Differences between revisions 65 and 122 (spanning 57 versions)
Revision 65 as of 2016-09-09 13:19:01
Size: 2167
Editor: MarkBarton
Comment:
Revision 122 as of 2017-02-10 13:36:19
Size: 910
Editor: MarkBarton
Comment:
Deletions are marked like this. Additions are marked like this.
Line 5: Line 5:
 * Type B Past Week Summary
  * Fabian, Mark, Yokogawa-kun and Kuwahara-kun did BS installation at Kamioka:
   * Calculated BS pitch correction ([[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5630|JGW-T1605630]])
   * Hung dummy optic and set pitch.
   * Prepared RM for hanging (adding OSEMs etc). One OSEM (#24) had wobbly leads and was brought back to Mitaka for rework.
   * Placed vacuum feedthroughs on assembly frame and cleaned initial batch (4) of D-Sub cables.
   * Decided position of BS rack with Miyakawa-san.
   * Measured various maraging rods and the rod holders on the SF.
   * Placed safety rails, rearranged floor panels, cleaned new floor panels, and otherwise improved safety.
  * Hirata-san:
   * Made new 3D models of the maraging rods for PRx and SRx
   * Made new collet design for PRx and SRx (3D and 2D).
   * Made new IM flag design for PRx and SRx (3D and 2D).
   * Washed lots of Type A BF parts and OSEM parts.
   * Cleaned the BS BF-IM maraging rod and organized the rest of the stock of rods.
   * Measured some BF part dimensions.
   * Pre-assembled parts for BFs.
 * Type B ongoing issues
 * Longer term to-do list
  * Do Inventor assembly for SR2 in chamber and on assembly frame (Hirata) - NEARLY DONE.
   * Part "disk security" top has to be modified - screw positions do not match.
  * Write more of payload assembly procedure (Fabian) - ONGOING
  * Write more of BS Assembly Procedure [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]], [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]] (Mark) - ONGOING
  * Lower breadboard installation to be incorporated into the procedure document.
  * Work on BS simulation (Fabian)
  * Do BS Simulink model (Mark, Kokeyama)
  * Do 2D drawings of SR2 parts (Hirata)
  * Redesign SRx IM wire clamps for larger prisms, remachined RMs
  * Order SRM/PRM parts (Hirata/Shoda)
  * Order SRx fasteners (Hirata)

 
 * Hirata-san:
  * Did drawings of SR damper.
 * Mark, Fabian, Enzo and Hirata-san (at Kamioka):
  * Took the end plate off the IM to get access to the pitch/roll picos.
  * Found the pitch pico was unreliable and replaced it.
  * Found the springs were not stiff enough, and immobilized 7 turns at the end of each with Cu wire to make them stiffer.
  * Reassembled and rebalanced the IM.
  * Reassembled and adjusted the IRM.
  * Discovered that the transverse offset between IRM and IM could be corrected by adjusting the roll of the BF.
  * Adjusted IM OSEMs to half-way.
  * Made and installed a new pair of wires for the BF yaw pico on the IM pico adapter (Hirata-san).
  * Installed an improved LVDT cable made by Hirata-san.
  * Made and hung posters for the Elites meeting visitors.

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

  • Hirata-san:
    • Did drawings of SR damper.
  • Mark, Fabian, Enzo and Hirata-san (at Kamioka):
    • Took the end plate off the IM to get access to the pitch/roll picos.
    • Found the pitch pico was unreliable and replaced it.
    • Found the springs were not stiff enough, and immobilized 7 turns at the end of each with Cu wire to make them stiffer.
    • Reassembled and rebalanced the IM.
    • Reassembled and adjusted the IRM.
    • Discovered that the transverse offset between IRM and IM could be corrected by adjusting the roll of the BF.
    • Adjusted IM OSEMs to half-way.
    • Made and installed a new pair of wires for the BF yaw pico on the IM pico adapter (Hirata-san).
    • Installed an improved LVDT cable made by Hirata-san.
    • Made and hung posters for the Elites meeting visitors.

KAGRA/Subgroups/VIS/TypeB/Minutes (last edited 2022-10-28 10:02:46 by fabian.arellano)