Line 5: Line 5:
 * Type B Past Week Summary, weeks of 9/19 and 9/26
  * Fabian, Mark and Liu-kun did BS installation at Kamioka:
   * Connected the DIO card to the LPCD. (Simulink model changes will be needed to make use of it.)
   * Took TF data from the TM-H1 coil output to the voltage and current monitors and found that the response was approximately flat, meaning that meaningful TFs can be taken of the RM/BS stage with no DIO.
   * Used the 90° prism and the optical lever to set the pitch of the RM to match the dummy BS.
   * Removed the RM trolley and added the bottom section of the security structure.
   * Lifted the IM/RM/BS with the load gauge adapter and load gauge and measured its mass.
  * Hirata-san:
   * Modified drawing of maraging rods for BS [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5706| D1605706]]
   * Made 3D models of stub flag gluing jigs.
   * Made 3D models and 2D drawing of BS BF-IM hexagon cable clamp assembly and cone parts. [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5734| D1605734]]
   * Washed parts and screws.
   * (For Type A) Assembled and adjusted blades of BF #9.
 * Longer term to-do list
  * Do Inventor assembly for SRx in chamber and on assembly frame (Hirata) - SR2/SR3 DONE, SRM ongoing.
   * Part "disk security" top has to be modified - screw positions do not match.
  * Write more of payload assembly procedure (Fabian) - ONGOING
  * Write more of BS Assembly Procedure [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]], [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]] (Mark) - ONGOING
  * Lower breadboard installation to be incorporated into the procedure document.
  * Work on BS simulation (Fabian)
  * Do BS Simulink model (Mark, Kokeyama) - TM/IM/BF level DONE
  * Do 2D drawings of SR2 parts (Hirata)
  * Redesign SRx IM wire clamps for larger prisms, remachined RMs
  * Order SRM/PRM parts (Hirata/Shoda)
  * Order SRx fasteners (Hirata)
=== Type B (Mark) ===
==== Past week report ====
At Kamioka (Mark, Ohishi-san, Fabian, Enzo, Hirata-san, Yoshioka-kun, Kozu-kun):
 * We solved the problem with the OSEMs: cables had been plugged into the LED current monitor outputs, not the PD outputs.
 * We solved a problem with the real-time model freezing which turned out to be the IO chassis having lost power.
 * We took some mass off the IM to allow for the weight of the cables, and readjusted it in pitch and roll.
 * We aligned the IM
Line 31: Line 13:
  ==== Plan for week of 8/28 ====
Kamioka: Mark (except Tue), Ohishi-san, Fabian (except Tue), Enzo (except Tue), Hirata-san, Yoshioka-kun (Fri), Kozu-kun (Thu, Fri).
 * Fix/adjust IRM OSEMs.
 * Add BF cap; cable and test BF-1 and BF-2 picos.
 * Lift and weigh BF/IRM/IM/RM/BS; adjust ballast mass.
 * Crane in SF.
 * Suspend BF/IRM/IM/RM/BS.

==== Plan for week of 9/4 ====
 * Install SF cap; route cables.
 * Lift and weigh SF/BF/IRM/IM/RM/BS.
 * Adjust SF ballast.

==== Vacation Info ====
Mark: TBD Mid-Oct

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Past week report

At Kamioka (Mark, Ohishi-san, Fabian, Enzo, Hirata-san, Yoshioka-kun, Kozu-kun):

  • We solved the problem with the OSEMs: cables had been plugged into the LED current monitor outputs, not the PD outputs.
  • We solved a problem with the real-time model freezing which turned out to be the IO chassis having lost power.
  • We took some mass off the IM to allow for the weight of the cables, and readjusted it in pitch and roll.
  • We aligned the IM

Plan for week of 8/28

Kamioka: Mark (except Tue), Ohishi-san, Fabian (except Tue), Enzo (except Tue), Hirata-san, Yoshioka-kun (Fri), Kozu-kun (Thu, Fri).

  • Fix/adjust IRM OSEMs.
  • Add BF cap; cable and test BF-1 and BF-2 picos.
  • Lift and weigh BF/IRM/IM/RM/BS; adjust ballast mass.
  • Crane in SF.
  • Suspend BF/IRM/IM/RM/BS.

Plan for week of 9/4

  • Install SF cap; route cables.
  • Lift and weigh SF/BF/IRM/IM/RM/BS.
  • Adjust SF ballast.