 * Type B Past Week Summary
  * Fabian, Mark, Yokogawa-kun and Kuwahara-kun did BS installation at Kamioka:
   * Hung RM.
   * Did permanent routing of RM OSEM cables to IM.
   * Did temporary routing of RM OSEM in-vacuum cables to flange (4 channels).
   * Did semi-permanent routing of all OSEM external cables to satellite amps (10 channels)
   * Did temporary routing of RM OSEMs to PR2 rack (4 channels).
   * Took data with geophones connected but immobilized and then stored geophones in boxes.
   * Tested signals from first satellite amp getting to digital system.
   * Weighed mirror box.
   * Did fit check of flag holders for stub flags. Very minor adjustments will be needed.
   * Covered everything in preparation for modifications to clean booth roof (9/20-21).
  * Hirata-san:
   * Finished 3D CAD of SR2 and SR3 in tanks, with optical layout included.
   * Started 3D CAD for SRM.
   * Checked flag design.
   * Assembled a bottom filter (ongoing).
   * Cleaned maraging rods.
 * Type B ongoing issues
 * Longer term to-do list
  * Do Inventor assembly for SRx in chamber and on assembly frame (Hirata) - SR2/SR3 DONE, SRM ongoing.
   * Part "disk security" top has to be modified - screw positions do not match.
  * Write more of payload assembly procedure (Fabian) - ONGOING
  * Write more of BS Assembly Procedure [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]], [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]] (Mark) - ONGOING
  * Lower breadboard installation to be incorporated into the procedure document.
  * Work on BS simulation (Fabian)
  * Do BS Simulink model (Mark, Kokeyama)
  * Do 2D drawings of SR2 parts (Hirata)
  * Redesign SRx IM wire clamps for larger prisms, remachined RMs
  * Order SRM/PRM parts (Hirata/Shoda)
  * Order SRx fasteners (Hirata)
=== Type B (Mark) ===
==== Report for week of 2/26 ====
 * We routed all the cables from the BF level up via the flying saucer to the SF.
 * Hirata-san tried filing the SF cap to improve the fit, but without much success.
 * Hirata-san installed the Cu segments and cable clamps on the SF cap and the SF LVDT and FR cables.
 * We cabled and tested the BF cap picos and the SF LVDT and FR. (The LVDT still needs a full calibration.)
 * We worked on recovering the IM OSEM alignment.
Line 37: Line 13:
  ==== Plan for week of 3/5 ====
 * Shoda-san at Mitaka.
 * Hirata-san vacation Mon 3/5, then Kamioka
 * Fabian Mitaka Mon-Tue (COMSOL training), Kamioka Wed-Fri.
 * Others at Kamioka.
 * -
 * '''Remove LBB temporary ballast masses from BS chamber.'''
 * Finish recovering IM OSEM alignment.
 * Calibrate SF LVDT.
 * Lift SF/... section and check total mass and balance.
 * Get SRM tank mushroom section installed (Hirata-san, Kimura-san)
 * Set up for rebuilding of two BFs.

==== Plan for week of 3/12 ====
 * Shoda-san at Mitaka.
 * Mark at ASJ (Chiba) Fri, then Mitaka.
 * Hirata-san vacation Mon 3/5; Kamioka Tue-Thu; Mitaka Fri
 * Others Kamioka Mon-Thu
 * Install boxes in SR3 and SRM racks.
 * Lay SR3 in-air cabling.
 * Continue rebuild of BFs.

==== Plan for week of 3/19 ====
 * Mark at LVC meeting
 * All others at Mitaka
 * Make two sets of IM OSEMs
 * Make last in-air pico adapter cable
 * Make three in-air stepper splitter cables for SR2, SR3 and SRM.
 * Set up Dummy BS prism removal.

==== Plan for week of 3/26 ====
 * Mark vacation.
 * Shoda-san at Mitaka
 * Others at Kamioka
 * --
 * F0 Prototype Blade Test
  * Characterize blades.
  * Choose best set of three.
  * Remove cracked blades from filter in SRM area.
  * Set up test weights in SRM area, first floor.
  * Remove floor panel in SRM area, second floor.
  * Install chosen blades.
  * Measure load capacity.

==== To-Do Lists, Schedule ====
 * [[KAGRA/Subgroups/VIS/TypeB/March2018]]
 * [[KAGRA/Subgroups/VIS/TypeB/April2018]]
 * [[KAGRA/Subgroups/VIS/TypeB/ToDoBS]]
 * [[KAGRA/Subgroups/VIS/TypeB/ToDoSR]]
 * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7779|JGW-L1807779-v1 Type B Schedule (SR)]]

==== Vacation Info ====
 * Mark at LVC, then vacation, 3/18 (Sun) - 4/1 (Sun)
 * Hirata-san vacation, Mon 3/5.
 * Fabian vacation, 3/26-4/27 (then gone).

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Report for week of 2/26

  • We routed all the cables from the BF level up via the flying saucer to the SF.
  • Hirata-san tried filing the SF cap to improve the fit, but without much success.
  • Hirata-san installed the Cu segments and cable clamps on the SF cap and the SF LVDT and FR cables.
  • We cabled and tested the BF cap picos and the SF LVDT and FR. (The LVDT still needs a full calibration.)
  • We worked on recovering the IM OSEM alignment.

Plan for week of 3/5

  • Shoda-san at Mitaka.
  • Hirata-san vacation Mon 3/5, then Kamioka
  • Fabian Mitaka Mon-Tue (COMSOL training), Kamioka Wed-Fri.
  • Others at Kamioka.
  • -
  • Remove LBB temporary ballast masses from BS chamber.

  • Finish recovering IM OSEM alignment.
  • Calibrate SF LVDT.
  • Lift SF/... section and check total mass and balance.
  • Get SRM tank mushroom section installed (Hirata-san, Kimura-san)
  • Set up for rebuilding of two BFs.

Plan for week of 3/12

  • Shoda-san at Mitaka.
  • Mark at ASJ (Chiba) Fri, then Mitaka.
  • Hirata-san vacation Mon 3/5; Kamioka Tue-Thu; Mitaka Fri
  • Others Kamioka Mon-Thu
  • Install boxes in SR3 and SRM racks.
  • Lay SR3 in-air cabling.
  • Continue rebuild of BFs.

Plan for week of 3/19

  • Mark at LVC meeting
  • All others at Mitaka
  • Make two sets of IM OSEMs
  • Make last in-air pico adapter cable
  • Make three in-air stepper splitter cables for SR2, SR3 and SRM.
  • Set up Dummy BS prism removal.

Plan for week of 3/26

  • Mark vacation.
  • Shoda-san at Mitaka
  • Others at Kamioka
  • --
  • F0 Prototype Blade Test
    • Characterize blades.
    • Choose best set of three.
    • Remove cracked blades from filter in SRM area.
    • Set up test weights in SRM area, first floor.
    • Remove floor panel in SRM area, second floor.
    • Install chosen blades.
    • Measure load capacity.

To-Do Lists, Schedule

Vacation Info

  • Mark at LVC, then vacation, 3/18 (Sun) - 4/1 (Sun)
  • Hirata-san vacation, Mon 3/5.
  • Fabian vacation, 3/26-4/27 (then gone).