* Type B Past Week Summary * Fabian, Mark, Yokogawa-kun and Kuwahara-kun did BS installation at Kamioka: * Calculated BS pitch correction ([[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5630|JGW-T1605630]]) * Hung dummy optic and set pitch. * Prepared RM for hanging (adding OSEMs etc). One OSEM (#24) had wobbly leads and was brought back to Mitaka for rework. * Placed vacuum feedthroughs on assembly frame and cleaned initial batch (4) of D-Sub cables. * Decided position of BS rack with Miyakawa-san. * Measured various maraging rods and the rod holders on the SF. * Placed safety rails, rearranged floor panels, cleaned new floor panels, and otherwise improved safety. * Hirata-san: * Made new 3D models of the maraging rods for PRx and SRx * Made new collet design for PRx and SRx (3D and 2D). * Made new IM flag design for PRx and SRx (3D and 2D). * Washed lots of Type A BF parts and OSEM parts. * Cleaned the BS BF-IM maraging rod and organized the rest of the stock of rods. * Measured some BF part dimensions. * Pre-assembled parts for BFs. * Type B ongoing issues * Longer term to-do list * Do Inventor assembly for SR2 in chamber and on assembly frame (Hirata) - NEARLY DONE. * Part "disk security" top has to be modified - screw positions do not match. * Write more of payload assembly procedure (Fabian) - ONGOING * Write more of BS Assembly Procedure [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]], [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]] (Mark) - ONGOING * Lower breadboard installation to be incorporated into the procedure document. * Work on BS simulation (Fabian) * Do BS Simulink model (Mark, Kokeyama) * Do 2D drawings of SR2 parts (Hirata) * Redesign SRx IM wire clamps for larger prisms, remachined RMs * Order SRM/PRM parts (Hirata/Shoda) * Order SRx fasteners (Hirata) |
=== Type B (Mark) === ==== Report for week of 4/2 ==== |
Line 36: | Line 8: |
* Fujii-kun and Yamamoto-kun got the SR3 real time model running. * We received the SR3. * However Mark and Tanioka-kun found Hirose-san had applied the First Contact patterns on the wrong sides, so we took it to Yamamoto-san's lab and Toyama University and re-applied the FC properly. We also bounced a 1064 nm beam off it to verify that the HR and AR coatings were not also swapped (they were OK). * We made magnet-standoff assemblies for both SR3 and SRM, and set up for gluing the prisms and magnets. We will attach the prisms and magnet-standoffs on Monday. * Hirata-san did inventory of the SR3/SRM payload parts received last week and started on the inventory of screws. * Fujii-kun, Enzo and team finished the preparation, adjustment of the SFs and BFs. * They calibrated one SF and BF. (The remaining one SF and BF will take about another day. Also, the FR stops need to be checked.) * Enzo and Kozu-kun finished setting up the SR3 and SRM racks. (The SRM rack still lacks a front-end, and power and network connections, but the SR3 is now ready for testing.) * Shoda-san worked on getting quotes for the ballast masses, on design of the SRM metal mass, and on splitting the BS model to reduce the load on the front-end computer. ==== Plan for week of 4/9 ==== * Shoda-san at Mitaka * Fujii-san at Mitaka * Tanioka-san at Kamioka, but possibly doing PEM stuff. * Others at Kamioka * -- * Finish SRM BF and SF calibration * Finish IMs and IRMs * Glue SR3 mirror ==== Plan for week of 4/16 ==== * Shoda-san at Mitaka * Fujii-san at Mitaka * Tanioka-san at Mitaka? * Others at Kamioka * -- * Build 1xRM * Start SR3 Hang * Align assembly frame. ==== Plan for week of 4/23 ==== * Shoda-san at Mitaka * Fujii-san at Mitaka? * Mark, Enzo at Kamioka * Hirata-san at Mitaka * Tanioka-san at Mitaka? * -- * Clean parts (cable clamp bases, etc, etc). * Observe KAGRA Phase 1 operations, assist if problems arise. ==== Plan for week of 4/30 ==== * Golden Week! ==== To-Do Lists, Schedule ==== * [[KAGRA/Subgroups/VIS/TypeB/March2018]] * [[KAGRA/Subgroups/VIS/TypeB/April2018]] * [[KAGRA/Subgroups/VIS/TypeB/ToDoBS]] * [[KAGRA/Subgroups/VIS/TypeB/ToDoSR]] * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7779|JGW-L1807779-v1 Type B Schedule (SR)]] ==== Vacation Info ==== * Fabian vacation, 3/26-4/27 (then gone). |
Scraps of text for incorporation in the VIS Meeting Minutes
KAGRA/Subgroups/VIS/MeetingNAOJ
Type B (Mark)
Report for week of 4/2
- Fujii-kun and Yamamoto-kun got the SR3 real time model running.
- We received the SR3.
- However Mark and Tanioka-kun found Hirose-san had applied the First Contact patterns on the wrong sides, so we took it to Yamamoto-san's lab and Toyama University and re-applied the FC properly. We also bounced a 1064 nm beam off it to verify that the HR and AR coatings were not also swapped (they were OK).
- We made magnet-standoff assemblies for both SR3 and SRM, and set up for gluing the prisms and magnets. We will attach the prisms and magnet-standoffs on Monday.
- Hirata-san did inventory of the SR3/SRM payload parts received last week and started on the inventory of screws.
- Fujii-kun, Enzo and team finished the preparation, adjustment of the SFs and BFs.
- They calibrated one SF and BF. (The remaining one SF and BF will take about another day. Also, the FR stops need to be checked.)
- Enzo and Kozu-kun finished setting up the SR3 and SRM racks. (The SRM rack still lacks a front-end, and power and network connections, but the SR3 is now ready for testing.)
- Shoda-san worked on getting quotes for the ballast masses, on design of the SRM metal mass, and on splitting the BS model to reduce the load on the front-end computer.
Plan for week of 4/9
- Shoda-san at Mitaka
- Fujii-san at Mitaka
- Tanioka-san at Kamioka, but possibly doing PEM stuff.
- Others at Kamioka
- --
- Finish SRM BF and SF calibration
- Finish IMs and IRMs
- Glue SR3 mirror
Plan for week of 4/16
- Shoda-san at Mitaka
- Fujii-san at Mitaka
- Tanioka-san at Mitaka?
- Others at Kamioka
- --
- Build 1xRM
- Start SR3 Hang
- Align assembly frame.
Plan for week of 4/23
- Shoda-san at Mitaka
- Fujii-san at Mitaka?
- Mark, Enzo at Kamioka
- Hirata-san at Mitaka
- Tanioka-san at Mitaka?
- --
- Clean parts (cable clamp bases, etc, etc).
- Observe KAGRA Phase 1 operations, assist if problems arise.
Plan for week of 4/30
- Golden Week!
To-Do Lists, Schedule
Vacation Info
- Fabian vacation, 3/26-4/27 (then gone).