2051
Comment:
|
2620
|
Deletions are marked like this. | Additions are marked like this. |
Line 5: | Line 5: |
* Type B Past Week Summary * Fabian, Mark, Yokogawa-kun and Kuwahara-kun did BS installation at Kamioka: * Hung RM. * Did permanent routing of RM OSEM cables to IM. * Did temporary routing of RM OSEM in-vacuum cables to flange (4 channels). * Did semi-permanent routing of all OSEM external cables to satellite amps (10 channels) * Did temporary routing of RM OSEMs to PR2 rack (4 channels). * Took data with geophones connected but immobilized and then stored geophones in boxes. * Tested signals from first satellite amp getting to digital system. * Weighed mirror box. * Did fit check of flag holders for stub flags. Very minor adjustments will be needed. * Covered everything in preparation for modifications to clean booth roof (9/20-21). * Hirata-san: * Finished 3D CAD of SR2 and SR3 in tanks, with optical layout included. * Started 3D CAD for SRM. * Checked flag design. * Assembled a bottom filter (ongoing). * Cleaned maraging rods. * Type B ongoing issues * Longer term to-do list * Do Inventor assembly for SRx in chamber and on assembly frame (Hirata) - SR2/SR3 DONE, SRM ongoing. * Part "disk security" top has to be modified - screw positions do not match. * Write more of payload assembly procedure (Fabian) - ONGOING * Write more of BS Assembly Procedure [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]], [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]] (Mark) - ONGOING * Lower breadboard installation to be incorporated into the procedure document. * Work on BS simulation (Fabian) * Do BS Simulink model (Mark, Kokeyama) * Do 2D drawings of SR2 parts (Hirata) * Redesign SRx IM wire clamps for larger prisms, remachined RMs * Order SRM/PRM parts (Hirata/Shoda) * Order SRx fasteners (Hirata) |
=== Type B (Mark) === ==== Report for week of 12/25 ==== * Hirata-san got the L-brackets machined and washed, and installed them on the IM ring bars. * Shoda-san recovered the BS from the power outage on 12/25. * Miyakawa-san fixed an issue with the SR2 RTM which had prevented it from running. * Shoda-san, Hirata-san and Kozu-kun weighed the IM without ballast masses, and then added the lower masses and installed the IM on the assembly frame. * They cleaned the assembly frame and installed new jack receptacles on the load gauge adapter. * They installed the winch system on the IM, and inspected the clamp pieces for possible scratches. * They ran cables for the SR2 steppers and OSEMs. * They calibrated the BF LVDT. |
Line 37: | Line 16: |
==== Report for week of 1/4 ==== * Mark fixed a number of errors with the Type B screens. ==== Report for week of 1/9 ==== * We weighed the mirror in its box (and later the empty box), and the RM. * Fabian worked on the SR2/SR3/SRM mass budget and did an inventory of spare ballast masses. * We hung the SR2 and RM. * We assembled the bottom section of the security structure below the RM. * We cabled the RM OSEMs up to the IM. * Hirata-san gave up on waiting for a third quote for the blades and blade parts and started the ordering process. * Hirata-san got rod cable clamp parts from Takahashi-san and worked on drawings for the improved BS vertical and yaw adjusters. ==== Plan for week of 1/15 ==== * Fabian at Mitaka Monday 1/15 to inspect filter load test items. * All at Kamioka. * Shoda-san to work on readjusting PR3 and also making OSEMs. * Enzo and Kozu-kun to help with making OSEMs. * Test RM OSEMs. * Check coil driver is successfully driving current. * Time permitting, do TF test from coils to optical sensor. * Suspend IM using load gauge adapter, and check/adjust total mass and balance. ==== Plan for week of 1/22 ==== * All at Kamioka * Bring in BF and suspend IM. * Route final RM/IM cables up to below BF. * Recheck/adjust total mass and balance. * Route selected cables to flange. * Test IM picos and BF yaw pico. ==== Plan for week of 1/29 ==== * Enzo at Mitaka 1/29 and most of 1/30, then vacation. * Kozu-kun away. * All others at Kamioka. * Build IRM around IM. * Cable/test/adjust IM OSEMs. * Time permitting, do TFs from IM OSEMs to themselves and to optical sensor. ==== Vacation Info ==== * Enzo 1/30-2/19 (at Mitaka 1/29, part of 1/30) * Kozu-kun 1/29-2/2 |
Scraps of text for incorporation in the VIS Meeting Minutes
KAGRA/Subgroups/VIS/MeetingNAOJ
Type B (Mark)
Report for week of 12/25
- Hirata-san got the L-brackets machined and washed, and installed them on the IM ring bars.
- Shoda-san recovered the BS from the power outage on 12/25.
- Miyakawa-san fixed an issue with the SR2 RTM which had prevented it from running.
- Shoda-san, Hirata-san and Kozu-kun weighed the IM without ballast masses, and then added the lower masses and installed the IM on the assembly frame.
- They cleaned the assembly frame and installed new jack receptacles on the load gauge adapter.
- They installed the winch system on the IM, and inspected the clamp pieces for possible scratches.
- They ran cables for the SR2 steppers and OSEMs.
- They calibrated the BF LVDT.
Report for week of 1/4
- Mark fixed a number of errors with the Type B screens.
Report for week of 1/9
- We weighed the mirror in its box (and later the empty box), and the RM.
- Fabian worked on the SR2/SR3/SRM mass budget and did an inventory of spare ballast masses.
- We hung the SR2 and RM.
- We assembled the bottom section of the security structure below the RM.
- We cabled the RM OSEMs up to the IM.
- Hirata-san gave up on waiting for a third quote for the blades and blade parts and started the ordering process.
- Hirata-san got rod cable clamp parts from Takahashi-san and worked on drawings for the improved BS vertical and yaw adjusters.
Plan for week of 1/15
- Fabian at Mitaka Monday 1/15 to inspect filter load test items.
- All at Kamioka.
- Shoda-san to work on readjusting PR3 and also making OSEMs.
- Enzo and Kozu-kun to help with making OSEMs.
- Test RM OSEMs.
- Check coil driver is successfully driving current.
- Time permitting, do TF test from coils to optical sensor.
- Suspend IM using load gauge adapter, and check/adjust total mass and balance.
Plan for week of 1/22
- All at Kamioka
- Bring in BF and suspend IM.
- Route final RM/IM cables up to below BF.
- Recheck/adjust total mass and balance.
- Route selected cables to flange.
- Test IM picos and BF yaw pico.
Plan for week of 1/29
- Enzo at Mitaka 1/29 and most of 1/30, then vacation.
- Kozu-kun away.
- All others at Kamioka.
- Build IRM around IM.
- Cable/test/adjust IM OSEMs.
- Time permitting, do TFs from IM OSEMs to themselves and to optical sensor.
Vacation Info
- Enzo 1/30-2/19 (at Mitaka 1/29, part of 1/30)
- Kozu-kun 1/29-2/2