 * Type B Past Week Summary, weeks of 9/19 and 9/26
  * Fabian, Mark and Liu-kun did BS installation at Kamioka:
   * Connected the DIO card to the LPCD. (Simulink model changes will be needed to make use of it.)
   * Took TF data from the TM-H1 coil output to the voltage and current monitors and found that the response was approximately flat.
   * Used the 90° prism and the optical lever to set the pitch of the RM to match the dummy BS.
   * Removed the RM trolley and added the bottom section of the security structure.
   * Lifted the IM/RM/BS with the load gauge adapter and load gauge and measured its mass.
  * Hirata-san:
   * Modified drawing of maraging rods for BS [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5706| D1605706]]
   * Made 3D models of stub flag gluing jigs.
   * Made 3D models and 2D drawing of BS BF-IM hexagon cable clamp assembly and cone parts. [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5734| D1605734]]
   * Washed parts and screws.
   * (For Type A) Assembled and adjusted blades of BF #9.
 * Longer term to-do list
  * Do Inventor assembly for SRx in chamber and on assembly frame (Hirata) - SR2/SR3 DONE, SRM ongoing.
   * Part "disk security" top has to be modified - screw positions do not match.
  * Write more of payload assembly procedure (Fabian) - ONGOING
  * Write more of BS Assembly Procedure [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]], [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]] (Mark) - ONGOING
  * Lower breadboard installation to be incorporated into the procedure document.
  * Work on BS simulation (Fabian)
  * Do BS Simulink model (Mark, Kokeyama) - TM/IM/BF level DONE
  * Do 2D drawings of SR2 parts (Hirata)
  * Redesign SRx IM wire clamps for larger prisms, remachined RMs
  * Order SRM/PRM parts (Hirata/Shoda)
  * Order SRx fasteners (Hirata)
=== Type B (Mark) ===
==== Past week report ====
At Kamioka (Mark, Enzo, Hirata-san, Yoshioka-kun):
 * We lubricated the stuck screw at the top of the security structure with stuck and were able to remove it.
 * Enzo disconnected and removed or coiled many in-vac cables at the PI level to free it.
 * We craned the PI. There was a minor safety incident - see below.
 * Hirata-san set up the filter service area, and we moved in a BF intended for one of the SRs (BF#3).
 * Fabian and Hirata-san worked out a method for characterizing a single spring, and Fabian finished characterizing the first one.
 * We did a big tidy-up and clean-up of the area, especially the corner where we intended to do the gluing.
 * We set up the BS gluing jigs and applied the glue. We will check the results on Monday.
Line 31: Line 16:
  ==== Plan for week of 7/24 ====
Full team at Kamioka from Mon-Fri, except Hirata-san (Tue-Fri) and Enzo (vacation).
 * Check results of gluing.
 * Finish BF rebuild.
 * Recheck alignment of assembly frame and centering of optical table.
 * Install IM, suspend BS and RM.

==== Plan for week of 7/31 ====
Full team at Kamioka from Mon-Fri, except Fabian (Mon-Thu) and Enzo (vacation).
 * Weigh/trim BS/RM/IM.
 * Bring in rebuilt BF.

Vacation Info:
Hirata-san: Thu 7/20 through Mon 7/24
Enzo: Sat 7/22 through Sun 8/6
Fabian: Fri 8/4 through Mon 8/21
Mark: TBD Mid-Oct

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Past week report

At Kamioka (Mark, Enzo, Hirata-san, Yoshioka-kun):

  • We lubricated the stuck screw at the top of the security structure with stuck and were able to remove it.
  • Enzo disconnected and removed or coiled many in-vac cables at the PI level to free it.
  • We craned the PI. There was a minor safety incident - see below.
  • Hirata-san set up the filter service area, and we moved in a BF intended for one of the SRs (BF#3).
  • Fabian and Hirata-san worked out a method for characterizing a single spring, and Fabian finished characterizing the first one.
  • We did a big tidy-up and clean-up of the area, especially the corner where we intended to do the gluing.
  • We set up the BS gluing jigs and applied the glue. We will check the results on Monday.

Plan for week of 7/24

Full team at Kamioka from Mon-Fri, except Hirata-san (Tue-Fri) and Enzo (vacation).

  • Check results of gluing.
  • Finish BF rebuild.
  • Recheck alignment of assembly frame and centering of optical table.
  • Install IM, suspend BS and RM.

Plan for week of 7/31

Full team at Kamioka from Mon-Fri, except Fabian (Mon-Thu) and Enzo (vacation).

  • Weigh/trim BS/RM/IM.
  • Bring in rebuilt BF.

Vacation Info: Hirata-san: Thu 7/20 through Mon 7/24 Enzo: Sat 7/22 through Sun 8/6 Fabian: Fri 8/4 through Mon 8/21 Mark: TBD Mid-Oct