* Type B Past Week Summary * Fabian, Mark, Yokogawa-kun and Kuwahara-kun did BS installation at Kamioka: * Hung RM. * Did permanent routing of RM OSEM cables to IM. * Did temporary routing of RM OSEM in-vacuum cables to flange (4 channels). * Did semi-permanent routing of all OSEM external cables to satellite amps (10 channels) * Did temporary routing of RM OSEMs to PR2 rack (4 channels). * Hirata-san: * Finished 3D CAD of SR2 and SR3 in tanks, with optical layout included. * Started 3D CAD for SRM. * Checked flag design. * Assembled a bottom filter (ongoing). * Cleaned maraging rods. * Type B ongoing issues * Longer term to-do list * Do Inventor assembly for SRx in chamber and on assembly frame (Hirata) - SR2/SR3 DONE, SRM ongoing. * Part "disk security" top has to be modified - screw positions do not match. * Write more of payload assembly procedure (Fabian) - ONGOING * Write more of BS Assembly Procedure [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]], [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]] (Mark) - ONGOING * Lower breadboard installation to be incorporated into the procedure document. * Work on BS simulation (Fabian) * Do BS Simulink model (Mark, Kokeyama) * Do 2D drawings of SR2 parts (Hirata) * Redesign SRx IM wire clamps for larger prisms, remachined RMs * Order SRM/PRM parts (Hirata/Shoda) * Order SRx fasteners (Hirata) |
=== Type B (Mark) === ==== Report for week of 6/11 ==== * Enzo redid the SR3 BIO connections to match the now-working BS setup. He also fixed PR2, which had a similar problem. * Enzo replaced LPCDs with HPCDs in the SR3. * Hirata-san installed the cable clamps and Cu segments on the SF cap. * Hirata-san and Kozu-kun continued tuning the filter in PI #3. Unfortunately it seems to be rather weaker than expected, and we have not found a compression setting that gives a good frequency. We may have to use tricks like reducing the number of Cu segments on the SF (or using Al ones) to save weight. * Mark, Enzo and Terrence suspended the BF/... section from the SF, and got it aligned for TFs. |
Line 32: | Line 13: |
==== Plan for week of 6/18 ==== * Mark Enzo, Hirata-san, Kozu-kun, Terrence at Kamioka Mon-Fri. * -- * Receive second and third sets of LBB damper rings. * Take TFs. * Cable, test SF LVDT and FR. * Add calculated ballast to SF. * Finish tuning F0 #3 for SR3. * Park F0 #1 (for SR2) in top of SR3 assembly frame. * Move F0 #3 behind SR3. * Move F0 #1 to "factory" area (in front of SRM) and start rebuild. * Install PI. * Suspend SF/... section. * Lots of cabling. ==== Plan for week of 6/25 ==== * Mark Enzo, Hirata-san, Kozu-kun, Terrence at Kamioka Mon-Fri. ==== To-Do Lists, Schedule ==== * [[KAGRA/Subgroups/VIS/TypeB/ToDoBS]] * [[KAGRA/Subgroups/VIS/TypeB/ToDoSR]] * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7779|JGW-L1807779 Type B Schedule (SR)]] ==== Vacation Info ==== |
Scraps of text for incorporation in the VIS Meeting Minutes
KAGRA/Subgroups/VIS/MeetingNAOJ
Type B (Mark)
Report for week of 6/11
- Enzo redid the SR3 BIO connections to match the now-working BS setup. He also fixed PR2, which had a similar problem.
- Enzo replaced LPCDs with HPCDs in the SR3.
- Hirata-san installed the cable clamps and Cu segments on the SF cap.
- Hirata-san and Kozu-kun continued tuning the filter in PI #3. Unfortunately it seems to be rather weaker than expected, and we have not found a compression setting that gives a good frequency. We may have to use tricks like reducing the number of Cu segments on the SF (or using Al ones) to save weight.
- Mark, Enzo and Terrence suspended the BF/... section from the SF, and got it aligned for TFs.
Plan for week of 6/18
- Mark Enzo, Hirata-san, Kozu-kun, Terrence at Kamioka Mon-Fri.
- --
- Receive second and third sets of LBB damper rings.
- Take TFs.
- Cable, test SF LVDT and FR.
- Add calculated ballast to SF.
- Finish tuning F0 #3 for SR3.
- Park F0 #1 (for SR2) in top of SR3 assembly frame.
- Move F0 #3 behind SR3.
- Move F0 #1 to "factory" area (in front of SRM) and start rebuild.
- Install PI.
- Suspend SF/... section.
- Lots of cabling.
Plan for week of 6/25
- Mark Enzo, Hirata-san, Kozu-kun, Terrence at Kamioka Mon-Fri.
To-Do Lists, Schedule