 * Type B Past Week Summary, weeks of 9/19 and 9/26
  * Fabian, Mark and Kuwahara-kun did BS installation at Kamioka:
   * The BS clean booth was modified 9/20-21 to allow crane access. The area was fairly clean when Fabian inspected it on 9/26, but there were lots of metal flakes stuck to tape holding foil over the slit in the top of the clean bag.
   * Mark created a new Type B rtcds model and MEDM screens for the BS, adapting the TypeBb/PR3.
   * Mark and Kokeyama-san debugged the new model, fixing several issues.
   * Kuwahara-kun derived OSEM2EUL and EUL2OSEM matrices.
   * Mark set up OSEMINF filters using measured OSEM calibration data to return outputs in µm.
   * Mark took free-swing data on the TM stage to get the pendulum mode frequencies for comparison to the SUMCON model.
   * Mark and Fabian debugged the coil output to the OSEMs. (At first the coil drive was not giving output because it did not have BIO inputs and so was reading the test input, not the main input. And for a while output failed because of a loose cable to the sat amp.)
   * Mark took fixed-sine TFs to check the polarity of the coil-magnet combinations.
  * Hirata-san:
   * Finished 3D CAD of SRM in tanks (but some work was lost due to a hard disk crash).
   * Did 3D and 2D for new maraging rods, stub flags for PR/SR (ditto re hard disk).
   * Measured/tested Type A BF #8 and started assembling #9.
 * Longer term to-do list
  * Do Inventor assembly for SRx in chamber and on assembly frame (Hirata) - SR2/SR3 DONE, SRM ongoing.
   * Part "disk security" top has to be modified - screw positions do not match.
  * Write more of payload assembly procedure (Fabian) - ONGOING
  * Write more of BS Assembly Procedure [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]], [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]] (Mark) - ONGOING
  * Lower breadboard installation to be incorporated into the procedure document.
  * Work on BS simulation (Fabian)
  * Do BS Simulink model (Mark, Kokeyama) - TM/IM/BF level DONE
  * Do 2D drawings of SR2 parts (Hirata)
  * Redesign SRx IM wire clamps for larger prisms, remachined RMs
  * Order SRM/PRM parts (Hirata/Shoda)
  * Order SRx fasteners (Hirata)
=== Type B (Mark) ===
==== Report for week of 1/29 ====
 * Mark made two sets of in-air pico splitter cables (each with a triple for IM and a double for BF) for SR2 and SR3.
 * Fabian, Hirata-san and Kozu-kun worked on cabling and testing the IM pitch/roll/yaw picos, the BF FR and the BF LVDT. The LVDT connections were initially unreliable and Hirata-san had to redo the pins on the coil wires.
 * Fabian installed ballast masses in the BF.
 * Mark worked on schedule.
 * Mark did inventory of the stepper motor drivers (many were not accounted for on the wiki and/or JGWDoc and one is missing) and reserved two for SR3.
Line 32: Line 13:
  ==== Plan for week of 2/13 ====
 * No work Monday (建国記念の日の振替休日)
 * Enzo on vacation
 * Hirata-san at Mitaka Tue (self-evaluation interview).
 * Shoda-san at Mitaka.
 * All others at Kamioka.
 * -
 * Build IRM around IM.
 * Cable/test/adjust IM OSEMs.
 * Do TFs from IM OSEMs to IM OSEMs, OL pitch/yaw.

==== Plan for week of 2/19 ====
 * Enzo back from Tuesday.
 * Shoda-san at Mitaka.
 * Hirata-san at Mitaka Tue+Wed (to receive and wash parts; hope to change to Mon+Tue).
 * All others at Kamioka.
 * -
 * Lift BF/... section and check total mass and balance.
 * Cable and test BF picos.
 * Add section of SS up to SF ring.
 * Bring in SF.
 * Hook BF/... section.
 * Route cables up to under SF.
 * Check/adjust total mass of BF/... section.

==== Plan for week of 2/26 ====
 * Shoda-san at Mitaka.
 * -
 * Add Cu segments to SF cap.
 * Lift SF/... section and check total mass and balance.

==== Vacation Info ====
 * Enzo 1/30-2/19.
 * Fabian 4/2-4/27 vacation (then gone).

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Report for week of 1/29

  • Mark made two sets of in-air pico splitter cables (each with a triple for IM and a double for BF) for SR2 and SR3.
  • Fabian, Hirata-san and Kozu-kun worked on cabling and testing the IM pitch/roll/yaw picos, the BF FR and the BF LVDT. The LVDT connections were initially unreliable and Hirata-san had to redo the pins on the coil wires.
  • Fabian installed ballast masses in the BF.
  • Mark worked on schedule.
  • Mark did inventory of the stepper motor drivers (many were not accounted for on the wiki and/or JGWDoc and one is missing) and reserved two for SR3.

Plan for week of 2/13

  • No work Monday (建国記念の日の振替休日)
  • Enzo on vacation
  • Hirata-san at Mitaka Tue (self-evaluation interview).
  • Shoda-san at Mitaka.
  • All others at Kamioka.
  • -
  • Build IRM around IM.
  • Cable/test/adjust IM OSEMs.
  • Do TFs from IM OSEMs to IM OSEMs, OL pitch/yaw.

Plan for week of 2/19

  • Enzo back from Tuesday.
  • Shoda-san at Mitaka.
  • Hirata-san at Mitaka Tue+Wed (to receive and wash parts; hope to change to Mon+Tue).
  • All others at Kamioka.
  • -
  • Lift BF/... section and check total mass and balance.
  • Cable and test BF picos.
  • Add section of SS up to SF ring.
  • Bring in SF.
  • Hook BF/... section.
  • Route cables up to under SF.
  • Check/adjust total mass of BF/... section.

Plan for week of 2/26

  • Shoda-san at Mitaka.
  • -
  • Add Cu segments to SF cap.
  • Lift SF/... section and check total mass and balance.

Vacation Info

  • Enzo 1/30-2/19.
  • Fabian 4/2-4/27 vacation (then gone).