 * Type B Past Week Summary
  * Fabian, Mark, Yokogawa-kun and Kuwahara-kun did BS installation at Kamioka:
   * Hung RM.
   * Did permanent routing of RM OSEM cables to IM.
   * Did temporary routing of RM OSEM in-vacuum cables to flange (4 channels).
   * Did semi-permanent routing of all OSEM external cables to satellite amps (10 channels)
   * Did temporary routing of RM OSEMs to PR2 rack (4 channels).
   * Took data with geophones connected but immobilized and then stored geophones in boxes.
   * Tested signals from first satellite amp getting to digital system.
   * Weighed mirror box.
   * Did fit check of flag holders for stub flags. Very minor adjustments will be needed.
   * Covered everything in preparation for modifications to clean booth roof (9/20-21).
  * Hirata-san:
   * Finished 3D CAD of SR2 and SR3 in tanks, with optical layout included.
   * Started 3D CAD for SRM.
   * Checked flag design.
   * Assembled a bottom filter (ongoing).
   * Cleaned maraging rods.
 * Type B ongoing issues
 * Longer term to-do list
  * Do Inventor assembly for SRx in chamber and on assembly frame (Hirata) - SR2/SR3 DONE, SRM ongoing.
   * Part "disk security" top has to be modified - screw positions do not match.
  * Write more of payload assembly procedure (Fabian) - ONGOING
  * Write more of BS Assembly Procedure [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]], [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]] (Mark) - ONGOING
  * Lower breadboard installation to be incorporated into the procedure document.
  * Work on BS simulation (Fabian)
  * Do BS Simulink model (Mark, Kokeyama)
  * Do 2D drawings of SR2 parts (Hirata)
  * Redesign SRx IM wire clamps for larger prisms, remachined RMs
  * Order SRM/PRM parts (Hirata/Shoda)
  * Order SRx fasteners (Hirata)
=== Type B (Mark) ===
==== Report for the week of 4/1 ====
 * Support of Type Bp
  * Hirata-san procured the jigs for PRs and Takahashi-san tested one at TAMA.
  * Hirata-san cleaned up the flags for PR2 and Mark did the one for PRM.
  * Fabian helped Fujii-kun and Takashashi-san to reglue the flags.
 * Mark did a lot of maintenance on the MEDM screens:
  * Made the name of the suspension more obvious (no yellow text!).
  * Added rack temperature indicators.
  * Fixed the labels in the ADC screen (to reflect the LEN OL moving from ADC#0 to #1).
  * Fixed broken links.
  * Committed files to the SVN.
 * Mark did maintenance on the Guardian to make it give more helpful messages in the TRIGGER state. Formerly it only checked the user model watchdog and the coil driver watchdog, not the DACKILL, and gave the same generic notification for both. Now it checks all three and tells the user which need attention.
 * Mark tidied up the cables in the SR2 rack and returned a large pile of no-longer-used cables to the tent.
 * Mark started a !HealthCheck page on the Operation Manual wiki.
Fabian and Mark
==== Plan for week of 4/8 ====
 * Mark, Fabian at Kamioka Mon-Fri.
 * Help with Type Bp.
 * Health checks on Type B.
 * Monitor pumpdown.
 * Work on Type B paper.
 * Modify RT models and/or Guardian to revert to the SAFE state under control in all but the most extreme emergency situations (rather than suddenly shutting off all output).
 * Tidy up.
  * Gather and clean tools.
  * Gather and organize unused parts and fasteners.
Line 37: Line 31:
  ==== Plan for week of 4/15 ====
 * Mark at Mitaka 4/15, Kamioka 4/16-18, f2f 4/19.
 * Fabian at Kamioka 4/15-18, f2f 4/19.

==== Vacation/Travel Info ====
 * Mark at Mitaka 4/15.
 * f2f 4/19 (Friday), 4/20, 4/21.
 * Terrence's next visit from 4/18.
 * Fabian's vacation 4/26 to 5/10.
 * Mark's vacation from about 5/22 to 6/11.
 * Mark's final day 6/28.

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Report for the week of 4/1

  • Support of Type Bp
    • Hirata-san procured the jigs for PRs and Takahashi-san tested one at TAMA.
    • Hirata-san cleaned up the flags for PR2 and Mark did the one for PRM.
    • Fabian helped Fujii-kun and Takashashi-san to reglue the flags.
  • Mark did a lot of maintenance on the MEDM screens:
    • Made the name of the suspension more obvious (no yellow text!).
    • Added rack temperature indicators.
    • Fixed the labels in the ADC screen (to reflect the LEN OL moving from ADC#0 to #1).
    • Fixed broken links.
    • Committed files to the SVN.
  • Mark did maintenance on the Guardian to make it give more helpful messages in the TRIGGER state. Formerly it only checked the user model watchdog and the coil driver watchdog, not the DACKILL, and gave the same generic notification for both. Now it checks all three and tells the user which need attention.
  • Mark tidied up the cables in the SR2 rack and returned a large pile of no-longer-used cables to the tent.
  • Mark started a HealthCheck page on the Operation Manual wiki.

Fabian and Mark

Plan for week of 4/8

  • Mark, Fabian at Kamioka Mon-Fri.
  • Help with Type Bp.
  • Health checks on Type B.
  • Monitor pumpdown.
  • Work on Type B paper.
  • Modify RT models and/or Guardian to revert to the SAFE state under control in all but the most extreme emergency situations (rather than suddenly shutting off all output).
  • Tidy up.
    • Gather and clean tools.
    • Gather and organize unused parts and fasteners.

Plan for week of 4/15

  • Mark at Mitaka 4/15, Kamioka 4/16-18, f2f 4/19.
  • Fabian at Kamioka 4/15-18, f2f 4/19.

Vacation/Travel Info

  • Mark at Mitaka 4/15.
  • f2f 4/19 (Friday), 4/20, 4/21.
  • Terrence's next visit from 4/18.
  • Fabian's vacation 4/26 to 5/10.
  • Mark's vacation from about 5/22 to 6/11.
  • Mark's final day 6/28.