 * Hirata-san produced a near-final Inventor assembly of the BS on the assembly frame, for use in writing the assembly procedure.
  * Includes assembly frame modifications suggested by Mirapro, including feet, wheels, lifting eyes, thicker crossbars under BF, IM etc.
  * Includes final rail system except for interface plate to mirror box.
  * Includes full PI with ballast masses.
  * Includes cable clamps.
  * Includes correct versions of BF and SF.
  * Includes new BF pushrod parts to work around different placement of blade screws in new version of BF.
  * Includes cleanbag support bars.
  * Includes key parts of mirror box (enough to check for interference) - needs more work.
  * Does not include various invisible duplicate assemblies.
 * Got status from Miyakawa-san on electronics - there should be enough of the boxes AEL is supplying.
 * Cleanbag design was finalized; Aso-san is ordering: [[attachment:160419-チャンバーカバーⅡ型.pdf]]
 * Quote for flags and prisms was received, but expensive - may drop rigid flag design.
 * The mirror box will require only very minor modifications for flags and prisms - Tatsumi-san will arrange immediately.
 * Fabian worked on understanding Sekiguchi-san's control design to help decide optimum wire thickness.
 * Mark worked on install procedure and schedule.
 * Takahashi-san enquired with NIKHEF about oscillator cards for LVDT chassis - lead time would be 3-4 months.
 *
 * Type B Past Week Summary
  * There were multiple issues with the dummy BS flag/prism gluing [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=1830 |klog]]. The sapphire prisms will need to be removed and reapplied. Hirose-san is going to organize this. He is trying the cup that had been made for the PR2 on the dummy BS. Despite not having the ideal radius of curvature, it works to confine the acetone, and we will see shortly how much soaking is required to get a prism off.
  * Akutsu-san provided stainless steel mirror panels for the dummy BS made by ATC.
  * Hirata-san added the optical layout information to the BS Inventor assembly. He requested tank information from Mirapro so he can continue to do SR2/3/M.
  * Hirata-san worked on the crane height problem with Saito-sensei. They concluded that craning in the suspension is possible but will require not just the vacuum tank lid but the ≈30 cm section of tank below it to be removed.
  * Hirata-san liaised with Nakamura-san of Mirapro. Mirapro could start assembling the frame in the first week of July.
  * Hirata-san cleaned more parts and measured another filter.
  * Fabian finished the IM assembly and started on the IRM and RM. Some of the IRM panels had been improperly wrapped and will be re-cleaned. The MPC (multi-purpose cube) on the RM will need some rework.
  * Mark did a top level schedule. The BS can probably be finished roughly when promised to Ando-san earlier, but the SRs will probably take rather longer because of all the prep work that still needs to be done. It may save time overall to delay the start of the BS installation a few weeks and concentrate on parts for SR.
  * Mark released a draft (about half-finished) of [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| JGW-E1504235 - BS Installation Procedure]].
  * Mark updated [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=3600| JGW-D1503600 - BS Suspension Cabling]] with a better arrangement for the IM and BF pico motor cables, as well as various other minor fixes.
  * Mark organized a review for Thursday 6/16.
 * Type B ongoing issues
  * Wires
   * Need to decide RM wire thickness and order BS and RM wires. Lead time is a few days from Nilaco.
  * OSEMs
   * Akutsu-san is working to get wide-mouth OSEMs
  * Longer cables for BF->PI and SF->PI.
   * Takahashi-san has ordered extra connectors (due any day) and will get a company to make the cables.
  * Feedthrough Adapters
   * Need large quantity of male and female D-Sub 9, IDC ribbon connectors - Takahashi-san is getting a quote.
  * Can we make SR wire breakers bigger?
   * Fukushima-san will start on machining test soon (as of 5/27).
  * Not enough crane height problem (Hirata, Saito) - SOLVED
  * Installation stuff
   * Crane scale - quote received
  * Ballast masses for payload
   * Initial batch received - ordered extra smaller ones to allow for adjustments.
  * Lower breadboard stuff
   * Installation to be incorporated into the procedure document. Mark/Takahashi to discuss.
   * Breadboard springs (in manufacture, expected end of July)
   * Nail-head parts: quote from Mirapro received, not urgent, will be combined with assembly frame order.
  * Documents
   * BS Assembly Procedure [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]], [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]]

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

  • Type B Past Week Summary
    • There were multiple issues with the dummy BS flag/prism gluing klog. The sapphire prisms will need to be removed and reapplied. Hirose-san is going to organize this. He is trying the cup that had been made for the PR2 on the dummy BS. Despite not having the ideal radius of curvature, it works to confine the acetone, and we will see shortly how much soaking is required to get a prism off.

    • Akutsu-san provided stainless steel mirror panels for the dummy BS made by ATC.
    • Hirata-san added the optical layout information to the BS Inventor assembly. He requested tank information from Mirapro so he can continue to do SR2/3/M.
    • Hirata-san worked on the crane height problem with Saito-sensei. They concluded that craning in the suspension is possible but will require not just the vacuum tank lid but the ≈30 cm section of tank below it to be removed.
    • Hirata-san liaised with Nakamura-san of Mirapro. Mirapro could start assembling the frame in the first week of July.
    • Hirata-san cleaned more parts and measured another filter.
    • Fabian finished the IM assembly and started on the IRM and RM. Some of the IRM panels had been improperly wrapped and will be re-cleaned. The MPC (multi-purpose cube) on the RM will need some rework.
    • Mark did a top level schedule. The BS can probably be finished roughly when promised to Ando-san earlier, but the SRs will probably take rather longer because of all the prep work that still needs to be done. It may save time overall to delay the start of the BS installation a few weeks and concentrate on parts for SR.
    • Mark released a draft (about half-finished) of JGW-E1504235 - BS Installation Procedure.

    • Mark updated JGW-D1503600 - BS Suspension Cabling with a better arrangement for the IM and BF pico motor cables, as well as various other minor fixes.

    • Mark organized a review for Thursday 6/16.
  • Type B ongoing issues
    • Wires
      • Need to decide RM wire thickness and order BS and RM wires. Lead time is a few days from Nilaco.
    • OSEMs
      • Akutsu-san is working to get wide-mouth OSEMs
    • Longer cables for BF->PI and SF->PI.

      • Takahashi-san has ordered extra connectors (due any day) and will get a company to make the cables.
    • Feedthrough Adapters
      • Need large quantity of male and female D-Sub 9, IDC ribbon connectors - Takahashi-san is getting a quote.
    • Can we make SR wire breakers bigger?
      • Fukushima-san will start on machining test soon (as of 5/27).
    • Not enough crane height problem (Hirata, Saito) - SOLVED
    • Installation stuff
      • Crane scale - quote received
    • Ballast masses for payload
      • Initial batch received - ordered extra smaller ones to allow for adjustments.
    • Lower breadboard stuff
      • Installation to be incorporated into the procedure document. Mark/Takahashi to discuss.
      • Breadboard springs (in manufacture, expected end of July)
      • Nail-head parts: quote from Mirapro received, not urgent, will be combined with assembly frame order.
    • Documents