 * Type B Past Week Summary, weeks of 9/19 and 9/26
  * Fabian, Mark and Liu-kun did BS installation at Kamioka:
   * Connected the DIO card to the LPCD. (Simulink model changes will be needed to make use of it.)
   * Took TF data from the TM-H1 coil output to the voltage and current monitors and found that the response was approximately flat, meaning that meaningful TFs can be taken of the RM/BS stage with no DIO.
   * Used the 90° prism and the optical lever to set the pitch of the RM to match the dummy BS.
   * Removed the RM trolley and added the bottom section of the security structure.
   * Lifted the IM/RM/BS with the load gauge adapter and load gauge and measured its mass.
  * Hirata-san:
   * Modified drawing of maraging rods for BS [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5706| D1605706]]
   * Made 3D models of stub flag gluing jigs.
   * Made 3D models and 2D drawing of BS BF-IM hexagon cable clamp assembly and cone parts. [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5734| D1605734]]
   * Washed parts and screws.
   * (For Type A) Assembled and adjusted blades of BF #9.
 * Longer term to-do list
  * Do Inventor assembly for SRx in chamber and on assembly frame (Hirata) - SR2/SR3 DONE, SRM ongoing.
   * Part "disk security" top has to be modified - screw positions do not match.
  * Write more of payload assembly procedure (Fabian) - ONGOING
  * Write more of BS Assembly Procedure [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]], [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]] (Mark) - ONGOING
  * Lower breadboard installation to be incorporated into the procedure document.
  * Work on BS simulation (Fabian)
  * Do BS Simulink model (Mark, Kokeyama) - TM/IM/BF level DONE
  * Do 2D drawings of SR2 parts (Hirata)
  * Redesign SRx IM wire clamps for larger prisms, remachined RMs
  * Order SRM/PRM parts (Hirata/Shoda)
  * Order SRx fasteners (Hirata)

 
 * Hirata-san:
  * Did drawings of SR damper.
 * Mark, Fabian, Enzo and Hirata-san (at Kamioka):
  * Took the end plate off the IM to get access to the pitch/roll picos.
  * Found the pitch pico was unreliable and replaced it.
  * Found the springs were not stiff enough, and immobilized 7 turns at the end of each with Cu wire to make them stiffer.
  * Reassembled and rebalanced the IM.
  * Reassembled and adjusted the IRM.
  * Discovered that the transverse offset between IRM and IM could be corrected by adjusting the roll of the BF.
  * Adjusted IM OSEMs to half-way.
  * Made and installed a new pair of wires for the BF yaw pico on the IM pico adapter (Hirata-san).
  * Installed an improved LVDT cable made by Hirata-san.
  * Made and hung posters for the Elites meeting visitors.

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

  • Hirata-san:
    • Did drawings of SR damper.
  • Mark, Fabian, Enzo and Hirata-san (at Kamioka):
    • Took the end plate off the IM to get access to the pitch/roll picos.
    • Found the pitch pico was unreliable and replaced it.
    • Found the springs were not stiff enough, and immobilized 7 turns at the end of each with Cu wire to make them stiffer.
    • Reassembled and rebalanced the IM.
    • Reassembled and adjusted the IRM.
    • Discovered that the transverse offset between IRM and IM could be corrected by adjusting the roll of the BF.
    • Adjusted IM OSEMs to half-way.
    • Made and installed a new pair of wires for the BF yaw pico on the IM pico adapter (Hirata-san).
    • Installed an improved LVDT cable made by Hirata-san.
    • Made and hung posters for the Elites meeting visitors.