* Type B Past Week Summary * Fabian, Mark, Yokogawa-kun and Kuwahara-kun did BS installation at Kamioka: * Hung RM. * Did permanent routing of RM OSEM cables to IM. * Did temporary routing of RM OSEM in-vacuum cables to flange (4 channels). * Did semi-permanent routing of all OSEM external cables to satellite amps (10 channels) * Did temporary routing of RM OSEMs to PR2 rack (4 channels). * Took data with geophones connected but immobilized and then stored geophones in boxes. * Tested signals from first satellite amp getting to digital system. * Weighed mirror box. * Did fit check of flag holders for stub flags. Very minor adjustments will be needed. * Covered everything in preparation for modifications to clean booth roof (9/20-21). * Hirata-san: * Finished 3D CAD of SR2 and SR3 in tanks, with optical layout included. * Started 3D CAD for SRM. * Checked flag design. * Assembled a bottom filter (ongoing). * Cleaned maraging rods. * Type B ongoing issues * Longer term to-do list * Do Inventor assembly for SRx in chamber and on assembly frame (Hirata) - SR2/SR3 DONE, SRM ongoing. * Part "disk security" top has to be modified - screw positions do not match. * Write more of payload assembly procedure (Fabian) - ONGOING * Write more of BS Assembly Procedure [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]], [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]] (Mark) - ONGOING * Lower breadboard installation to be incorporated into the procedure document. * Work on BS simulation (Fabian) * Do BS Simulink model (Mark, Kokeyama) * Do 2D drawings of SR2 parts (Hirata) * Redesign SRx IM wire clamps for larger prisms, remachined RMs * Order SRM/PRM parts (Hirata/Shoda) * Order SRx fasteners (Hirata) |
=== Type B (Mark) === ==== Past week report ==== At Kamioka (Mark, Ohishi-san, Enzo, Yoshioka-kun, Kozu-kun): * We finished installing the RM OSEMs and installed the new Type5-2.2 and 5-2.4 OSEM cables. * We hung the RM and set its pitch. * We doubled-checked the BS and RM pitch, tightened the clamps and removed the winch system. * We installed the bottom section of the security structure to protect the RM/BS. * We lifted the IM/RM/BS section and weighed it. It was about 1.25 kg too heavy for the new BF, so we improvised a lighter set of ballast masses. * We installed the section of the security structure up to the BF ring, and the BF crossbars and jacks of the assembly frame. * We brought in the new BF. * We installed the BF-IRM rods and IRM top plate. * We reinstalled the IM flags and other items that had been taken off to use the winch system. * We hooked the BF-IM rod (with hex cable clamp). (We did not unlock the BF keystone.) * We cabled and tested the IM-PIT, IM-ROL and IM-YAW picos and the BF FR stepper (but not, yet, the BF LVDT). |
Line 37: | Line 20: |
==== Plan for week of 8/14 ==== Site closure: Mon, Tue<<BR>> Vacation: Fabian (Mon-Fri)<<BR>> Kamioka: Mark (Wed-Fri), Enzo (Wed-Fri), Yoshioka-kun (Wed, Fri), Ohishi (Thu-Fri).<<BR>> * Remove LBB blade units from PI, then remove blades and send for remachining. * Remove LBB rings from chamber and send for recleaning. * Unlock BF, adjust ballast masses on IM/RM/BS to correct pitch/roll/vertical. * Test, calibrate BF LVDT. Mitaka: Hirata-san (Mon-Fri)<<BR>> * SR Stuff ==== Plan for week of 8/21 ==== Vacation: Fabian (Mon)<<BR>> Kamioka: Mark, Ohishi, Fabian (Tue-Fri), Enzo, Yoshioka-kun (Tue, Wed, Fri), Kozu-kun. * Install side panels of IRM and OSEMs. * Route IRM OSEM cables, test/adjust IRM OSEMs. * Add BF cap; cable and test BF-1 and BF-2 picos. * Lift and weigh BF/IRM/IM/RM/BS; adjust ballast mass. * Crane in SF. Mitaka: Hirata-san. * SR stuff. ==== Vacation Info ==== Fabian: Fri 8/4 through Mon 8/21 Mark: TBD Mid-Oct |
Scraps of text for incorporation in the VIS Meeting Minutes
KAGRA/Subgroups/VIS/MeetingNAOJ
Type B (Mark)
Past week report
At Kamioka (Mark, Ohishi-san, Enzo, Yoshioka-kun, Kozu-kun):
- We finished installing the RM OSEMs and installed the new Type5-2.2 and 5-2.4 OSEM cables.
- We hung the RM and set its pitch.
- We doubled-checked the BS and RM pitch, tightened the clamps and removed the winch system.
- We installed the bottom section of the security structure to protect the RM/BS.
- We lifted the IM/RM/BS section and weighed it. It was about 1.25 kg too heavy for the new BF, so we improvised a lighter set of ballast masses.
- We installed the section of the security structure up to the BF ring, and the BF crossbars and jacks of the assembly frame.
- We brought in the new BF.
- We installed the BF-IRM rods and IRM top plate.
- We reinstalled the IM flags and other items that had been taken off to use the winch system.
- We hooked the BF-IM rod (with hex cable clamp). (We did not unlock the BF keystone.)
- We cabled and tested the IM-PIT, IM-ROL and IM-YAW picos and the BF FR stepper (but not, yet, the BF LVDT).
Plan for week of 8/14
Site closure: Mon, Tue
Vacation: Fabian (Mon-Fri)
Kamioka: Mark (Wed-Fri), Enzo (Wed-Fri), Yoshioka-kun (Wed, Fri), Ohishi (Thu-Fri).
- Remove LBB blade units from PI, then remove blades and send for remachining.
- Remove LBB rings from chamber and send for recleaning.
- Unlock BF, adjust ballast masses on IM/RM/BS to correct pitch/roll/vertical.
- Test, calibrate BF LVDT.
Mitaka: Hirata-san (Mon-Fri)
- SR Stuff
Plan for week of 8/21
Vacation: Fabian (Mon)
Kamioka: Mark, Ohishi, Fabian (Tue-Fri), Enzo, Yoshioka-kun (Tue, Wed, Fri), Kozu-kun.
- Install side panels of IRM and OSEMs.
- Route IRM OSEM cables, test/adjust IRM OSEMs.
- Add BF cap; cable and test BF-1 and BF-2 picos.
- Lift and weigh BF/IRM/IM/RM/BS; adjust ballast mass.
- Crane in SF.
Mitaka: Hirata-san.
- SR stuff.
Vacation Info
Fabian: Fri 8/4 through Mon 8/21 Mark: TBD Mid-Oct