* Fabian, Mark, Yokogawa-kun and Kuwahara-kun did BS installation at Kamioka: * Calculated BS pitch correction ([[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5630|JGW-T1605630]]) * Hung dummy optic and set pitch. * Prepared RM for hanging (adding OSEMs etc). One OSEM (#24) had wobbly leads and was brought back to Mitaka for rework. * Placed vacuum feedthroughs on assembly frame and cleaned initial batch (4) of D-Sub cables. * Decided position of BS rack with Miyakawa-san. * Measured various maraging rods and the rod holders on the SF. * Placed safety rails, rearranged floor panels, cleaned new floor panels, and otherwise improved safety. * Hirata-san: * Made new 3D models of the maraging rods for PRx and SRx * Made new collet design for PRx and SRx (3D and 2D). * Made new IM flag design for PRx and SRx (3D and 2D). * Washed lots of Type A BF parts and OSEM parts. * Cleaned the BS BF-IM maraging rod and organized the rest of the stock of rods. * Measured some BF part dimensions. * Pre-assembled parts for BFs. * Type B ongoing issues * Longer term to-do list * Do Inventor assembly for SR2 in chamber and on assembly frame (Hirata) - NEARLY DONE. * Part "disk security" top has to be modified - screw positions do not match. * Write more of payload assembly procedure (Fabian) - ONGOING * Write more of BS Assembly Procedure [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]], [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]] (Mark) - ONGOING * Lower breadboard installation to be incorporated into the procedure document. * Work on BS simulation (Fabian) * Do BS Simulink model (Mark, Kokeyama) * Do 2D drawings of SR2 parts (Hirata) * Redesign SRx IM wire clamps for larger prisms, remachined RMs * Order SRM/PRM parts (Hirata/Shoda) * Order SRx fasteners (Hirata) |
* Mark (with Enzo) did initial TFs on the BF. * Did fixed-sine TFs on individual OSEMs at low frequency to check actuator polarity (klog [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=2176 | 2176]] and [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=2182|2182]]). * Set gains in the COILOUTF block to compensate for actuator polarity. * Mark (with Enzo) did a free-swing measurement on the BS after earthquake of 11/22 (klog [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=2182|2182]]). * Results suspicious (noted by Shoda-san): too much difference between OSEMs - horizontal showing much less motion than vertical. * Possible rubbing in horizontal. * May need a trip to Kamioka. * Mark (with Enzo) made corrections and improvements to many of the MEDM screens (klog [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=2176 | 2176]] and [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=2182|2182]]). * Main overview screen was not generic in many places, and links to GDS_TP screens were broken. * ADC monitor screen referenced bad channels with LIGO-style names. * DAC monitor screen was not generic and did not support IM OSEMs. * Watchdog IM OSEM AC band limit filter screen was a copy of the TM one. * Watchdog TM OSEM AC band limit filter screen appears to be getting OL signals as input - needs model changes to fix. * The zoomed screens for IM OSEM centering were called incorrectly and did not work. * Various screens had LIGO-style channel names as labels. * Mark did a draft of D1603600-v12 reflecting the new assignment of IM OSEMs to DAQ channels (#4-9 are now V1, V2, V3, H1, H2, H3 rather than H1, H2, ...) from last Friday (the wiring was changed to reflect the model). * Mark worked on schedule. * Hirata-san |
Scraps of text for incorporation in the VIS Meeting Minutes
KAGRA/Subgroups/VIS/MeetingNAOJ
- Type B Past Week Summary
- Mark (with Enzo) did initial TFs on the BF.
Mark (with Enzo) did a free-swing measurement on the BS after earthquake of 11/22 (klog 2182).
- Results suspicious (noted by Shoda-san): too much difference between OSEMs - horizontal showing much less motion than vertical.
- Possible rubbing in horizontal.
- May need a trip to Kamioka.
Mark (with Enzo) made corrections and improvements to many of the MEDM screens (klog 2176 and 2182).
- Main overview screen was not generic in many places, and links to GDS_TP screens were broken.
- ADC monitor screen referenced bad channels with LIGO-style names.
- DAC monitor screen was not generic and did not support IM OSEMs.
- Watchdog IM OSEM AC band limit filter screen was a copy of the TM one.
- Watchdog TM OSEM AC band limit filter screen appears to be getting OL signals as input - needs model changes to fix.
- The zoomed screens for IM OSEM centering were called incorrectly and did not work.
- Various screens had LIGO-style channel names as labels.
- Mark did a draft of D1603600-v12 reflecting the new assignment of IM OSEMs to DAQ channels (#4-9 are now V1, V2, V3, H1, H2, H3 rather than H1, H2, ...) from last Friday (the wiring was changed to reflect the model).
- Mark worked on schedule.
- Hirata-san