Differences between revisions 66 and 121 (spanning 55 versions)
Revision 66 as of 2016-09-15 13:12:28
Size: 1679
Editor: MarkBarton
Comment:
Revision 121 as of 2017-02-03 13:33:12
Size: 1344
Editor: MarkBarton
Comment:
Deletions are marked like this. Additions are marked like this.
Line 5: Line 5:
 * Type B Past Week Summary
  * Fabian, Mark, Yokogawa-kun and Kuwahara-kun did BS installation at Kamioka:
   * Hung RM.
   * Did permanent routing of RM OSEM cables to IM.
   * Did temporary routing of RM OSEM in-vacuum cables to flange (4 channels).
   * Did semi-permanent routing of all OSEM external cables to satellite amps (10 channels)
   * Did temporary routing of RM OSEMs to PR2 rack (4 channels).
  * Hirata-san:
   * Finished 3D CAD of SR2 and SR3 in tanks, with optical layout included.
   * Started 3D CAD for SRM.
   * Checked flag design.
   * Assembled a bottom filter (ongoing).
   * Cleaned maraging rods.
 * Type B ongoing issues
 * Longer term to-do list
  * Do Inventor assembly for SRx in chamber and on assembly frame (Hirata) - SR2/SR3 DONE, SRM ongoing.
   * Part "disk security" top has to be modified - screw positions do not match.
  * Write more of payload assembly procedure (Fabian) - ONGOING
  * Write more of BS Assembly Procedure [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]], [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]] (Mark) - ONGOING
  * Lower breadboard installation to be incorporated into the procedure document.
  * Work on BS simulation (Fabian)
  * Do BS Simulink model (Mark, Kokeyama)
  * Do 2D drawings of SR2 parts (Hirata)
  * Redesign SRx IM wire clamps for larger prisms, remachined RMs
  * Order SRM/PRM parts (Hirata/Shoda)
  * Order SRx fasteners (Hirata)

 
 * Hirata-san:
  * Made BS disposable wire clamp 3Dmodel and drawings.
  * Made ballast mass drawings for BS Bottomfilter and Standardfilter.
  * Made parts list and screw list for disposable wire clamp and ballast mass.
  * Sent drawings and lists to i-ject for quotation.
  * Start to make drawings for SR big parts (optical bench,damper rings,sus wires,cable clamps) - ongoing.
 * Mark, Fabian and Enzo (at Kamioka):
  * Realized that some of the imbalance in the BF was from the fishing rod and calculated a new set of blade offsets to center the rod but leave the torque from the FR to be cancelled by the trim mass for now.
  * Applied the blade offsets and checked that the BF hung as expected.
  * Found that the yoke was rubbing again and corrected it by putting it at an angle matching the keystone.
  * Found that the cables were adding too much stiffness and friction and rerouted them.
  * Found that the GAS was unstable and reduced the compression symmetrically to get 0.37 Hz.
  * Rebalanced the IM to set the right pitch, yaw and height.
  * Tested the IM picos. Unfortunately the pitch pico stuck near or at one end of its range and we will need to take the end plate off the IM to find out what is wrong.

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

  • Hirata-san:
    • Made BS disposable wire clamp 3Dmodel and drawings.
    • Made ballast mass drawings for BS Bottomfilter and Standardfilter.
    • Made parts list and screw list for disposable wire clamp and ballast mass.
    • Sent drawings and lists to i-ject for quotation.
    • Start to make drawings for SR big parts (optical bench,damper rings,sus wires,cable clamps) - ongoing.
  • Mark, Fabian and Enzo (at Kamioka):
    • Realized that some of the imbalance in the BF was from the fishing rod and calculated a new set of blade offsets to center the rod but leave the torque from the FR to be cancelled by the trim mass for now.
    • Applied the blade offsets and checked that the BF hung as expected.
    • Found that the yoke was rubbing again and corrected it by putting it at an angle matching the keystone.
    • Found that the cables were adding too much stiffness and friction and rerouted them.
    • Found that the GAS was unstable and reduced the compression symmetrically to get 0.37 Hz.
    • Rebalanced the IM to set the right pitch, yaw and height.
    • Tested the IM picos. Unfortunately the pitch pico stuck near or at one end of its range and we will need to take the end plate off the IM to find out what is wrong.