Size: 2360
Comment:
|
Size: 1817
Comment:
|
Deletions are marked like this. | Additions are marked like this. |
Line 5: | Line 5: |
* Type B Past Week Summary * Fabian, Mark and Liu-kun did BS installation at Kamioka: * Connected the DIO card to the LPCD. (Simulink model changes will be needed to make use of it.) * Took TF data from the TM-H1 coil output to the voltage and current monitors and found that the response was approximately flat, meaning that meaningful TFs can be taken of the RM/BS stage with no DIO. * Used the 90° prism and the optical lever to set the pitch of the RM to match the dummy BS. * Removed the RM trolley and added the bottom section of the security structure. * Lifted the IM/RM/BS with the load gauge adapter and load gauge and measured its mass. * Hirata-san: * Modified drawing of maraging rods for BS [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5706| D1605706]] * Made 3D models of stub flag gluing jigs. * Made 3D models and 2D drawing of BS BF-IM hexagon cable clamp assembly and cone parts. [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5734| D1605734]] * Washed parts and screws. * (For Type A) Assembled and adjusted blades of BF #9. * Mark checked lots of drawings by Hirata-san. * Mark worked on schedule but only succeeded in completely garbling the Type B section of the VIS schedule on the server. * Longer term to-do list * Do Inventor assembly for SRx in chamber and on assembly frame (Hirata) - SR2/SR3 DONE, SRM ongoing. * Part "disk security" top has to be modified - screw positions do not match. * Write more of payload assembly procedure (Fabian) - ONGOING * Write more of BS Assembly Procedure [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]], [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]] (Mark) - ONGOING * Lower breadboard installation to be incorporated into the procedure document. * Work on BS simulation (Fabian) * Do BS Simulink model (Mark, Kokeyama) - TM/IM/BF level DONE * Do 2D drawings of SR2 parts (Hirata) * Redesign SRx IM wire clamps for larger prisms, remachined RMs * Order SRM/PRM parts (Hirata/Shoda) * Order SRx fasteners (Hirata) |
=== Type B (Mark) === ==== Report for week of 1/15 ==== * We set up the QPD for the OL, initialized the OL and TM sections of the RTM, and did TFs from the TM OSEMs to the OL. * Initially we had no coherence, but we debugged issues with the watchdog, LPCD, and DAC board and then got good TFs. * We lifted the IM/RM/SR with the load gauge adapter and checked the weight, which was close to the mass budget. * We installed the section of the AF above the IM, and the BF cross bars and jacks, and craned in the BF. * We installed the BF-IRM rods, IRM, BF-IM rod, flying saucer and the cable clamps on the bottom of the BF. * We hooked the IM section, but found it was heavy by several hundred grams. We also noticed the BF keystone had a noticeable tilt of about 1.2 mm (high on the +X side). * We removed 738 g of trim mass and found that load rose and sat about 2 mm high. So the discrepancy is of order 500-600 g. * Shoda-san, Enzo and Kozu-kun made and characterized a batch of OSEMs. * Hirata-san finished drawings for the improved BS PI yaw/vertical adjustment, placed orders for damping ring receptacles and other items, and prepared the second SR BF in case we needed to swap it in. ==== Plan for week of 1/22 ==== * Fix or swap BF. * Route selected cables to flange. * Test IM picos and BF yaw pico. |
Line 33: | Line 22: |
==== Plan for week of 1/29 ==== * Enzo at Mitaka 1/29 and most of 1/30, then vacation. * Kozu-kun away. * All others at Kamioka. * Build IRM around IM. * Cable/test/adjust IM OSEMs. * Time permitting, do TFs from IM OSEMs to themselves and to optical sensor. ==== Vacation Info ==== * Enzo 1/30-2/19 (at Mitaka 1/29, part of 1/30) * Kozu-kun 1/29-2/2 |
Scraps of text for incorporation in the VIS Meeting Minutes
KAGRA/Subgroups/VIS/MeetingNAOJ
Type B (Mark)
Report for week of 1/15
- We set up the QPD for the OL, initialized the OL and TM sections of the RTM, and did TFs from the TM OSEMs to the OL.
- Initially we had no coherence, but we debugged issues with the watchdog, LPCD, and DAC board and then got good TFs.
- We lifted the IM/RM/SR with the load gauge adapter and checked the weight, which was close to the mass budget.
- We installed the section of the AF above the IM, and the BF cross bars and jacks, and craned in the BF.
- We installed the BF-IRM rods, IRM, BF-IM rod, flying saucer and the cable clamps on the bottom of the BF.
- We hooked the IM section, but found it was heavy by several hundred grams. We also noticed the BF keystone had a noticeable tilt of about 1.2 mm (high on the +X side).
- We removed 738 g of trim mass and found that load rose and sat about 2 mm high. So the discrepancy is of order 500-600 g.
- Shoda-san, Enzo and Kozu-kun made and characterized a batch of OSEMs.
- Hirata-san finished drawings for the improved BS PI yaw/vertical adjustment, placed orders for damping ring receptacles and other items, and prepared the second SR BF in case we needed to swap it in.
Plan for week of 1/22
- Fix or swap BF.
- Route selected cables to flange.
- Test IM picos and BF yaw pico.
Plan for week of 1/29
- Enzo at Mitaka 1/29 and most of 1/30, then vacation.
- Kozu-kun away.
- All others at Kamioka.
- Build IRM around IM.
- Cable/test/adjust IM OSEMs.
- Time permitting, do TFs from IM OSEMs to themselves and to optical sensor.
Vacation Info
- Enzo 1/30-2/19 (at Mitaka 1/29, part of 1/30)
- Kozu-kun 1/29-2/2