 * Type B Past Week Summary, weeks of 9/19 and 9/26
  * Fabian, Mark and Kuwahara-kun did BS installation at Kamioka:
   * The BS clean booth was modified 9/20-21 to allow crane access. The area was fairly clean when Fabian inspected it on 9/26, but there were lots of metal flakes stuck to tape holding foil over the slit in the top of the clean bag.
   * Mark created a new Type B rtcds model and MEDM screens for the BS, adapting the TypeBb/PR3.
   * Mark and Kokeyama-san debugged the new model, fixing several issues.
   * Kuwahara-kun derived OSEM2EUL and EUL2OSEM matrices.
   * Mark set up OSEMINF filters using measured OSEM calibration data to return outputs in µm.
   * Mark took free-swing data on the TM stage to get the pendulum mode frequencies for comparison to the SUMCON model.
   * Mark and Fabian debugged the coil output to the OSEMs. (At first the coil drive was not giving output because it did not have BIO inputs and so was reading the test input, not the main input. And for a while output failed because of a loose cable to the sat amp.)
   * Mark took fixed-sine TFs to check the polarity of the coil-magnet combinations.
   * Mark installed a BIO card in the PR2 rack and added cables from the TM voltage and current monitors to as-yet unused IM OSEM inputs to check the calibration.
   * Fabian wrapped the assembly frame in cling wrap to see if it helped with wind during TFs.
  * Hirata-san:
   * Finished 3D CAD of SRM in tanks (but some work was lost due to a hard disk crash).
   * Did 3D and 2D for new maraging rods, stub flags for PR/SR (ditto re hard disk).
   * Measured/tested Type A BF #8 and started assembling #9.
 * Longer term to-do list
  * Do Inventor assembly for SRx in chamber and on assembly frame (Hirata) - SR2/SR3 DONE, SRM ongoing.
   * Part "disk security" top has to be modified - screw positions do not match.
  * Write more of payload assembly procedure (Fabian) - ONGOING
  * Write more of BS Assembly Procedure [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]], [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]] (Mark) - ONGOING
  * Lower breadboard installation to be incorporated into the procedure document.
  * Work on BS simulation (Fabian)
  * Do BS Simulink model (Mark, Kokeyama) - TM/IM/BF level DONE
  * Do 2D drawings of SR2 parts (Hirata)
  * Redesign SRx IM wire clamps for larger prisms, remachined RMs
  * Order SRM/PRM parts (Hirata/Shoda)
  * Order SRx fasteners (Hirata)
=== Type B (Mark) ===
==== Report for week of 9/24 ====
 * Monday 9/24 was a holiday (Autumn Equinox).
===== SR2 =====
 * We moved all the SR2 feedthrough and in-vacuum and in-air cables.
 * We tested all the OSEMs and most of the LVDTs. We still need to run power to the pico drivers, and test them and the steppers.
 * We unlocked and mostly realigned the suspension. The IM is sitting lower than before but can be brought up to nominal height with BF GAS offset, without any signs of anything touching. The IM also has a moderately large pitch (2.8 mrad according to the OSEMs, about 1 mrad according to the OL) and some roll, which we expect to be able to correct with some pico adjustment. The horizontal IM OSEMs are well-centered (so there is no yaw misalignment).
Line 34: Line 13:
  ===== SRM =====
 * We made another attempt to set the pitch of the SRM, but weren't satisfied with how close we were able to get (target 20 mm low, achieved 23 mm), so we didn't tighten the clamps or continue to setting the pitch of the RM.

==== Plan for week of 10/1 ====
 * Mark, Hirata-san, Fabian, Panwei at Kamioka Mon-Fri.
===== SRM =====
 * Set pitch of SRM and RM, tighten clamps, remove winch system.
 * Weigh IM/... section.
 * Build up SS to BF level.
 * Add BF.
 * Suspend IM and tweak height/balance.
 * Cable/test BF.
 * Install IRM.
 * Install/cable/test IM OSEMs.

==== Plan for week of 10/8 ====
 * Monday 10/8 is Sports Day.
 * Enzo returns Tuesday 10/9.
 * Mark and Terrence (plus TBD) at Kamioka Mon-Fri.
 * Enzo, Hirata-san, Fabian and Panwei at Kamioka Tue-Fri.
===== SR2/SR3 =====
 * Terrence to set up LEN half of SR3 OL and, time permitting, TILT and LEN for SR2.
===== SRM =====
 * Continue installation.

==== To-Do Lists, Schedule ====
 * [[KAGRA/Subgroups/VIS/TypeB/ToDoBS]]
 * [[KAGRA/Subgroups/VIS/TypeB/ToDoSR]]
 * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7779|JGW-L1807779 Type B Schedule (SR)]]

==== Vacation/Visitor Info ====
 * Enzo: 9/15 through 10/8 vacation in Chile.
 * Terrence: 10/8-12, 10/29-11/2 at Kamioka.

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Report for week of 9/24

  • Monday 9/24 was a holiday (Autumn Equinox).

SR2
  • We moved all the SR2 feedthrough and in-vacuum and in-air cables.
  • We tested all the OSEMs and most of the LVDTs. We still need to run power to the pico drivers, and test them and the steppers.
  • We unlocked and mostly realigned the suspension. The IM is sitting lower than before but can be brought up to nominal height with BF GAS offset, without any signs of anything touching. The IM also has a moderately large pitch (2.8 mrad according to the OSEMs, about 1 mrad according to the OL) and some roll, which we expect to be able to correct with some pico adjustment. The horizontal IM OSEMs are well-centered (so there is no yaw misalignment).

SRM
  • We made another attempt to set the pitch of the SRM, but weren't satisfied with how close we were able to get (target 20 mm low, achieved 23 mm), so we didn't tighten the clamps or continue to setting the pitch of the RM.

Plan for week of 10/1

  • Mark, Hirata-san, Fabian, Panwei at Kamioka Mon-Fri.

SRM
  • Set pitch of SRM and RM, tighten clamps, remove winch system.
  • Weigh IM/... section.
  • Build up SS to BF level.
  • Add BF.
  • Suspend IM and tweak height/balance.
  • Cable/test BF.
  • Install IRM.
  • Install/cable/test IM OSEMs.

Plan for week of 10/8

  • Monday 10/8 is Sports Day.
  • Enzo returns Tuesday 10/9.
  • Mark and Terrence (plus TBD) at Kamioka Mon-Fri.
  • Enzo, Hirata-san, Fabian and Panwei at Kamioka Tue-Fri.

SR2/SR3
  • Terrence to set up LEN half of SR3 OL and, time permitting, TILT and LEN for SR2.

SRM
  • Continue installation.

To-Do Lists, Schedule

Vacation/Visitor Info

  • Enzo: 9/15 through 10/8 vacation in Chile.
  • Terrence: 10/8-12, 10/29-11/2 at Kamioka.