Line 5: Line 5:
 * Type B Past Week Summary
  * Fabian, Mark, Yokogawa-kun and Kuwahara-kun did BS installation at Kamioka:
   * Hung RM.
   * Did permanent routing of RM OSEM cables to IM.
   * Did temporary routing of RM OSEM in-vacuum cables to flange (4 channels).
   * Did semi-permanent routing of all OSEM external cables to satellite amps (10 channels)
   * Did temporary routing of RM OSEMs to PR2 rack (4 channels).
   * Took data with geophones connected but immobilized and then stored geophones in boxes.
   * Tested signals from first satellite amp getting to digital system.
   * Weighed mirror box.
   * Did fit check of flag holders for stub flags. Very minor adjustments will be needed.
   * Covered everything in preparation for modifications to clean booth roof (9/20-21).
  * Hirata-san:
   * Finished 3D CAD of SR2 and SR3 in tanks, with optical layout included.
   * Started 3D CAD for SRM.
   * Checked flag design.
   * Assembled a bottom filter (ongoing).
   * Cleaned maraging rods.
 * Type B ongoing issues
 * Longer term to-do list
  * Do Inventor assembly for SRx in chamber and on assembly frame (Hirata) - SR2/SR3 DONE, SRM ongoing.
   * Part "disk security" top has to be modified - screw positions do not match.
  * Write more of payload assembly procedure (Fabian) - ONGOING
  * Write more of BS Assembly Procedure [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]], [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]] (Mark) - ONGOING
  * Lower breadboard installation to be incorporated into the procedure document.
  * Work on BS simulation (Fabian)
  * Do BS Simulink model (Mark, Kokeyama)
  * Do 2D drawings of SR2 parts (Hirata)
  * Redesign SRx IM wire clamps for larger prisms, remachined RMs
  * Order SRM/PRM parts (Hirata/Shoda)
  * Order SRx fasteners (Hirata)
=== Type B (Mark) ===
==== Past week report ====
At Kamioka (Mark, Ohishi-san, Fabian, Enzo, Hirata-san, Yoshioka-kun, Kozu-kun):
 * We put lock nuts on the F0 FR and calibrated the F0 LVDT against FR position and keystone height.
 * Enzo traced the issue with the geophones to a specific cable.
 * We measured the BF and F0 GAS resonant frequencies.
 * We adjusted the spacing of the SR damper.
 * We double-checked the BS pitch with the OL.
 * We debugged the PI yaw mechanism. We managed to get the return spring properly adjusted, but the stepper motor tends to jam because of the strange design.
 * '''We prepared the suspension for lifting and craned it into the tank.'''
 * Hirata-san fixed an issue with one of the nailheads on the LBB intermediate ring support rods not properly seating, by removing the rod and reinstalling it upside down (with the problem nailhead in a less critical position).
 * Enzo and team moved all the in-air cables from the assembly frame to the tank.
 * Fabian and Ohishi-san unlocked the bottom section of the suspension and got it hanging freely.
 
==== Plan for week of 9/25 ====
Mark, Fabian, Enzo (Mon, Tue), Ohishi-san (Tue, Fri), Hirata-san, Yoshioka-kun (Tue, Wed, Fri), Kozu-kun
 * Finish moving in-air cabling and feedthroughs and reconnect in-vacuum cables (through Cu O-rings).
 * Unlock rest of suspension and readjust.
 * Debug electronics.
 * Unclamp LBB ring "sandwich" so LBB Cu ring is suspended on upper rods.
 * Install LBB lower rods and hook LBB.
 * Adjust LBB damper Cu-magnet gap.
 * Measure required ballast for LBB.
 * Remove First Contact, try OL.
 * Prepare for SR2 work.
Line 37: Line 31:
  ==== Plan for week of 10/2 ====
Kamioka: Mark, Enzo, Fabian, Ohishi-san.
 * TFs etc.
Mitaka: Hirata-san?
 * SF design/purchasing.

==== Vacation Info ====
Mark: 10/16-24
Enzo: 9/27-29

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Past week report

At Kamioka (Mark, Ohishi-san, Fabian, Enzo, Hirata-san, Yoshioka-kun, Kozu-kun):

  • We put lock nuts on the F0 FR and calibrated the F0 LVDT against FR position and keystone height.
  • Enzo traced the issue with the geophones to a specific cable.
  • We measured the BF and F0 GAS resonant frequencies.
  • We adjusted the spacing of the SR damper.
  • We double-checked the BS pitch with the OL.
  • We debugged the PI yaw mechanism. We managed to get the return spring properly adjusted, but the stepper motor tends to jam because of the strange design.
  • We prepared the suspension for lifting and craned it into the tank.

  • Hirata-san fixed an issue with one of the nailheads on the LBB intermediate ring support rods not properly seating, by removing the rod and reinstalling it upside down (with the problem nailhead in a less critical position).
  • Enzo and team moved all the in-air cables from the assembly frame to the tank.
  • Fabian and Ohishi-san unlocked the bottom section of the suspension and got it hanging freely.

Plan for week of 9/25

Mark, Fabian, Enzo (Mon, Tue), Ohishi-san (Tue, Fri), Hirata-san, Yoshioka-kun (Tue, Wed, Fri), Kozu-kun

  • Finish moving in-air cabling and feedthroughs and reconnect in-vacuum cables (through Cu O-rings).
  • Unlock rest of suspension and readjust.
  • Debug electronics.
  • Unclamp LBB ring "sandwich" so LBB Cu ring is suspended on upper rods.
  • Install LBB lower rods and hook LBB.
  • Adjust LBB damper Cu-magnet gap.
  • Measure required ballast for LBB.
  • Remove First Contact, try OL.
  • Prepare for SR2 work.

Plan for week of 10/2

Kamioka: Mark, Enzo, Fabian, Ohishi-san.

  • TFs etc.

Mitaka: Hirata-san?

  • SF design/purchasing.

Vacation Info

Mark: 10/16-24 Enzo: 9/27-29