Differences between revisions 67 and 305 (spanning 238 versions)
Revision 67 as of 2016-09-16 13:33:31
Size: 2051
Editor: MarkBarton
Comment:
Revision 305 as of 2018-07-27 14:19:43
Size: 2930
Editor: MarkBarton
Comment:
Deletions are marked like this. Additions are marked like this.
Line 5: Line 5:
 * Type B Past Week Summary
  * Fabian, Mark, Yokogawa-kun and Kuwahara-kun did BS installation at Kamioka:
   * Hung RM.
   * Did permanent routing of RM OSEM cables to IM.
   * Did temporary routing of RM OSEM in-vacuum cables to flange (4 channels).
   * Did semi-permanent routing of all OSEM external cables to satellite amps (10 channels)
   * Did temporary routing of RM OSEMs to PR2 rack (4 channels).
   * Took data with geophones connected but immobilized and then stored geophones in boxes.
   * Tested signals from first satellite amp getting to digital system.
   * Weighed mirror box.
   * Did fit check of flag holders for stub flags. Very minor adjustments will be needed.
   * Covered everything in preparation for modifications to clean booth roof (9/20-21).
  * Hirata-san:
   * Finished 3D CAD of SR2 and SR3 in tanks, with optical layout included.
   * Started 3D CAD for SRM.
   * Checked flag design.
   * Assembled a bottom filter (ongoing).
   * Cleaned maraging rods.
 * Type B ongoing issues
 * Longer term to-do list
  * Do Inventor assembly for SRx in chamber and on assembly frame (Hirata) - SR2/SR3 DONE, SRM ongoing.
   * Part "disk security" top has to be modified - screw positions do not match.
  * Write more of payload assembly procedure (Fabian) - ONGOING
  * Write more of BS Assembly Procedure [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]], [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]] (Mark) - ONGOING
  * Lower breadboard installation to be incorporated into the procedure document.
  * Work on BS simulation (Fabian)
  * Do BS Simulink model (Mark, Kokeyama)
  * Do 2D drawings of SR2 parts (Hirata)
  * Redesign SRx IM wire clamps for larger prisms, remachined RMs
  * Order SRM/PRM parts (Hirata/Shoda)
  * Order SRx fasteners (Hirata)
=== Type B (Mark) ===
==== Report for week of 7/23 ====
 * We finished adding cable clamps to the SR2 PI and SF.
 * We craned in the SR2 PI and installed the PI-SF rod. As expected, there was not quite enough load capacity for even a 2 Cu-segment SF.
 * We changed the CuBe spring on the SR2 PI from an F2 type to an F1 and got about an extra 2 kg, which is plenty for 2 Cu segments.
 * We moved the feedthroughs from the SR3 assembly frame to the SR3 tank. Mirapro then moved the assembly frame to the SRM area. Mirapro also moved the duct on the +Y side of the SR3 tank to give us access to that side.
 * We laid a new set of SR3 in-air cables running directly to the tank. (We will repurpose the original set for SRM.)
 * We reconnected the SR3 cables on both sides of the feedthroughs. We had to adjust the routing of the in-vacuum ones several times to stop them touching the tank, but we finally found a good solution.
 * With help from Ohishi-san we removed the First Contact and then unlocked the whole suspension by stages. We need to check the optic pitch and do a little more mechanical adjustment but we were able to take TFs and implement IM and GAS control filters.
 * Hirata-san and Fujii-kun received most of the SRM metal mass parts, did inventory and practiced some of the key steps in the assembly, especially inserting the Sol-Black coated parts without touching the delicate surfaces.
 * Mark did inventory of the BIO stuff for the WD and of the OL parts.
Line 37: Line 17:
==== Plan for week of 7/30 ====
 * Mark, Enzo, Hirata-san, Fabian, Kozu-kun, Terrence, Panwei at Kamioka Mon-Fri.
 * Kozu-kun works at Mozumi Mon, Fri, and Thu afternoon.

===== SR3 =====
 * Finalize optic pitch, OSEM alignment.
 * Hook LBB, add ballast mass, set up temporary OL (horizontal beam, pitch/yaw only).
 * Identify/acquire items required for final OL (steering mirrors, second QPD, lens, collimator).

===== SR2 =====
 * Fix issue with PI/SS/chain alignment.
 * Put magnets on SR damper ring (2 Cu segment pattern).
 * Remove PI-SF rod temporarily, install Cu segments and damper ring.
 * Do vertical height budget; choose optimum F0 keystone height.
 * Add estimated final ballast mass.
 * Do PI cable routing.
 * Adjust ballast/trim mass, with reserve for cables.
Line 38: Line 35:
===== SRM =====
 * Set up filter tuning area.
 * Tune F0 for SRM.
 * Add LBB blade units, cable clamps etc.
 * Check PI coil connections, IP LVDT magnets.

==== To-Do Lists, Schedule ====
 * [[KAGRA/Subgroups/VIS/TypeB/ToDoBS]]
 * [[KAGRA/Subgroups/VIS/TypeB/ToDoSR]]
 * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7779|JGW-L1807779 Type B Schedule (SR)]]

==== Vacation Info ====
 * Terrence: 8/24-26 f2f, then returns to Hong Kong.
 * Enzo: 9/14 JPS, 9/15 through 10/8 vacation in Chile.

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Report for week of 7/23

  • We finished adding cable clamps to the SR2 PI and SF.
  • We craned in the SR2 PI and installed the PI-SF rod. As expected, there was not quite enough load capacity for even a 2 Cu-segment SF.
  • We changed the CuBe spring on the SR2 PI from an F2 type to an F1 and got about an extra 2 kg, which is plenty for 2 Cu segments.

  • We moved the feedthroughs from the SR3 assembly frame to the SR3 tank. Mirapro then moved the assembly frame to the SRM area. Mirapro also moved the duct on the +Y side of the SR3 tank to give us access to that side.
  • We laid a new set of SR3 in-air cables running directly to the tank. (We will repurpose the original set for SRM.)
  • We reconnected the SR3 cables on both sides of the feedthroughs. We had to adjust the routing of the in-vacuum ones several times to stop them touching the tank, but we finally found a good solution.
  • With help from Ohishi-san we removed the First Contact and then unlocked the whole suspension by stages. We need to check the optic pitch and do a little more mechanical adjustment but we were able to take TFs and implement IM and GAS control filters.
  • Hirata-san and Fujii-kun received most of the SRM metal mass parts, did inventory and practiced some of the key steps in the assembly, especially inserting the Sol-Black coated parts without touching the delicate surfaces.
  • Mark did inventory of the BIO stuff for the WD and of the OL parts.

Plan for week of 7/30

  • Mark, Enzo, Hirata-san, Fabian, Kozu-kun, Terrence, Panwei at Kamioka Mon-Fri.
  • Kozu-kun works at Mozumi Mon, Fri, and Thu afternoon.

SR3
  • Finalize optic pitch, OSEM alignment.
  • Hook LBB, add ballast mass, set up temporary OL (horizontal beam, pitch/yaw only).
  • Identify/acquire items required for final OL (steering mirrors, second QPD, lens, collimator).

SR2
  • Fix issue with PI/SS/chain alignment.
  • Put magnets on SR damper ring (2 Cu segment pattern).
  • Remove PI-SF rod temporarily, install Cu segments and damper ring.
  • Do vertical height budget; choose optimum F0 keystone height.
  • Add estimated final ballast mass.
  • Do PI cable routing.
  • Adjust ballast/trim mass, with reserve for cables.

SRM
  • Set up filter tuning area.
  • Tune F0 for SRM.
  • Add LBB blade units, cable clamps etc.
  • Check PI coil connections, IP LVDT magnets.

To-Do Lists, Schedule

Vacation Info

  • Terrence: 8/24-26 f2f, then returns to Hong Kong.
  • Enzo: 9/14 JPS, 9/15 through 10/8 vacation in Chile.

KAGRA/Subgroups/VIS/TypeB/Minutes (last edited 2022-10-28 10:02:46 by fabian.arellano)