2051
Comment:
|
1797
|
Deletions are marked like this. | Additions are marked like this. |
Line 5: | Line 5: |
* Type B Past Week Summary * Fabian, Mark, Yokogawa-kun and Kuwahara-kun did BS installation at Kamioka: * Hung RM. * Did permanent routing of RM OSEM cables to IM. * Did temporary routing of RM OSEM in-vacuum cables to flange (4 channels). * Did semi-permanent routing of all OSEM external cables to satellite amps (10 channels) * Did temporary routing of RM OSEMs to PR2 rack (4 channels). * Took data with geophones connected but immobilized and then stored geophones in boxes. * Tested signals from first satellite amp getting to digital system. * Weighed mirror box. * Did fit check of flag holders for stub flags. Very minor adjustments will be needed. * Covered everything in preparation for modifications to clean booth roof (9/20-21). * Hirata-san: * Finished 3D CAD of SR2 and SR3 in tanks, with optical layout included. * Started 3D CAD for SRM. * Checked flag design. * Assembled a bottom filter (ongoing). * Cleaned maraging rods. * Type B ongoing issues * Longer term to-do list * Do Inventor assembly for SRx in chamber and on assembly frame (Hirata) - SR2/SR3 DONE, SRM ongoing. * Part "disk security" top has to be modified - screw positions do not match. * Write more of payload assembly procedure (Fabian) - ONGOING * Write more of BS Assembly Procedure [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]], [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]] (Mark) - ONGOING * Lower breadboard installation to be incorporated into the procedure document. * Work on BS simulation (Fabian) * Do BS Simulink model (Mark, Kokeyama) * Do 2D drawings of SR2 parts (Hirata) * Redesign SRx IM wire clamps for larger prisms, remachined RMs * Order SRM/PRM parts (Hirata/Shoda) * Order SRx fasteners (Hirata) |
* Mark, Fabian and Enzo continued BS Test Hang work: * We installed the BF fishing rod stepper motor adaptor cable. * We tried to install the BF LVDT cable but first we encountered trouble routing it, and then several wires broke at the D-Sub end. * We laid 6 in-air cables from the tank to the PR2 rank for BF and SF picos, steppers and LVDTs. * We lifted the BF/IRM/IM/RM/BS section to weigh it and check its balance. * It was 195.6 kg, which is 18 kg(!) less than the capacity of the SF. * There was a major imbalance in roll: with all four built-in trim masses moved up the +Y end, it still needed 270 g of extra trim mass to be level. * Unfortunately when we put the payload, the IM was slightly yawed and ended up on the horizontal EQ stop screws. This let the IM-BF maraging rod go slack, which disturbed the leveling of the IM (because every time it is picked up the maraging rod settles in a different place, giving a different suspension point). We may have to partly disassemble the IRM and rearrange the time mass on the the IM. * We shipped BS mirror box parts to Shoda-san and components for a new LVDT cable to Hirata-san. * We posed for pictures of the BS by a team from National Geographic. * Hirata-san * Did parts and fastener lists for the SR payload. * Did a 3D model with the SR suspension on the BS assembly frame (to help Mark make adjustments to the frame design). * Did 2D drawings of Fabian's concept for BS EQ stop parts. * Did a 3D model of a wire clamp with replaceable jaw parts (to avoid having to reuse parts with scars from pressure). * Did 2D drawings of a new wire clamps for on top of the BS and SR RMs. |
Scraps of text for incorporation in the VIS Meeting Minutes
KAGRA/Subgroups/VIS/MeetingNAOJ
- Mark, Fabian and Enzo continued BS Test Hang work:
- We installed the BF fishing rod stepper motor adaptor cable.
- We tried to install the BF LVDT cable but first we encountered trouble routing it, and then several wires broke at the D-Sub end.
- We laid 6 in-air cables from the tank to the PR2 rank for BF and SF picos, steppers and LVDTs.
- We lifted the BF/IRM/IM/RM/BS section to weigh it and check its balance.
- It was 195.6 kg, which is 18 kg(!) less than the capacity of the SF.
- There was a major imbalance in roll: with all four built-in trim masses moved up the +Y end, it still needed 270 g of extra trim mass to be level.
- Unfortunately when we put the payload, the IM was slightly yawed and ended up on the horizontal EQ stop screws. This let the IM-BF maraging rod go slack, which disturbed the leveling of the IM (because every time it is picked up the maraging rod settles in a different place, giving a different suspension point). We may have to partly disassemble the IRM and rearrange the time mass on the the IM.
- We shipped BS mirror box parts to Shoda-san and components for a new LVDT cable to Hirata-san.
- We posed for pictures of the BS by a team from National Geographic.
- Hirata-san
- Did parts and fastener lists for the SR payload.
- Did a 3D model with the SR suspension on the BS assembly frame (to help Mark make adjustments to the frame design).
- Did 2D drawings of Fabian's concept for BS EQ stop parts.
- Did a 3D model of a wire clamp with replaceable jaw parts (to avoid having to reuse parts with scars from pressure).
- Did 2D drawings of a new wire clamps for on top of the BS and SR RMs.