 * Type B Past Week Summary, weeks of 9/19 and 9/26
  * Fabian, Mark and Liu-kun did BS installation at Kamioka:
   * Connected the DIO card to the LPCD. (Simulink model changes will be needed to make use of it.)
   * Took TF data from the TM-H1 coil output to the voltage and current monitors and found that the response was approximately flat, meaning that meaningful TFs can be taken of the RM/BS stage with no DIO.
   * Used the 90° prism and the optical lever to set the pitch of the RM to match the dummy BS.
   * Removed the RM trolley and added the bottom section of the security structure.
   * Lifted the IM/RM/BS with the load gauge adapter and load gauge and measured its mass.
  * Hirata-san:
   * Modified drawing of maraging rods for BS [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5706| D1605706]]
   * Made 3D models of stub flag gluing jigs.
   * Made 3D models and 2D drawing of BS BF-IM hexagon cable clamp assembly and cone parts. [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5734| D1605734]]
   * Washed parts and screws.
   * (For Type A) Assembled and adjusted blades of BF #9.
 * Longer term to-do list
  * Do Inventor assembly for SRx in chamber and on assembly frame (Hirata) - SR2/SR3 DONE, SRM ongoing.
   * Part "disk security" top has to be modified - screw positions do not match.
  * Write more of payload assembly procedure (Fabian) - ONGOING
  * Write more of BS Assembly Procedure [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]], [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]] (Mark) - ONGOING
  * Lower breadboard installation to be incorporated into the procedure document.
  * Work on BS simulation (Fabian)
  * Do BS Simulink model (Mark, Kokeyama) - TM/IM/BF level DONE
  * Do 2D drawings of SR2 parts (Hirata)
  * Redesign SRx IM wire clamps for larger prisms, remachined RMs
  * Order SRM/PRM parts (Hirata/Shoda)
  * Order SRx fasteners (Hirata)
=== Type B (Mark) ===
==== Report for week of 12/25 ====
 * Hirata-san got the L-brackets machined and washed, and installed them on the IM ring bars.
 * Shoda-san recovered the BS from the power outage on 12/25.
 * Miyakawa-san fixed an issue with the SR2 RTM which had prevented it from running.
 * Shoda-san, Hirata-san and Kozu-kun weighed the IM without ballast masses, and then added the lower masses and installed the IM on the assembly frame.
 * They cleaned the assembly frame and installed new jack receptacles on the load gauge adapter.
 * They installed the winch system on the IM, and inspected the clamp pieces for possible scratches.
 * They ran cables for the SR2 steppers and OSEMs.
 * They calibrated the BF LVDT.
Line 31: Line 16:
  ==== Report for week of 1/4 ====
 * Mark fixed a number of errors with the Type B screens.

==== Report for week of 1/9 ====
 * We weighed the mirror in its box (and later the empty box), and the RM.
 * Fabian worked on the SR2/SR3/SRM mass budget and did an inventory of spare ballast masses.
 * We hung the SR2 and RM.
 * We assembled the bottom section of the security structure below the RM.
 * Hirata-san gave up on waiting for a third quote for the blades and blade parts and started the ordering process.
 * Hirata-san got rod cable clamp parts from Takahashi-san and worked on drawings for the improved BS vertical and yaw adjusters.

==== Plan for week of 1/15 ====
 * Shoda-san at Mitaka making OSEMs.
 *
==== Plan for week of 1/22 ====

==== Plan for week of 1/22 ====
 * Mark, Fabian, Enzo, Shoda-san at Kamioka Tue-Fri.
 * Hang SR and RM.

==== Vacation Info ====
 * Enzo 1/30-2/19 (at Mitaka 1/29, part of 1/30)
 * Kozu-kun 1/29-2/2

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Report for week of 12/25

  • Hirata-san got the L-brackets machined and washed, and installed them on the IM ring bars.
  • Shoda-san recovered the BS from the power outage on 12/25.
  • Miyakawa-san fixed an issue with the SR2 RTM which had prevented it from running.
  • Shoda-san, Hirata-san and Kozu-kun weighed the IM without ballast masses, and then added the lower masses and installed the IM on the assembly frame.
  • They cleaned the assembly frame and installed new jack receptacles on the load gauge adapter.
  • They installed the winch system on the IM, and inspected the clamp pieces for possible scratches.
  • They ran cables for the SR2 steppers and OSEMs.
  • They calibrated the BF LVDT.

Report for week of 1/4

  • Mark fixed a number of errors with the Type B screens.

Report for week of 1/9

  • We weighed the mirror in its box (and later the empty box), and the RM.
  • Fabian worked on the SR2/SR3/SRM mass budget and did an inventory of spare ballast masses.
  • We hung the SR2 and RM.
  • We assembled the bottom section of the security structure below the RM.
  • Hirata-san gave up on waiting for a third quote for the blades and blade parts and started the ordering process.
  • Hirata-san got rod cable clamp parts from Takahashi-san and worked on drawings for the improved BS vertical and yaw adjusters.

Plan for week of 1/15

  • Shoda-san at Mitaka making OSEMs.

Plan for week of 1/22

Plan for week of 1/22

  • Mark, Fabian, Enzo, Shoda-san at Kamioka Tue-Fri.
  • Hang SR and RM.

Vacation Info

  • Enzo 1/30-2/19 (at Mitaka 1/29, part of 1/30)
  • Kozu-kun 1/29-2/2