reinstall IRM, adjust OSEMs * Replace broken Type 3 cable. * Do TFs from IRM OSEMs to IRM and IM OSEMs. * Cable up and test BF LVDT and fishing rod (time permitting). * Disconnect BF and ship back to Mitaka (time permitting). * Hirata-san: * More SR procurement. |
Scraps of text for incorporation in the VIS Meeting Minutes
KAGRA/Subgroups/VIS/MeetingNAOJ
- Activity report for weeks of 12/26 and 1/2
- Hirata-san:
- Modified parts list and screw list for payload.
- Sent lists to i-ject and asked for preliminary quotes.
- Made drawings for some jigs (PR hold-down jig) and some parts for payload (PR/SR wire clamps with disposable jaw pieces - improved version with disposable pieces in both primary and secondary clamps).
- For Type Bp:
- Searched for PR gluing jigs.
- Washed and assembled recoilmass base for mirror hanging jigs, and sent them to Kamioka.
- Washed additional masses for IM and sent them to Kamioka.
- For others:
- Washed IMMT plate and sent them to Kamioka.
- Fabian
- Designed a pull down system to fix the PR IM to the EQ stop (similar to the SR one).
- Worked on design of the SR assembly frame. As hoped, the SR version can be almost identical to the BS version.
- Worked on design of additional trim mass (≈18 kg) for the BS BF.
- Checked assembly PR/SR drawings. There were a few corrections/changes.
- Checked fastener list. There were few corrections/changes.
- Checked component list for the manufacture order. There were few corrections/changes.
- Helped in searching for the PR gluing jigs.
- Mark
- Started design of SR assembly frame (but then passed it to Fabian).
- Worked on task lists and schedule.
- Hirata-san:
- Plan for 1/10-13
- Mark and Fabian at Kamioka:
- Finish rebalance of IM
- Reinstall IRM, adjust OSEMs
- Replace broken Type 3 cable.
- Do TFs from IRM OSEMs to IRM and IM OSEMs.
- Cable up and test BF LVDT and fishing rod (time permitting).
- Disconnect BF and ship back to Mitaka (time permitting).
- Hirata-san:
- More SR procurement.
- Mark and Fabian at Kamioka: