 * Type B Past Week Summary
  * Fabian, Mark, Yokogawa-kun and Kuwahara-kun did BS installation at Kamioka:
   * Hung RM.
   * Did permanent routing of RM OSEM cables to IM.
   * Did temporary routing of RM OSEM in-vacuum cables to flange (4 channels).
   * Did semi-permanent routing of all OSEM external cables to satellite amps (10 channels)
   * Did temporary routing of RM OSEMs to PR2 rack (4 channels).
  * Hirata-san:
   * Finished 3D CAD of SR2 and SR3 in tanks, with optical layout included.
   * Started 3D CAD for SRM.
   * Checked flag design.
   * Assembled a bottom filter (ongoing).
   * Cleaned maraging rods.
 * Type B ongoing issues
 * Longer term to-do list
  * Do Inventor assembly for SRx in chamber and on assembly frame (Hirata) - SR2/SR3 DONE, SRM ongoing.
   * Part "disk security" top has to be modified - screw positions do not match.
  * Write more of payload assembly procedure (Fabian) - ONGOING
  * Write more of BS Assembly Procedure [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]], [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]] (Mark) - ONGOING
  * Lower breadboard installation to be incorporated into the procedure document.
  * Work on BS simulation (Fabian)
  * Do BS Simulink model (Mark, Kokeyama)
  * Do 2D drawings of SR2 parts (Hirata)
  * Redesign SRx IM wire clamps for larger prisms, remachined RMs
  * Order SRM/PRM parts (Hirata/Shoda)
  * Order SRx fasteners (Hirata)
=== Type B (Mark) ===
==== Report for week of 6/18 ====
 * Mark checked the health of the suspensions after an earthquake on Monday morning. The BS watchdog tripped and there was a few µrad change in the pointing, but otherwise it was fine. SR3 and SR2 were also fine.
 * Mark, Enzo and Terrence finalized the trim mass on the BF to set the SF keystone height and BF pitch/roll.
 * They weighed the SF/... section. With no internal trim mass in the SF but with the flying saucer and rod, but with 2 Promec masses for rough balance, it was 255.4 kg, so allowing 1 kg for cables and fine trim mass, we would like a PI load capacity of 256.4 kg.
 * Hirata-san and Kozu-kun struggled to tune the top filter for SR3 - see klogs 5310, 5324, 5337, xxxx. At first the results were somewhat unrepeatable, with high frequency and low load capacity. This was improved by using a torque wrench (set to 50 N.m) to tighten the blade base clamp screws, retightening the blade tip screws (which had worked loose) and tightening the collar on the end of the shaft of the magic wand. Eventually ...
 * Enzo and Terrence cabled and tested the SF fishing rod, and reversed the connections on the SF LVDT actuation to bring it to standard polarity.
 * Mark and Enzo made many improvements to the Type B MEDM screens.
 * Enzo and Mark measured the BF and SF bounce frequencies (with the other keystone locked).
 * Enzo replaced a HPCD that seemed to have failed during the bounce test (but had just had a watchdog trip), and then replaced the replacement, which really did fail. It turns out we need to avoid applying more than about 25000 counts of GAS actuation.
 * Enzo offloaded the BF LVDT actuator with the BF FR to remove the need for a 10000 ct offset.
 
==== Plan for week of 6/25 ====
 * Mark, Enzo, Hirata-san, Terrence at Kamioka Mon-Fri.
 * Kozu-kun at Kamioka except Thu.
 * --
 * Shutdown Type B controls (as far as possible) in preparation for risk of accidental power outage during electrical work on 6/26.
 * Add calculated ballast to SF.
 * Park F0 #1 (for SR2) in top of SR3 assembly frame.
 * Move F0 #3 behind SR3.
 * Move F0 #1 to "factory" area (in front of SRM) and start rebuild.
 * Install PI.
 * Suspend SF/... section.
 * Lots of cable routing.
Line 32: Line 30:
  ==== Plan for week of 7/2 ====
 * Mark, Hirata-san, Terrence at Kamioka Mon-Fri.
 * Enzo at Kamioka Mon-Wed
 * Kozu-kun at Kamioka except Wed.

==== To-Do Lists, Schedule ====
 * [[KAGRA/Subgroups/VIS/TypeB/ToDoBS]]
 * [[KAGRA/Subgroups/VIS/TypeB/ToDoSR]]
 * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7779|JGW-L1807779 Type B Schedule (SR)]]

==== Vacation Info ====
 * Kozu-kun: 7/4 Tokyo.
 * Enzo: 7/5-6 NAOJ Party, Mitaka.
 * Terrence: 8/24-26 f2f, then returns to Hong Kong.
 * Enzo: 9/14 JPS, 9/15 through 10/18 vacation in Chile.

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Report for week of 6/18

  • Mark checked the health of the suspensions after an earthquake on Monday morning. The BS watchdog tripped and there was a few µrad change in the pointing, but otherwise it was fine. SR3 and SR2 were also fine.
  • Mark, Enzo and Terrence finalized the trim mass on the BF to set the SF keystone height and BF pitch/roll.
  • They weighed the SF/... section. With no internal trim mass in the SF but with the flying saucer and rod, but with 2 Promec masses for rough balance, it was 255.4 kg, so allowing 1 kg for cables and fine trim mass, we would like a PI load capacity of 256.4 kg.
  • Hirata-san and Kozu-kun struggled to tune the top filter for SR3 - see klogs 5310, 5324, 5337, xxxx. At first the results were somewhat unrepeatable, with high frequency and low load capacity. This was improved by using a torque wrench (set to 50 N.m) to tighten the blade base clamp screws, retightening the blade tip screws (which had worked loose) and tightening the collar on the end of the shaft of the magic wand. Eventually ...
  • Enzo and Terrence cabled and tested the SF fishing rod, and reversed the connections on the SF LVDT actuation to bring it to standard polarity.
  • Mark and Enzo made many improvements to the Type B MEDM screens.
  • Enzo and Mark measured the BF and SF bounce frequencies (with the other keystone locked).
  • Enzo replaced a HPCD that seemed to have failed during the bounce test (but had just had a watchdog trip), and then replaced the replacement, which really did fail. It turns out we need to avoid applying more than about 25000 counts of GAS actuation.
  • Enzo offloaded the BF LVDT actuator with the BF FR to remove the need for a 10000 ct offset.

Plan for week of 6/25

  • Mark, Enzo, Hirata-san, Terrence at Kamioka Mon-Fri.
  • Kozu-kun at Kamioka except Thu.
  • --
  • Shutdown Type B controls (as far as possible) in preparation for risk of accidental power outage during electrical work on 6/26.
  • Add calculated ballast to SF.
  • Park F0 #1 (for SR2) in top of SR3 assembly frame.
  • Move F0 #3 behind SR3.
  • Move F0 #1 to "factory" area (in front of SRM) and start rebuild.
  • Install PI.
  • Suspend SF/... section.
  • Lots of cable routing.

Plan for week of 7/2

  • Mark, Hirata-san, Terrence at Kamioka Mon-Fri.
  • Enzo at Kamioka Mon-Wed
  • Kozu-kun at Kamioka except Wed.

To-Do Lists, Schedule

Vacation Info

  • Kozu-kun: 7/4 Tokyo.
  • Enzo: 7/5-6 NAOJ Party, Mitaka.
  • Terrence: 8/24-26 f2f, then returns to Hong Kong.
  • Enzo: 9/14 JPS, 9/15 through 10/18 vacation in Chile.