Differences between revisions 65 and 83 (spanning 18 versions)
Revision 65 as of 2016-09-09 13:19:01
Size: 2167
Editor: MarkBarton
Comment:
Revision 83 as of 2016-11-18 13:53:17
Size: 1249
Editor: MarkBarton
Comment:
Deletions are marked like this. Additions are marked like this.
Line 6: Line 6:
  * Fabian, Mark, Yokogawa-kun and Kuwahara-kun did BS installation at Kamioka:
   * Calculated BS pitch correction ([[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5630|JGW-T1605630]])
   * Hung dummy optic and set pitch.
   * Prepared RM for hanging (adding OSEMs etc). One OSEM (#24) had wobbly leads and was brought back to Mitaka for rework.
   * Placed vacuum feedthroughs on assembly frame and cleaned initial batch (4) of D-Sub cables.
   * Decided position of BS rack with Miyakawa-san.
   * Measured various maraging rods and the rod holders on the SF.
   * Placed safety rails, rearranged floor panels, cleaned new floor panels, and otherwise improved safety.
  * Hirata-san:
   * Made new 3D models of the maraging rods for PRx and SRx
   * Made new collet design for PRx and SRx (3D and 2D).
   * Made new IM flag design for PRx and SRx (3D and 2D).
   * Washed lots of Type A BF parts and OSEM parts.
   * Cleaned the BS BF-IM maraging rod and organized the rest of the stock of rods.
   * Measured some BF part dimensions.
   * Pre-assembled parts for BFs.
 * Type B ongoing issues
 * Longer term to-do list
  * Do Inventor assembly for SR2 in chamber and on assembly frame (Hirata) - NEARLY DONE.
   * Part "disk security" top has to be modified - screw positions do not match.
  * Write more of payload assembly procedure (Fabian) - ONGOING
  * Write more of BS Assembly Procedure [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]], [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]] (Mark) - ONGOING
  * Lower breadboard installation to be incorporated into the procedure document.
  * Work on BS simulation (Fabian)
  * Do BS Simulink model (Mark, Kokeyama)
  * Do 2D drawings of SR2 parts (Hirata)
  * Redesign SRx IM wire clamps for larger prisms, remachined RMs
  * Order SRM/PRM parts (Hirata/Shoda)
  * Order SRx fasteners (Hirata)

 
  * Mark and Hirata-san worked at Kamioka, with valuable help from Enzo (on loan from Type Bp team).
   * We got all the adapter cables for the BF made (Hirata-san did some work on Monday at Mitaka).
   * We installed the extension for the BF yaw pico on the IM pico adapter cable.
   * We got all the in-vacuum and in-air cabling for the IM OSEMs done.
   * We tried to install the stepper and LVDT adapter cables but realized we didn't have enough information on which wires was which. (We later tracked this info down but did not have time to do anything with it - we would have needed to do the rest of the in-vacuum and in-air cabling and set up the stepper motor and LVDT drivers, so we concentrated on the OSEMs.)
   * We plugged in the IM OSEMs, set gains and offsets, and did a noise test (analysis and klog pending).
   * We mounted the OSEMs on the IRM and routed the cabling neatly.
   * We released the suspension.
   * We adjusted the OSEM mounting plates to center the OSEMs on the flags.
   * We adjusted the OSEMs in/out to midrange.
   * The suspension is now ready for OSEM-OSEM TFs!

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

  • Type B Past Week Summary
    • Mark and Hirata-san worked at Kamioka, with valuable help from Enzo (on loan from Type Bp team).
      • We got all the adapter cables for the BF made (Hirata-san did some work on Monday at Mitaka).
      • We installed the extension for the BF yaw pico on the IM pico adapter cable.
      • We got all the in-vacuum and in-air cabling for the IM OSEMs done.
      • We tried to install the stepper and LVDT adapter cables but realized we didn't have enough information on which wires was which. (We later tracked this info down but did not have time to do anything with it - we would have needed to do the rest of the in-vacuum and in-air cabling and set up the stepper motor and LVDT drivers, so we concentrated on the OSEMs.)
      • We plugged in the IM OSEMs, set gains and offsets, and did a noise test (analysis and klog pending).
      • We mounted the OSEMs on the IRM and routed the cabling neatly.
      • We released the suspension.
      • We adjusted the OSEM mounting plates to center the OSEMs on the flags.
      • We adjusted the OSEMs in/out to midrange.
      • The suspension is now ready for OSEM-OSEM TFs!

KAGRA/Subgroups/VIS/TypeB/Minutes (last edited 2022-10-28 10:02:46 by fabian.arellano)