 * Type B Past Week Summary, weeks of 9/19 and 9/26
  * Fabian, Mark and Liu-kun did BS installation at Kamioka:
   * Connected the DIO card to the LPCD. (Simulink model changes will be needed to make use of it.)
   * Took TF data from the TM-H1 coil output to the voltage and current monitors and found that the response was approximately flat, meaning that meaningful TFs can be taken of the RM/BS stage with no DIO.
   * Used the 90° prism and the optical lever to set the pitch of the RM to match the dummy BS.
   * Removed the RM trolley and added the bottom section of the security structure.
   * Lifted the IM/RM/BS with the load gauge adapter and load gauge and measured its mass.
  * Hirata-san:
   * Modified drawing of maraging rods for BS [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5706| D1605706]]
   * Made 3D models of stub flag gluing jigs.
   * Made 3D models and 2D drawing of BS BF-IM hexagon cable clamp assembly and cone parts. [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5734| D1605734]]
   * Washed parts and screws.
   * (For Type A) Assembled and adjusted blades of BF #9.
 * Longer term to-do list
  * Do Inventor assembly for SRx in chamber and on assembly frame (Hirata) - SR2/SR3 DONE, SRM ongoing.
   * Part "disk security" top has to be modified - screw positions do not match.
  * Write more of payload assembly procedure (Fabian) - ONGOING
  * Write more of BS Assembly Procedure [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]], [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]] (Mark) - ONGOING
  * Lower breadboard installation to be incorporated into the procedure document.
  * Work on BS simulation (Fabian)
  * Do BS Simulink model (Mark, Kokeyama) - TM/IM/BF level DONE
  * Do 2D drawings of SR2 parts (Hirata)
  * Redesign SRx IM wire clamps for larger prisms, remachined RMs
  * Order SRM/PRM parts (Hirata/Shoda)
  * Order SRx fasteners (Hirata)

 
 * Type B Past Week Summary
  * Mark (with Enzo) did initial TFs on the BF.
   * Did fixed-sine TFs on individual OSEMs at low frequency to check actuator polarity (klog [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=2176 | 2176]] and [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=2182|2182]]).
   * Set gains in the COILOUTF block to compensate for actuator polarity.
  * Mark (with Enzo) did a free-swing measurement on the BS after earthquake of 11/22 (klog [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=2182|2182]]).
   * Results suspicious (noted by Shoda-san): too much difference between OSEMs - horizontal showing much less motion than vertical.
   * Possible rubbing in horizontal.
   * May need a trip to Kamioka.
  * Mark (with Enzo) made corrections and improvements to many of the MEDM screens (klog [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=2176 | 2176]] and [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=2182|2182]]).
   * Main overview screen was not generic in many places, and links to GDS_TP screens were broken.
   * ADC monitor screen referenced bad channels with LIGO-style names.
   * DAC monitor screen was not generic and did not support IM OSEMs.
   * Watchdog IM OSEM AC band limit filter screen was a copy of the TM one.
   * Watchdog TM OSEM AC band limit filter screen appears to be getting OL signals as input - needs model changes to fix.
   * The zoomed screens for IM OSEM centering were called incorrectly and did not work.
   * Various screens had LIGO-style channel names as labels.
  * Mark did a draft of D1603600-v12, including:
   * New assignment of IM OSEMs to DAQ channels (#4-9 are now V1, V2, V3, H1, H2, H3 rather than H1, H2, ...) from last Friday (the wiring was changed to reflect the model so as to remain consistent with PRx).
   * Information on how to identify the wires from the steppers and LVDTs so that the adapter cables can be plugged in properly.
  * Mark worked on schedule.
  * Hirata-san did drawings for new 8-mm maraging wires for Type A.
  * Hirata-san worked on PR/SR mirror box modifications with Shoda-san.
  

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

  • Type B Past Week Summary
    • Mark (with Enzo) did initial TFs on the BF.
      • Did fixed-sine TFs on individual OSEMs at low frequency to check actuator polarity (klog 2176 and 2182).

      • Set gains in the COILOUTF block to compensate for actuator polarity.
    • Mark (with Enzo) did a free-swing measurement on the BS after earthquake of 11/22 (klog 2182).

      • Results suspicious (noted by Shoda-san): too much difference between OSEMs - horizontal showing much less motion than vertical.
      • Possible rubbing in horizontal.
      • May need a trip to Kamioka.
    • Mark (with Enzo) made corrections and improvements to many of the MEDM screens (klog 2176 and 2182).

      • Main overview screen was not generic in many places, and links to GDS_TP screens were broken.
      • ADC monitor screen referenced bad channels with LIGO-style names.
      • DAC monitor screen was not generic and did not support IM OSEMs.
      • Watchdog IM OSEM AC band limit filter screen was a copy of the TM one.
      • Watchdog TM OSEM AC band limit filter screen appears to be getting OL signals as input - needs model changes to fix.
      • The zoomed screens for IM OSEM centering were called incorrectly and did not work.
      • Various screens had LIGO-style channel names as labels.
    • Mark did a draft of D1603600-v12, including:
      • New assignment of IM OSEMs to DAQ channels (#4-9 are now V1, V2, V3, H1, H2, H3 rather than H1, H2, ...) from last Friday (the wiring was changed to reflect the model so as to remain consistent with PRx).
      • Information on how to identify the wires from the steppers and LVDTs so that the adapter cables can be plugged in properly.
    • Mark worked on schedule.
    • Hirata-san did drawings for new 8-mm maraging wires for Type A.
    • Hirata-san worked on PR/SR mirror box modifications with Shoda-san.