* Type B Past Week Summary * Fabian, Mark, Yokogawa-kun and Kuwahara-kun did BS installation at Kamioka: * Hung RM. * Did permanent routing of RM OSEM cables to IM. * Did temporary routing of RM OSEM in-vacuum cables to flange (4 channels). * Did semi-permanent routing of all OSEM external cables to satellite amps (10 channels) * Did temporary routing of RM OSEMs to PR2 rack (4 channels). * Took data with geophones connected but immobilized and then stored geophones in boxes. * Tested signals from first satellite amp getting to digital system. * Weighed mirror box. * Did fit check of flag holders for stub flags. Very minor adjustments will be needed. * Covered everything in preparation for modifications to clean booth roof (9/20-21). * Hirata-san: * Finished 3D CAD of SR2 and SR3 in tanks, with optical layout included. * Started 3D CAD for SRM. * Checked flag design. * Assembled a bottom filter (ongoing). * Cleaned maraging rods. * Type B ongoing issues * Longer term to-do list * Do Inventor assembly for SRx in chamber and on assembly frame (Hirata) - SR2/SR3 DONE, SRM ongoing. * Part "disk security" top has to be modified - screw positions do not match. * Write more of payload assembly procedure (Fabian) - ONGOING * Write more of BS Assembly Procedure [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]], [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]] (Mark) - ONGOING * Lower breadboard installation to be incorporated into the procedure document. * Work on BS simulation (Fabian) * Do BS Simulink model (Mark, Kokeyama) * Do 2D drawings of SR2 parts (Hirata) * Redesign SRx IM wire clamps for larger prisms, remachined RMs * Order SRM/PRM parts (Hirata/Shoda) * Order SRx fasteners (Hirata) |
=== Type B (Mark) === ==== Past week report ==== At Kamioka (Mark, Ohishi-san, Fabian, Enzo, Hirata-san, Yoshioka-kun, Kozu-kun): * We craned out the SF temporarily and retrieved the lost PEEK cable clamp collet from the BF. * We installed the BF. * We routed cables from the BF via the hex cable clamp to the SF level. * We adjusted the BF trim mass for pitch, roll and vertical, and got the IRM hanging symmetrically around the IM. * We adjusted all the IRM OSEMs laterally and in/out. * We calibrated the SF LVDT and tested the SF FR stepper. * We suspended the SF/... section and weighed it but found the old 7-mm maraging rod adapter did not hold it at the center, so we chad to lift it with slings and could not accurately trim it for pitch/roll. * We craned in the PI with the SF damper ring hanging from it. * We suspended the SF successfully from the PI and unlocked the F0 keystone to check the mass budget. We needed about 1.5 kg extra, which is about right. * However we had to leave out the F0-SF hex cable clamp because of a bad thread on the inside of the cap. Hirata-san will make a new cap by enlarging the 7-mm hole in an old cap to 8 mm. |
Line 37: | Line 19: |
==== Plan for week of 9/4 ==== Mark, Fabian, Enzo (Tue-Fri), Ohishi-san, Hirata-san, Yoshioka-kun (Tue, Wed, Fri), Kozu-kun (Thu, Fri) * Retrieve PEEK piece from BF. * Crane SF back in. * Suspend BF/IRM/IM/RM/BS. * Test SF FR. * Calibrate SF LVDT. * Install SF cap; route cables. * Lift and weigh SF/BF/IRM/IM/RM/BS. * Adjust SF ballast. ==== Plan for week of 9/13 ==== Mark (except Wed), Fabian (except ASJ), Enzo, Ohishi-san, Hirata-san, Yoshioka-kun (Tue, Wed, Fri), Kozu-kun * Prepare magnet ring. * Bring in PI. * Route cables. * Suspend SF/..., adjust tilt of SF and total mass. * Adjust damper gap. ==== Vacation Info ==== Mark: 10/16-24 |
Scraps of text for incorporation in the VIS Meeting Minutes
KAGRA/Subgroups/VIS/MeetingNAOJ
Type B (Mark)
Past week report
At Kamioka (Mark, Ohishi-san, Fabian, Enzo, Hirata-san, Yoshioka-kun, Kozu-kun):
- We craned out the SF temporarily and retrieved the lost PEEK cable clamp collet from the BF.
- We installed the BF.
- We routed cables from the BF via the hex cable clamp to the SF level.
- We adjusted the BF trim mass for pitch, roll and vertical, and got the IRM hanging symmetrically around the IM.
- We adjusted all the IRM OSEMs laterally and in/out.
- We calibrated the SF LVDT and tested the SF FR stepper.
- We suspended the SF/... section and weighed it but found the old 7-mm maraging rod adapter did not hold it at the center, so we chad to lift it with slings and could not accurately trim it for pitch/roll.
- We craned in the PI with the SF damper ring hanging from it.
- We suspended the SF successfully from the PI and unlocked the F0 keystone to check the mass budget. We needed about 1.5 kg extra, which is about right.
- However we had to leave out the F0-SF hex cable clamp because of a bad thread on the inside of the cap. Hirata-san will make a new cap by enlarging the 7-mm hole in an old cap to 8 mm.
Plan for week of 9/4
Mark, Fabian, Enzo (Tue-Fri), Ohishi-san, Hirata-san, Yoshioka-kun (Tue, Wed, Fri), Kozu-kun (Thu, Fri)
- Retrieve PEEK piece from BF.
- Crane SF back in.
- Suspend BF/IRM/IM/RM/BS.
- Test SF FR.
- Calibrate SF LVDT.
- Install SF cap; route cables.
- Lift and weigh SF/BF/IRM/IM/RM/BS.
- Adjust SF ballast.
Plan for week of 9/13
Mark (except Wed), Fabian (except ASJ), Enzo, Ohishi-san, Hirata-san, Yoshioka-kun (Tue, Wed, Fri), Kozu-kun
- Prepare magnet ring.
- Bring in PI.
- Route cables.
- Suspend SF/..., adjust tilt of SF and total mass.
- Adjust damper gap.