* Type B Past Week Summary, weeks of 9/19 and 9/26 * Fabian, Mark and Liu-kun did BS installation at Kamioka: * Connected the DIO card to the LPCD. (Simulink model changes will be needed to make use of it.) * Took TF data from the TM-H1 coil output to the voltage and current monitors and found that the response was approximately flat. * Used the 90° prism and the optical lever to set the pitch of the RM to match the dummy BS. * Removed the RM trolley and added the bottom section of the security structure. * Lifted the IM/RM/BS with the load gauge adapter and load gauge and measured its mass. * Hirata-san: * Modified drawing of maraging rods for BS [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5706| D1605706]] * Made 3D models of stub flag gluing jigs. * Made 3D models and 2D drawing of BS BF-IM hexagon cable clamp assembly and cone parts. [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5734| D1605734]] * Washed parts and screws. * (For Type A) Assembled and adjusted blades of BF #9. * Longer term to-do list * Do Inventor assembly for SRx in chamber and on assembly frame (Hirata) - SR2/SR3 DONE, SRM ongoing. * Part "disk security" top has to be modified - screw positions do not match. * Write more of payload assembly procedure (Fabian) - ONGOING * Write more of BS Assembly Procedure [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]], [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]] (Mark) - ONGOING * Lower breadboard installation to be incorporated into the procedure document. * Work on BS simulation (Fabian) * Do BS Simulink model (Mark, Kokeyama) - TM/IM/BF level DONE * Do 2D drawings of SR2 parts (Hirata) * Redesign SRx IM wire clamps for larger prisms, remachined RMs * Order SRM/PRM parts (Hirata/Shoda) * Order SRx fasteners (Hirata) |
=== Type B (Mark) === ==== Past week report ==== At Kamioka (Mark, Fabian, Enzo, Hirata-san): * We disconnected the in-vacuum and in-air cabling from the feedthroughs. * We removed crossbars below BF and SF. * We set the SF damper to 4 mm clearance. * We adjusted the jacks to nominal height. * We removed the geophones and PI yaw stepper for craning. * We craned the suspension into the tank, and hooked the LBB Cu ring. * We replaced the geophones etc. * We unlocked all but the IP and adjusted the jacks until the pendulum was centered in the security structure. * We unlocked the IP and adjusted to to center with the jacks and fishing rods. * We craned the vacuum tank lid+ring back on, and then removed just the lid (only). * We unclamped the LBB damper rings and removed the spacers. * We removed the blocks and shims supporting the LBB, inserted the long screw feet and hooked the LBB to the Cu damper ring. * We added 2*31.5 kg of ballast to the LBB, which got the blades to the point where firm pressure would depress the tips. * We reconnected the in-vacuum cabling. In ≈15 places we opted to omit the Type 1 cable and use a F-F gender bender. * We reconnected all but four of the in-air cables. |
Line 31: | Line 24: |
==== Plan for week of 6/26 ==== Mark and Enzo at Kamioka: * Double-check where gender-benders were used. * Finish connecting in-air cabling. * Debug all cabling. * Work with Simon to set up LSOL. Fabian at Mitaka: * Design final ballast masses for IM, BF and SF assuming no BF rebuild (needs to be adaptable). * Check all items for BS flag/prism gluing are available (prisms, flags, jigs, mirror box, glue, scale, mixing tools etc). Hirata-san at Mitaka: * Do new 3D CAD: * BS Test Hang build, with top of tank, full suspension, and LBB damper all reversed. * Final BS build, as above, but with everything BF down rotated back to original. * In-tank version. * On-assembly-frame version. (Adjust jack positions if possible, or leave for Mark to do.) * SR2 on BS assembly frame. (Adjust jack positions if possible, or leave for Mark to do.) |
Scraps of text for incorporation in the VIS Meeting Minutes
KAGRA/Subgroups/VIS/MeetingNAOJ
Type B (Mark)
Past week report
At Kamioka (Mark, Fabian, Enzo, Hirata-san):
- We disconnected the in-vacuum and in-air cabling from the feedthroughs.
- We removed crossbars below BF and SF.
- We set the SF damper to 4 mm clearance.
- We adjusted the jacks to nominal height.
- We removed the geophones and PI yaw stepper for craning.
- We craned the suspension into the tank, and hooked the LBB Cu ring.
- We replaced the geophones etc.
- We unlocked all but the IP and adjusted the jacks until the pendulum was centered in the security structure.
- We unlocked the IP and adjusted to to center with the jacks and fishing rods.
- We craned the vacuum tank lid+ring back on, and then removed just the lid (only).
- We unclamped the LBB damper rings and removed the spacers.
- We removed the blocks and shims supporting the LBB, inserted the long screw feet and hooked the LBB to the Cu damper ring.
- We added 2*31.5 kg of ballast to the LBB, which got the blades to the point where firm pressure would depress the tips.
- We reconnected the in-vacuum cabling. In ≈15 places we opted to omit the Type 1 cable and use a F-F gender bender.
- We reconnected all but four of the in-air cables.
Plan for week of 6/26
Mark and Enzo at Kamioka:
- Double-check where gender-benders were used.
- Finish connecting in-air cabling.
- Debug all cabling.
- Work with Simon to set up LSOL.
Fabian at Mitaka:
- Design final ballast masses for IM, BF and SF assuming no BF rebuild (needs to be adaptable).
- Check all items for BS flag/prism gluing are available (prisms, flags, jigs, mirror box, glue, scale, mixing tools etc).
Hirata-san at Mitaka:
- Do new 3D CAD:
- BS Test Hang build, with top of tank, full suspension, and LBB damper all reversed.
- Final BS build, as above, but with everything BF down rotated back to original.
- In-tank version.
- On-assembly-frame version. (Adjust jack positions if possible, or leave for Mark to do.)
- SR2 on BS assembly frame. (Adjust jack positions if possible, or leave for Mark to do.)