2051
Comment:
|
2520
|
Deletions are marked like this. | Additions are marked like this. |
Line 5: | Line 5: |
* Type B Past Week Summary * Fabian, Mark, Yokogawa-kun and Kuwahara-kun did BS installation at Kamioka: * Hung RM. * Did permanent routing of RM OSEM cables to IM. * Did temporary routing of RM OSEM in-vacuum cables to flange (4 channels). * Did semi-permanent routing of all OSEM external cables to satellite amps (10 channels) * Did temporary routing of RM OSEMs to PR2 rack (4 channels). * Took data with geophones connected but immobilized and then stored geophones in boxes. * Tested signals from first satellite amp getting to digital system. * Weighed mirror box. * Did fit check of flag holders for stub flags. Very minor adjustments will be needed. * Covered everything in preparation for modifications to clean booth roof (9/20-21). * Hirata-san: * Finished 3D CAD of SR2 and SR3 in tanks, with optical layout included. * Started 3D CAD for SRM. * Checked flag design. * Assembled a bottom filter (ongoing). * Cleaned maraging rods. * Type B ongoing issues * Longer term to-do list * Do Inventor assembly for SRx in chamber and on assembly frame (Hirata) - SR2/SR3 DONE, SRM ongoing. * Part "disk security" top has to be modified - screw positions do not match. * Write more of payload assembly procedure (Fabian) - ONGOING * Write more of BS Assembly Procedure [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]], [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]] (Mark) - ONGOING * Lower breadboard installation to be incorporated into the procedure document. * Work on BS simulation (Fabian) * Do BS Simulink model (Mark, Kokeyama) * Do 2D drawings of SR2 parts (Hirata) * Redesign SRx IM wire clamps for larger prisms, remachined RMs * Order SRM/PRM parts (Hirata/Shoda) * Order SRx fasteners (Hirata) |
=== Type B (Mark) === ==== Report for week of 2/26 ==== * We routed all the cables from the BF level up via the flying saucer to the SF. * Hirata-san tried filing the SF cap to improve the fit, but without much success. * Hirata-san installed the Cu segments and cable clamps on the SF cap and the SF LVDT and FR cables. * We cabled and tested the BF cap picos and the SF LVDT and FR. (The LVDT still needs a full calibration.) * We worked on recovering the IM OSEM alignment. |
Line 37: | Line 13: |
==== Plan for week of 3/5 ==== * Shoda-san at Mitaka. * Hirata-san vacation Mon 3/5, then Kamioka * Fabian Mitaka Mon-Tue (COMSOL training), Kamioka Wed-Fri. * Others at Kamioka. * - * '''Remove LBB temporary ballast masses from BS chamber.''' * Finish recovering IM OSEM alignment. * Calibrate SF LVDT. * Lift SF/... section and check total mass and balance. * Get SRM tank mushroom section installed (Hirata-san, Kimura-san) * Set up for rebuilding of two BFs. ==== Plan for week of 3/12 ==== * Shoda-san at Mitaka. * Mark at ASJ (Chiba) Fri, then Mitaka. * Hirata-san vacation Mon 3/5; Kamioka Tue-Thu; Mitaka Fri * Others Kamioka Mon-Thu * Install boxes in SR3 and SRM racks. * Lay SR3 in-air cabling. * Continue rebuild of BFs. ==== Plan for week of 3/19 ==== * Mark at LVC meeting * All others at Mitaka * Make two sets of IM OSEMs * Make last in-air pico adapter cable * Make three in-air stepper splitter cables for SR2, SR3 and SRM. * Set up Dummy BS prism removal. ==== Plan for week of 3/26 ==== * Mark vacation. * Shoda-san at Mitaka * Others at Kamioka * -- * F0 Prototype Blade Test * Characterize blades. * Choose best set of three. * Remove cracked blades from filter in SRM area. * Set up test weights in SRM area, first floor. * Remove floor panel in SRM area, second floor. * Install chosen blades. * Measure load capacity. ==== To-Do Lists, Schedule ==== * [[KAGRA/Subgroups/VIS/TypeB/March2018]] * [[KAGRA/Subgroups/VIS/TypeB/April2018]] * [[KAGRA/Subgroups/VIS/TypeB/ToDoBS]] * [[KAGRA/Subgroups/VIS/TypeB/ToDoSR]] * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7779|JGW-L1807779-v1 Type B Schedule (SR)]] ==== Vacation Info ==== * Mark at LVC, then vacation, 3/18 (Sun) - 4/1 (Sun) * Hirata-san vacation, Mon 3/5. * Fabian vacation, 3/26-4/27 (then gone). |
Scraps of text for incorporation in the VIS Meeting Minutes
KAGRA/Subgroups/VIS/MeetingNAOJ
Type B (Mark)
Report for week of 2/26
- We routed all the cables from the BF level up via the flying saucer to the SF.
- Hirata-san tried filing the SF cap to improve the fit, but without much success.
- Hirata-san installed the Cu segments and cable clamps on the SF cap and the SF LVDT and FR cables.
- We cabled and tested the BF cap picos and the SF LVDT and FR. (The LVDT still needs a full calibration.)
- We worked on recovering the IM OSEM alignment.
Plan for week of 3/5
- Shoda-san at Mitaka.
- Hirata-san vacation Mon 3/5, then Kamioka
- Fabian Mitaka Mon-Tue (COMSOL training), Kamioka Wed-Fri.
- Others at Kamioka.
- -
Remove LBB temporary ballast masses from BS chamber.
- Finish recovering IM OSEM alignment.
- Calibrate SF LVDT.
- Lift SF/... section and check total mass and balance.
- Get SRM tank mushroom section installed (Hirata-san, Kimura-san)
- Set up for rebuilding of two BFs.
Plan for week of 3/12
- Shoda-san at Mitaka.
- Mark at ASJ (Chiba) Fri, then Mitaka.
- Hirata-san vacation Mon 3/5; Kamioka Tue-Thu; Mitaka Fri
- Others Kamioka Mon-Thu
- Install boxes in SR3 and SRM racks.
- Lay SR3 in-air cabling.
- Continue rebuild of BFs.
Plan for week of 3/19
- Mark at LVC meeting
- All others at Mitaka
- Make two sets of IM OSEMs
- Make last in-air pico adapter cable
- Make three in-air stepper splitter cables for SR2, SR3 and SRM.
- Set up Dummy BS prism removal.
Plan for week of 3/26
- Mark vacation.
- Shoda-san at Mitaka
- Others at Kamioka
- --
- F0 Prototype Blade Test
- Characterize blades.
- Choose best set of three.
- Remove cracked blades from filter in SRM area.
- Set up test weights in SRM area, first floor.
- Remove floor panel in SRM area, second floor.
- Install chosen blades.
- Measure load capacity.
To-Do Lists, Schedule
Vacation Info
- Mark at LVC, then vacation, 3/18 (Sun) - 4/1 (Sun)
- Hirata-san vacation, Mon 3/5.
- Fabian vacation, 3/26-4/27 (then gone).