 * Type B Past Week Summary
  * Fabian, Mark, Yokogawa-kun and Kuwahara-kun did BS installation at Kamioka:
   * Hung RM.
   * Did permanent routing of RM OSEM cables to IM.
   * Did temporary routing of RM OSEM in-vacuum cables to flange (4 channels).
   * Did semi-permanent routing of all OSEM external cables to satellite amps (10 channels)
   * Did temporary routing of RM OSEMs to PR2 rack (4 channels).
   * Took data with geophones connected but immobilized and then stored geophones in boxes.
   * Tested signals from first satellite amp getting to digital system.
   * Weighed mirror box.
   * Did fit check of flag holders for stub flags. Very minor adjustments will be needed.
   * Covered everything in preparation for modifications to clean booth roof (9/20-21).
  * Hirata-san:
   * Finished 3D CAD of SR2 and SR3 in tanks, with optical layout included.
   * Started 3D CAD for SRM.
   * Checked flag design.
   * Assembled a bottom filter (ongoing).
   * Cleaned maraging rods.
 * Type B ongoing issues
 * Longer term to-do list
  * Do Inventor assembly for SRx in chamber and on assembly frame (Hirata) - SR2/SR3 DONE, SRM ongoing.
   * Part "disk security" top has to be modified - screw positions do not match.
  * Write more of payload assembly procedure (Fabian) - ONGOING
  * Write more of BS Assembly Procedure [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]], [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]] (Mark) - ONGOING
  * Lower breadboard installation to be incorporated into the procedure document.
  * Work on BS simulation (Fabian)
  * Do BS Simulink model (Mark, Kokeyama)
  * Do 2D drawings of SR2 parts (Hirata)
  * Redesign SRx IM wire clamps for larger prisms, remachined RMs
  * Order SRM/PRM parts (Hirata/Shoda)
  * Order SRx fasteners (Hirata)

 
 * Mark, Fabian and Enzo continued BS Test Hang work:
  * We installed the BF fishing rod stepper motor adaptor cable.
  * We tried to install the BF LVDT cable but first we encountered trouble routing it, and then several wires broke at the D-Sub end.
  * We laid 6 in-air cables from the tank to the PR2 rank for BF and SF picos, steppers and LVDTs.
  * We lifted the BF/IRM/IM/RM/BS section to weigh it and check its balance.
   * It was 195.6 kg, which is 18 kg(!) less than the capacity of the SF.
   * There was a major imbalance in roll: with all four built-in trim masses moved up the +Y end, it still needed 270 g of extra trim mass to be level.
  * Unfortunately when we put the payload, the IM was slightly yawed and ended up on the horizontal EQ stop screws. This let the IM-BF maraging rod go slack, which disturbed the leveling of the IM (because every time it is picked up the maraging rod settles in a different place, giving a different suspension point). We may have to partly disassemble the IRM and rearrange the time mass on the the IM.
  * We shipped BS mirror box parts to Shoda-san and components for a new LVDT cable to Hirata-san.
  * We posed for pictures of the BS by a team from National Geographic.
 * Hirata-san
  * Did parts and fastener lists for the SR payload.
  * Did a 3D model with the SR suspension on the BS assembly frame (to help Mark make adjustments to the frame design).
  * Did 2D drawings of Fabian's concept for BS EQ stop parts.
  * Did a 3D model of a wire clamp with replaceable jaw parts (to avoid having to reuse parts with scars from pressure).
  * Did 2D drawings of a new wire clamps for on top of the BS and SR RMs.

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

  • Mark, Fabian and Enzo continued BS Test Hang work:
    • We installed the BF fishing rod stepper motor adaptor cable.
    • We tried to install the BF LVDT cable but first we encountered trouble routing it, and then several wires broke at the D-Sub end.
    • We laid 6 in-air cables from the tank to the PR2 rank for BF and SF picos, steppers and LVDTs.
    • We lifted the BF/IRM/IM/RM/BS section to weigh it and check its balance.
      • It was 195.6 kg, which is 18 kg(!) less than the capacity of the SF.
      • There was a major imbalance in roll: with all four built-in trim masses moved up the +Y end, it still needed 270 g of extra trim mass to be level.
    • Unfortunately when we put the payload, the IM was slightly yawed and ended up on the horizontal EQ stop screws. This let the IM-BF maraging rod go slack, which disturbed the leveling of the IM (because every time it is picked up the maraging rod settles in a different place, giving a different suspension point). We may have to partly disassemble the IRM and rearrange the time mass on the the IM.
    • We shipped BS mirror box parts to Shoda-san and components for a new LVDT cable to Hirata-san.
    • We posed for pictures of the BS by a team from National Geographic.
  • Hirata-san
    • Did parts and fastener lists for the SR payload.
    • Did a 3D model with the SR suspension on the BS assembly frame (to help Mark make adjustments to the frame design).
    • Did 2D drawings of Fabian's concept for BS EQ stop parts.
    • Did a 3D model of a wire clamp with replaceable jaw parts (to avoid having to reuse parts with scars from pressure).
    • Did 2D drawings of a new wire clamps for on top of the BS and SR RMs.